Road 3.5 project: Land plot located in 2 communes and wards, different compensation prices

SÓNG HỮU |

Hanoi - Land acquisition for the Ring Road 3.5 project, Thuong Cat bridge section - National Highway 32, still faces some difficulties.

The project to invest in the construction of Ring Road 3.5 section from Thuong Cat bridge to National Highway 32 is a group B project, a special-grade project. Total length 3.5km, cross-section 60m.

The starting point of the project is at the intersection with the current Ky Vu road; the ending point is at the intersection with National Highway 32.

The project has a total investment of about 1,495 billion VND (construction cost of 683.853 billion VND); project implementation time from 2023 - 2026.

Regarding site clearance (GPMB), the Hanoi Traffic Construction Investment Project Management Board (the investor) said that the area to be GPMB is 29.236ha/657 options (Thuong Cat ward: 6.016 ha/215 options; Tay Tuu ward: 13.68ha/230 options; O Dien commune: 5.45 ha/160 options; Hoai Duc commune: 4.09 ha/52 options); relocating 160 graves in Tay Tuu ward.

People's Committees of communes and wards strive to complete site clearance before June 30, 2026.

Up to now, Tay Tuu ward has issued notices of land recovery for 206 households. 85/218 agricultural land plans have been investigated; 0/12 residential land (related to the collective housing area of Construction Company 695 - Ministry of National Defense/78m2/8 cases of land use; existing residential area (TDP Thuong 2)/344m2/4 cases of land use).

Regarding tomb relocation, 157/160 graves have been identified; 160/160 graves have been investigated and counted (3 graves have not been identified as relatives). 150/160 graves have been relocated; 81 plans have been approved.

Thuong Cat ward has issued 166/229 land acquisition notices.

O Dien wards and Hoai Duc commune are completing dossiers to serve the appraisal of land clearance maps.

Regarding the underground and above ground relocation work, the survey and inventory have been completed; dossiers are being completed and submitted for appraisal.

Regarding construction work, the investor said that it has only just received the handover of the public land area (traffic road land, about 10,203m2 of Tay Thang Long intersection in Tay Tuu ward, Thuong Cat ward). The received land area is only enough to cast concrete components and install shacks.

On the land area that has been handed over, there is currently a road construction contractor casting precast components - technical trenches. The bridge construction contractor is preparing to cast girders...

Currently, the project still has some difficulties and obstacles. The main difficulties are the site clearance of the project with a large volume in Thuong Cat, Tay Tuu wards, O Dien and Hoai Duc communes.

The nature of intertwined administrative boundaries after the merger of the two-level government (some land plots are located on the old administrative boundaries of two or three communes/wards). Currently, the work of planting markers for determination in the field has not been carried out, making it very difficult for units directly implementing land recovery and compensation, support, and resettlement.

Land ownership work is facing difficulties because households within the site clearance boundary of the project are carrying out purchase and sale, transfer or no longer cultivate.

The land compensation unit price has a difference when one land plot is located in two communes and wards.

The Hanoi Traffic Construction Investment Project Management Board requests the People's Committees of Thuong Cat, Tay Tuu wards, O Dien and Hoai Duc communes to pay attention to coordinating with the investor to accelerate land recovery and site clearance to construct project items.

SÓNG HỮU
RELATED NEWS

Household leases land to companies for wrong purposes, authorities intervene to handle

|

Hanoi - Chuong My Ward determines that a mobile information station installed on agricultural land is not for the right land use purpose, requesting dismantling before April 16.

Thuong Cat Bridge will relieve traffic pressure in the capital

|

On October 10, Hanoi will start construction of Thuong Cat bridge and the road at both ends of the bridge. When completed, the project will contribute to relieving traffic pressure in the capital.

Hanoi Chairman: From now until the end of the year, the construction of Thuong Cat Bridge and Tran Hung Dao Bridge will start

|

Chairman of Hanoi People's Committee Tran Sy Thanh said that from now until the end of the year, the construction of Thuong Cat Bridge and Tran Hung Dao Bridge will begin.

Cong Hien 2026" Award: Dinh Bac wins the Young Sports Face award

|

The 2026 Cong Hien Awards ceremony named typical individuals and collectives of Vietnamese sports in the past year, recognizing the journey of effort and breakthrough.

Teacher punishes violating student by holding a syringe and injecting it into his hand

|

Ho Chi Minh City - On April 15, a case of a teacher punishing a student for violating regulations by holding a syringe and injecting it into his hand was stirred up online.

Ho Chi Minh City adds new administrative procedures for motorbike emission inspection

|

Ho Chi Minh City has just supplemented administrative procedures for motorbike emission testing, preparing for the implementation roadmap from July 1, 2027 with a scale of more than 11 million vehicles.

Inadequate planning, difficult to handle the situation of overlapping Tam Dao National Park

|

Prolonged inadequacies in planning, overlapping between Tam Dao National Park and people's land have caused difficulties for management.

Pension proposed to be increased to 3.8 million VND/month for people retiring before 1995

|

The Ministry of Home Affairs proposes to increase the pension level to 3.8 million VND/month for low-income beneficiaries after adjustment, in order to ensure the minimum living standard.

Household leases land to companies for wrong purposes, authorities intervene to handle

SÓNG HỮU |

Hanoi - Chuong My Ward determines that a mobile information station installed on agricultural land is not for the right land use purpose, requesting dismantling before April 16.

Chốt thời điểm giao đủ mặt bằng làm đường nối cầu Thượng Cát - Quốc lộ 32

SÓNG HỮU |

Hà Nội - Dự kiến, công tác giải phóng mặt bằng để xây dựng đường Vành đai 3,5 đoạn từ cầu Thượng Cát đến Quốc lộ 32 sẽ hoàn thành trong tháng 6.2026.

Thuong Cat Bridge will relieve traffic pressure in the capital

Minh Hạnh |

On October 10, Hanoi will start construction of Thuong Cat bridge and the road at both ends of the bridge. When completed, the project will contribute to relieving traffic pressure in the capital.

Hanoi Chairman: From now until the end of the year, the construction of Thuong Cat Bridge and Tran Hung Dao Bridge will start

Anh Tuấn |

Chairman of Hanoi People's Committee Tran Sy Thanh said that from now until the end of the year, the construction of Thuong Cat Bridge and Tran Hung Dao Bridge will begin.