7 communes and towns of Long Thanh district handed over 100% of the ground to build highways

HÀ ANH CHIẾN |

Dong Nai - Up to now, 7/9 communes and towns in Long Thanh district have handed over 100% of the ground to the Bien Hoa - Vung Tau Expressway Project.

On April 13, information from the People's Committee of Long Thanh District said that up to now, there have been 7/9 communes and towns to complete the liberation of 100% of the Bien Hoa - Vung Tau highway project, including the communes: Phuoc Binh, An Phuoc, Phuoc Thai, Long Phuoc, Tan Hiep, Loc An and Long Thanh town.

For Long An commune, the part of component sub -project has completed 100% of the ground liberation; The sub -project section of component 2 has 3 cases without handing over the ground and Long Duc commune has 242 cases without handing over the ground.

Bien Hoa - Vung Tau Expressway Project section through Long Thanh district has a length of about 28km, the total area to be recovered nearly 228 hectares.

Up to now, the district has handed over 224.4 ha, reaching 98.5%. In particular, the sub -project of component 1 handed over the ground was 95.5%, the component sub -project 2 handed over the ground reached 99.9%.

The district has also issued a plan to be completed before April 15. Through propaganda and advocacy, many households have agreed to hand over the ground before proceeding to enforce.

HÀ ANH CHIẾN
RELATED NEWS

Land recovery for the Bien Hoa Vung Tau expressway project through Long Thanh district has reached more than 97%

|

Dong Nai - Long Thanh District mobilized the handover of more than 222 hectares of land, reaching a rate of more than 97% of the reclaimed land area of the Bien Hoa - Vung Tau expressway project.

Reviewing and handling contractors behind schedule on Bien Hoa - Vung Tau Expressway

|

The Bien Hoa - Vung Tau Expressway section through Ba Ria - Vung Tau is expected to open to traffic on April 30. Meanwhile, the section through Dong Nai has not yet completed site clearance. The province is currently racing to complete the embankment before June 30 according to the schedule assigned by the Government.

New direction of the Prime Minister on Bien Hoa - Vung Tau Expressway

|

The Government Office has just announced the direction and operation of the Prime Minister on March 28, 2025, including the direction at the Bien Hoa - Vung Tau Expressway Project.

Ms. Ha Thi Nga was introduced to hold the position of Vice Chairwoman - Secretary General of the Central Committee of the Vietnam Fatherland Front

|

Ms. Ha Thi Nga was introduced and submitted for consultation and election to hold the position of Vice Chairwoman - Secretary General of the Central Committee of the Vietnam Fatherland Front, term X.

The 14th Party Congress must be guaranteed absolute security and safety

|

Standing Secretary of the Secretariat Tran Cam Tu emphasized the requirement to ensure absolute security and safety for the 14th Party Congress.

Ha Long Canned Food store doors are closed, locked

|

Hai Phong - Many days after the Ha Long Canned Food scandal, the products of this brand continue to be absent from supermarkets and convenience stores in Hai Phong.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Scene of the accident that killed 4 people on the highway section through Thanh Hoa

|

Thanh Hoa - Through the scene of the accident that killed 4 people and injured many others on the highway, it can be seen that the vehicles collided with each other very strongly.

US warns Iran will pay a heavy price for suppressing protests by force

|

US President Donald Trump warned that Iran would pay a heavy price if it continued to suppress protests by force, and declared readiness to support the Iranian people.

Land recovery for the Bien Hoa Vung Tau expressway project through Long Thanh district has reached more than 97%

HÀ ANH CHIẾN |

Dong Nai - Long Thanh District mobilized the handover of more than 222 hectares of land, reaching a rate of more than 97% of the reclaimed land area of the Bien Hoa - Vung Tau expressway project.

Reviewing and handling contractors behind schedule on Bien Hoa - Vung Tau Expressway

HÀ ANH CHIẾN |

The Bien Hoa - Vung Tau Expressway section through Ba Ria - Vung Tau is expected to open to traffic on April 30. Meanwhile, the section through Dong Nai has not yet completed site clearance. The province is currently racing to complete the embankment before June 30 according to the schedule assigned by the Government.

New direction of the Prime Minister on Bien Hoa - Vung Tau Expressway

Xuyên Đông |

The Government Office has just announced the direction and operation of the Prime Minister on March 28, 2025, including the direction at the Bien Hoa - Vung Tau Expressway Project.