On April 13, information from the People's Committee of Long Thanh District said that up to now, there have been 7/9 communes and towns to complete the liberation of 100% of the Bien Hoa - Vung Tau highway project, including the communes: Phuoc Binh, An Phuoc, Phuoc Thai, Long Phuoc, Tan Hiep, Loc An and Long Thanh town.
For Long An commune, the part of component sub -project has completed 100% of the ground liberation; The sub -project section of component 2 has 3 cases without handing over the ground and Long Duc commune has 242 cases without handing over the ground.
Bien Hoa - Vung Tau Expressway Project section through Long Thanh district has a length of about 28km, the total area to be recovered nearly 228 hectares.
Up to now, the district has handed over 224.4 ha, reaching 98.5%. In particular, the sub -project of component 1 handed over the ground was 95.5%, the component sub -project 2 handed over the ground reached 99.9%.
The district has also issued a plan to be completed before April 15. Through propaganda and advocacy, many households have agreed to hand over the ground before proceeding to enforce.