People complain about last minute change of coastal road

Hữu Long |

Khanh Hoa - People complained about the change in route direction when marking the coastal road with capital of more than 2,000 billion VND, affecting their lives.

Route change but people don't know

Mr. Tran Thanh Doan (born in 1956, residing in Xuan Tu 1 village, Van Hung commune, Van Ninh district) has more than 2,000 square meters of land recovered by the state to implement the Coastal Road Project from Van Luong commune, Van Ninh district to Ninh Hoa town.

Du an Tuyen duong ven bien tu xa Van Luong, huyen Van Ninh di thi xa Ninh Hoa co chieu dai 20km, von 2.031 ti dong, thuc hien trong giai doan 2024 - 2027.

In mid-2024, the Van Phong Economic Zone Management Board and the locality held a meeting to agree on the content of marking the route.

The initial plan for local locations was to adjust the route to the East to avoid affecting people and reduce land clearance costs. The East direction has few houses, mainly aquaculture land.

Around July 2024, people encountered some strangers who arbitrarily changed the location of the border post. Instead of the border post being outside the pond, the border post was now facing many houses.

The change of the new milestone did not take into account and has not received the consensus of some people.

According to Mr. Tran Thanh Doan, people support the Party and State's policy in implementing the project. However, the implementation must be in accordance with regulations, limiting the impact on people's lives.

Ong Tran Thanh Doan - dai dien khoang 10 ho dan, khieu nai viec thay doi huong tuyen duong ven bien. Anh: Huu Long
Mr. Tran Thanh Doan - representative of about 10 households, complained about the change in direction of the coastal road. Photo: Huu Long

The wish of the people in Xuan Tu 1 village is that the investor should keep the original road milestone - towards the aquaculture pond.

There are mistakes and errors so re-mark them.

In September 2024, Mr. Vuong Xuan Phuong - Deputy Head of Van Phong Economic Zone Management Board responded to the people's petition in writing.

Huong tuyen ban dau (mau do) va sau do duoc duoc thay doi, dieu chinh (mau xanh dam). Anh: Huu Long
The original route (red) and then changed and adjusted (dark blue). Photo: Huu Long

Mr. Vuong Xuan Phuong explained that after Khanh Hoa Provincial People's Committee accepted the project's route and site clearance boundary plan, the consulting unit proceeded to set up site clearance boundary markers.

However, when marking Area K18 in Xuan Tu 1 village, there was a mistake, so the consulting unit re-marked according to the approved design documents.

"Thereby, the Management Board of Van Phong Economic Zone has also promptly directed, corrected and seriously drawn comprehensive lessons from the unnecessary mistakes and misunderstandings as reported in the petition" - quoted from the response signed by Mr. Vuong Xuan Phuong.

At the regular press conference in October 2024, Mr. Le Hong Phuong - Deputy Head of Van Phong Economic Zone Management Board said that during the project implementation process, the investor must carry out 2 steps: pre-feasibility and feasibility. For the pre-feasibility step, when compared with the planning of Van Phong Economic Zone, some locations will adjust the benchmark to ensure technicality.

“To speed up the progress, we transferred the information about the feasible route to Van Ninh district for preliminary marking. Therefore, afterwards, people also had questions…” - Mr. Le Hong Phuong said.

Ong Le Hong Phuong tai buoi hop bao, phan hoi noi dung khieu nai cua nguoi dan. Anh: Huu Long
Mr. Le Hong Phuong at the press conference, responding to the people's complaints. Photo: Huu Long

During the consultation process, the people gave feedback and the investor accepted it. Specifically, according to the feasible front line of the project, it will affect 41 households. After that, the investor and the locality reviewed and adjusted it to present the feasible step. This received consensus from the people but there were also some disagreements.

Mr. Le Hong Phuong stated that the land recovery will be carried out by the investor in accordance with regulations on recovery, resettlement arrangement, and ensuring people's rights.

Currently, the Management Board of Van Phong Economic Zone has reported to the Ministry of Construction on the basic design of this project. It is expected that in the fourth quarter of 2024, the investor will organize a bidding to implement the project.

Hữu Long
RELATED NEWS

Stocks maintain recovery momentum

|

The focus of this week's stock market will be the mid-term assessment of market upgrades by FTSE Russell, a catalyst that opens up new waves of increase.

Stone mine "suspended" for 9 months, Gia Lai warns to replace commune leaders

|

Gia Lai - Although licensed, a quarry is still "suspended" for 9 months due to land lease procedures at the commune level.

Hanoi Industrial Meal Company won 148/148 bidding packages, with a total value of 505.8 billion VND

|

Hanoi Industrial Meal Service Joint Stock Company participated and won all 148 bidding packages to supply meals at schools in Hanoi and some northern provinces.

Teachers of Song Hong school nearly 20 months without salary, Phu Tho Department of Home Affairs speaks out

|

Phu Tho - Regarding the case of teachers of Song Hong Intermediate School who have not received salary for nearly 20 months, the Phu Tho Department of Home Affairs has spoken out.

400 billion VND for reconstruction, emergency traffic projects in Da Nang are still messy

|

Da Nang - After more than 4 years of construction, the nearly 400 billion VND emergency traffic project in the mountainous disaster area is still unfinished, bumpy as if it has never been rebuilt.

Day and night construction at the construction site of the widest cable-stayed bridge project in Hai Phong

|

Hai Phong - To date, the construction of the nearly 1,500m long cable-stayed main bridge under the Nguyen Trai bridge project has reached about 32% of the progress, striving to reach the finish line in September 2027.

Today the National Assembly considers and decides on personnel and organizational structure

|

According to the Session program, today April 6, the First Session of the 16th National Assembly officially opens.

Continue to find land to build Khanh Hoa Provincial Museum

Hữu Long |

Khanh Hoa - The locality does not agree with the policy of building a museum on the coastal land of Nha Trang and directs to continue finding suitable land.

Checking the case of "unclean" land being auctioned in Khanh Hoa

Hữu Long |

Khanh Hoa - The locality will inspect the case of "unclean" land but the commune organized an auction, causing people to win the land auction but not receive it.

Dân khiếu nại vụ đất “chưa sạch” mang đi đấu giá ở Khánh Hòa

Hữu Long |

Khánh Hòa - Một người dân trúng đấu giá 5 thửa đất nhưng không được bàn giao. Đáng nói là các thửa đất “chưa sạch” nhưng xã vẫn đấu giá.