People complain about last minute change of coastal road

Hữu Long |

Khanh Hoa - People complained about the change in route direction when marking the coastal road with capital of more than 2,000 billion VND, affecting their lives.

Route change but people don't know

Mr. Tran Thanh Doan (born in 1956, residing in Xuan Tu 1 village, Van Hung commune, Van Ninh district) has more than 2,000 square meters of land recovered by the state to implement the Coastal Road Project from Van Luong commune, Van Ninh district to Ninh Hoa town.

Du an Tuyen duong ven bien tu xa Van Luong, huyen Van Ninh di thi xa Ninh Hoa co chieu dai 20km, von 2.031 ti dong, thuc hien trong giai doan 2024 - 2027.

In mid-2024, the Van Phong Economic Zone Management Board and the locality held a meeting to agree on the content of marking the route.

The initial plan for local locations was to adjust the route to the East to avoid affecting people and reduce land clearance costs. The East direction has few houses, mainly aquaculture land.

Around July 2024, people encountered some strangers who arbitrarily changed the location of the border post. Instead of the border post being outside the pond, the border post was now facing many houses.

The change of the new milestone did not take into account and has not received the consensus of some people.

According to Mr. Tran Thanh Doan, people support the Party and State's policy in implementing the project. However, the implementation must be in accordance with regulations, limiting the impact on people's lives.

Ong Tran Thanh Doan - dai dien khoang 10 ho dan, khieu nai viec thay doi huong tuyen duong ven bien. Anh: Huu Long
Mr. Tran Thanh Doan - representative of about 10 households, complained about the change in direction of the coastal road. Photo: Huu Long

The wish of the people in Xuan Tu 1 village is that the investor should keep the original road milestone - towards the aquaculture pond.

There are mistakes and errors so re-mark them.

In September 2024, Mr. Vuong Xuan Phuong - Deputy Head of Van Phong Economic Zone Management Board responded to the people's petition in writing.

Huong tuyen ban dau (mau do) va sau do duoc duoc thay doi, dieu chinh (mau xanh dam). Anh: Huu Long
The original route (red) and then changed and adjusted (dark blue). Photo: Huu Long

Mr. Vuong Xuan Phuong explained that after Khanh Hoa Provincial People's Committee accepted the project's route and site clearance boundary plan, the consulting unit proceeded to set up site clearance boundary markers.

However, when marking Area K18 in Xuan Tu 1 village, there was a mistake, so the consulting unit re-marked according to the approved design documents.

"Thereby, the Management Board of Van Phong Economic Zone has also promptly directed, corrected and seriously drawn comprehensive lessons from the unnecessary mistakes and misunderstandings as reported in the petition" - quoted from the response signed by Mr. Vuong Xuan Phuong.

At the regular press conference in October 2024, Mr. Le Hong Phuong - Deputy Head of Van Phong Economic Zone Management Board said that during the project implementation process, the investor must carry out 2 steps: pre-feasibility and feasibility. For the pre-feasibility step, when compared with the planning of Van Phong Economic Zone, some locations will adjust the benchmark to ensure technicality.

“To speed up the progress, we transferred the information about the feasible route to Van Ninh district for preliminary marking. Therefore, afterwards, people also had questions…” - Mr. Le Hong Phuong said.

Ong Le Hong Phuong tai buoi hop bao, phan hoi noi dung khieu nai cua nguoi dan. Anh: Huu Long
Mr. Le Hong Phuong at the press conference, responding to the people's complaints. Photo: Huu Long

During the consultation process, the people gave feedback and the investor accepted it. Specifically, according to the feasible front line of the project, it will affect 41 households. After that, the investor and the locality reviewed and adjusted it to present the feasible step. This received consensus from the people but there were also some disagreements.

Mr. Le Hong Phuong stated that the land recovery will be carried out by the investor in accordance with regulations on recovery, resettlement arrangement, and ensuring people's rights.

Currently, the Management Board of Van Phong Economic Zone has reported to the Ministry of Construction on the basic design of this project. It is expected that in the fourth quarter of 2024, the investor will organize a bidding to implement the project.

Hữu Long
RELATED NEWS

7th Conference of the Presidium of the Central Committee of the Vietnam Fatherland Front, X term

|

On the morning of April 12, the Central Committee of the Vietnam Fatherland Front organized the 7th Conference of the Presidium of the Central Committee of the Vietnam Fatherland Front, term X to discuss and give opinions on some work contents.

Ambulance and pickup truck collide in a crossroads in Phu Tho

|

Phu Tho - On the evening of April 11, at the intersection of Nguyen Tat Thanh street and Truong Chinh street (Van Phu ward), a traffic accident occurred between an ambulance and a pickup truck.

Hormuz opens its door, 3 super ships carrying 6 million barrels of oil head to Asia

|

Oil flows through the Strait of Hormuz are stirring again as 3 supercarriers capable of carrying up to 6 million barrels leave the Persian Gulf on April 11.

World gold prices fluctuate sharply, reversing direction

|

Gold prices fell to around 4,731 USD per ounce as investors became cautious again in the face of the risk of the US and Iran ceasefire breaking down.

Businesses in Hanoi reward money and attract new workers

|

In the context of increasing recruitment demand in industrial parks, many businesses in Hanoi are promoting bonus policies for new workers.

Music festival with a scale of 50,000 spectators opens the National Radio Festival in Quang Ninh

|

Quang Ninh - The "New Era Sounds" music festival with a scale of about 50,000 spectators took place on the evening of April 11, during the Opening Ceremony of the National Radio Festival.

Continue to find land to build Khanh Hoa Provincial Museum

Hữu Long |

Khanh Hoa - The locality does not agree with the policy of building a museum on the coastal land of Nha Trang and directs to continue finding suitable land.

Checking the case of "unclean" land being auctioned in Khanh Hoa

Hữu Long |

Khanh Hoa - The locality will inspect the case of "unclean" land but the commune organized an auction, causing people to win the land auction but not receive it.

Dân khiếu nại vụ đất “chưa sạch” mang đi đấu giá ở Khánh Hòa

Hữu Long |

Khánh Hòa - Một người dân trúng đấu giá 5 thửa đất nhưng không được bàn giao. Đáng nói là các thửa đất “chưa sạch” nhưng xã vẫn đấu giá.