Hon Rom Golf Course project in Lam Dong is 13 years behind schedule, owes 17.5 billion in land rent

Duy Tuấn |

Lam Dong - The Hon Rom Golf Course project has been behind schedule for more than 13 years, with many problems with land, construction and a debt of 17.5 billion VND in land rent.

On December 2, information from Lam Dong Provincial Inspectorate said that the unit had publicly announced the conclusion of the thematic inspection of the Hon Rom Golf Course Project in Mui Ne Ward.

The project is invested by S.I Development Company Limited, granted an investment certificate since 2007 with a scale of nearly 197 hectares, with a total capital of more than 548 billion VND.

According to the conclusion, by the time of inspection, the project had been behind schedule for more than 13 years. The company did not carry out the investment certificate adjustment procedures when the 138ha area (pre-termly allocated) was recovered to be handed over to another unit for mineral exploitation.

Loi vao Du an San Golf Hon Rom. Anh: Duy Tuan
Entrance to Hon Rom Golf Course Project. Photo: Duy Tuan

Regarding land, the inspectorate pointed out that the Department of Natural Resources and Environment (formerly) advised the People's Committee of Binh Thuan province (before the merger) to lease 322,210m2 of land that did not meet land use needs.

The permission to change the purpose of 25,828.5m2 from production and business land to urban residential land was also determined to be not in accordance with the planning. After that, the project returned to its original purpose in 2022.

Regarding construction, S.I Development Company Limited constructed many items without a license. The People's Committee of Mui Ne Ward was held responsible for allowing illegal construction and not checking for a long time.

The enterprise still owes 17.5 billion VND in land rent, not meeting its obligations under the law.

Mot khu vuc ben trong du an. Anh: Duy Tuan
An area inside the project. Photo: Duy Tuan

To remove difficulties and obstacles, create conditions for S.I Development Joint Stock Company and attract investment, the Provincial Inspectorate recommended that the Provincial People's Committee consider and propose to the Central Government to allow businesses to continue implementing the project in accordance with legal procedures and order.

If approved, the Department of Finance must guide investors to adjust the project; review and evaluate the feasibility of the project and the investor's resources.

The Department of Agriculture and Environment comprehensively re-evaluates the land use needs of the project. Lam Dong Provincial Tax Department urges companies to pay VND 17.5 billion in land rent,

At the same time, departments and People's Committees of Mui Ne Ward must review responsibilities for each violation. Investors are required to quickly fulfill financial obligations, make legal adjustments and ensure progress when continuing implementation.

Investors are required to quickly fulfill financial obligations, make legal adjustments and ensure progress when continuing implementation.

Duy Tuấn
RELATED NEWS

sentosa Villa project in Lam Dong is more than 11 years behind schedule, facing many violations

|

Lam Dong - The Provincial Inspectorate pointed out a series of problems related to land, construction and real estate business at sentosa Villa project.

Inspectorate points out a series of problems in the La Gi residential and commercial area encroachment project

|

Lam Dong - Many problems with land, planning and real estate business at the La Gi New Residential - Trade - Service Area Encroachment Project.

Inspectorate points out violations in the Trang An eco-tourism area infrastructure construction project

|

The Government Inspectorate pointed out limitations, shortcomings, and violations in the Trang An eco-tourism area infrastructure construction project.

Soldiers return to the village, rebuild houses with people after the fierce flood in Dak Lak

|

Dak Lak - After the fierce flood, people in Hoa Thinh commune are gradually stabilizing their lives, repairing their houses and restoring production with the timely support of the army.

Opening the way for freelance workers to buy social housing using the post-inspection mechanism

|

The difficulty in proving income makes it almost impossible for freelance workers to access social housing. Experts propose stepping up post-inspections to remove this bottleneck.

volatility of Southeast Asian billionaire, Mr. Pham Nhat Vuong approaches 2nd place

|

Mr. Pham Nhat Vuong is narrowing the gap with billionaire Low Tuck Kwong, likely to rise to 2nd place in Southeast Asia.

AI sings Trinh's rock style and the worry about his real voice being overwhelmed

|

Artificial intelligence stirred up music with AI singing Trinh's music in rock style, AI singing ancient music and impersonating real artists.

Storm No. 15 weakens, the new storm in early December is weakening

|

As Typhoon No. 15 Koto has weakened, a new low pressure is likely to strengthen into Typhoon Wilma in early December.

sentosa Villa project in Lam Dong is more than 11 years behind schedule, facing many violations

Duy Tuấn |

Lam Dong - The Provincial Inspectorate pointed out a series of problems related to land, construction and real estate business at sentosa Villa project.

Inspectorate points out a series of problems in the La Gi residential and commercial area encroachment project

Duy Tuấn |

Lam Dong - Many problems with land, planning and real estate business at the La Gi New Residential - Trade - Service Area Encroachment Project.

Inspectorate points out violations in the Trang An eco-tourism area infrastructure construction project

TRÍ MINH |

The Government Inspectorate pointed out limitations, shortcomings, and violations in the Trang An eco-tourism area infrastructure construction project.