Nearly 4,000 billion VND for resettlement to build Gia Nghia - Chon Thanh Expressway

ĐÌNH TRỌNG |

Binh Phuoc - The Provincial People's Committee is calculating to build 6 resettlement areas for people when clearing land to build the Gia Nghia - Chon Thanh expressway.

On March 13, the People's Committee of Binh Phuoc province held a meeting to review the progress of component project 5 on site clearance, resettlement and related work of the Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) expressway project.

Currently, Binh Phuoc province is urgently implementing issues related to technical infrastructure to invest in the construction of 6 resettlement areas.

Resettlement areas for people whose land has been cleared to build expressways will be built in 4 districts, towns and cities: Dong Xoai, Chon Thanh, Bu Dang and Dong Phu district. The total estimated investment for resettlement areas is nearly 4,000 billion VND.

Cuoc hop
Meeting to deploy component project 5 on site clearance, resettlement and related work for the Gia Nghia - Chon Thanh expressway project. Photo: Nhu Nam

Ms. Tran Tue Hien - Chairman of Binh Phuoc Provincial People's Committee requested localities where the project passes through to focus on mass mobilization work, creating high consensus and unity among the people. At the same time, it is recommended that departments and branches join hands to coordinate with localities to focus on solving all difficulties and problems. Timely remove bottlenecks in implementing assigned tasks.

Currently, Binh Phuoc province is stepping up to implement component project 1 of the project, complete the feasibility study report, deploy the design, select a construction contractor and procedures to be able to start construction in 2025.

Tuyen cao toc di qua dia ban tinh Binh Phuoc 100km. Anh: Dinh Trong
The expressway passing through Binh Phuoc province is more than 100km long. Photo: Dinh Trong

The Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) expressway project is 128.8km long, with a design of 4 lanes. Of which, the section through Dak Nong province will be implemented with 27.8km, through Binh Phuoc with more than 100km. The total investment of the project is 25,500 billion VND. Of which, the central budget is 10,500 billion VND; the provincial budget is 1,200 billion VND; Dak Nong is 1,000 billion VND. The project is expected to be completed by the end of 2026 and put into operation in 2027.

ĐÌNH TRỌNG
TIN LIÊN QUAN

Speeding up the construction of Gia Nghia - Chon Thanh Expressway

|

Dak Nong - Gia Nghia - Chon Thanh expressway project is expected to start construction in September 2025.

Removing obstacles for Gia Nghia - Chon Thanh expressway project

|

Dak Nong - The locality is focusing on removing obstacles and implementing the Gia Nghia - Chon Thanh expressway project on schedule.

Finalized time for Gia Nghia – Chon Thanh expressway construction

|

Dak Nong - It is expected that by September 2025 at the latest, the Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) expressway project will start construction.

Opening a road to take a stroke driver on the highway to the hospital for emergency care

|

Discovering Hoang Viet Nam driver unconscious in the cabin on the Phap Van - Cau Gie Expressway, traffic police cleared the way to take the victim to the emergency room.

Cave of clouds floating like a fairyland on the Dong Van stone plateau

|

Tuyen Quang - Hang May Gate in Dong Van has a giant lotus bud shape, leading to a world of stone jars hidden in the magical mist of clouds.

More than 3 points/subject for admission to many public high schools in Hanoi

|

Many public high schools in Hanoi have very low benchmark scores, students only need to achieve an average of 3 points/subject that they have been admitted to.

GDP in the first 6 months of the year increased by 7.52%, highest in the period 2011-2025

|

GDP in the first 6 months of 2025 increased by 7.52% over the same period last year, the highest level in the first six months of the year in the period 2011-2025.

The career of Vietnamese actors owning National Treasures before retiring

|

Vietnamese actors own National Treasures with a huge film fortune.

Speeding up the construction of Gia Nghia - Chon Thanh Expressway

PHAN TUẤN |

Dak Nong - Gia Nghia - Chon Thanh expressway project is expected to start construction in September 2025.

Removing obstacles for Gia Nghia - Chon Thanh expressway project

THANH QUỲNH |

Dak Nong - The locality is focusing on removing obstacles and implementing the Gia Nghia - Chon Thanh expressway project on schedule.

Finalized time for Gia Nghia – Chon Thanh expressway construction

THANH QUỲNH |

Dak Nong - It is expected that by September 2025 at the latest, the Gia Nghia (Dak Nong) - Chon Thanh (Binh Phuoc) expressway project will start construction.