Disburse about VND2,400 billion to compensate for the construction site of Ho Chi Minh City Ring Road 4 through the old Binh Duong

ĐÌNH TRỌNG |

HCMC - The units have disbursed compensation of about VND 2,400 billion for site clearance to build the Ho Chi Minh City Ring Road 4 project, the section passing through the old Binh Duong area.

On December 6, the Land Fund Development Center is coordinating with 10 communes and wards to speed up the implementation of the component project of site clearance for Ho Chi Minh City Ring Road 4, the section passing through the old Binh Duong area. This is one of the important transport infrastructure projects connecting Ho Chi Minh City with neighboring provinces. The project has been under construction since June 2025.

The project's site clearance is 27.83 km long and has some intersection locations. The area of recovered land is 250.46 ha. The project affects 1,598 households, individuals and organizations. It is expected that 300 cases will be resettled.

The project passes through the wards of Tay Nam, Long Nguyen, Thoi Hoa, Hoa Loi, Binh Duong, Vinh Tan, Binh Co, Tan Uyen and Bac Tan Uyen commune, Thuong Tan commune.

Currently, the units have issued a notice of land recovery to 100% of affected cases and completed the survey work. The work of appraising drawings has reached about 85% of the affected cases. About 1,500 cases were counted, reaching over 95%.

Cac don vi lien quan dang phoi hop voi cac dia phuong tang toc giai ngan den bu giai phong mat bang cho du an. Anh: Dinh Trong
The land that needs compensation for site clearance passes through Thoi Hoa ward. Photo: Dinh Trong

Localities have also completed the determination and approval of specific land prices.

Regarding disbursement, according to the Ho Chi Minh City People's Committee, the capital plan for allocating compensation and site clearance for the project in 2025 is 7,307 billion VND. By the end of November 2025, over 410 cases with compensation of over VND 2,400 billion had been approved and disbursed. The site has been handed over about 33 hectares.

Currently, the Land Fund Development Center is coordinating with localities where the project passes through to encourage people to agree to hand over the site. Thereby, speeding up the progress of compensation disbursement, receiving the handover of the site so that the construction unit has clean land to carry out the project.

Doan di qua khu do thi, cong nghiep My Phuoc da duoc dau tu 10 lan xe chay. Anh: Dinh Trong
The section passing through the urban and industrial area of My Phuoc has been invested with 10 lanes. Photo: Dinh Trong

The Ho Chi Minh City Ring Road 4 project has a total length of more than 200 km. The project has a total investment of more than 120,412 billion VND in phase 1. The project is invested to facilitate regional connectivity and improve the efficiency of exploitation of expressways, national highways, etc., connecting traffic between Long Thanh International Port and provinces and cities in the key economic region of the South.

Phoi canh du an duong Vanh dai 4 TPHCM. Anh: Dinh Trong
Perspective of the Ho Chi Minh City Ring Road 4 project. Photo: Dinh Trong

The section passing through the old Binh Duong area is 47.9 km long, the first section of the project is from Thu Bien bridge, Dong Nai river to Saigon river. This project section is implemented under the form of Construction - Business - Transfer (BOT), with a total investment of VND 11,743 billion. The investment scale of phase 1 includes 4 lanes and a continuous emergency lane, designed speed of 100km/h. The investor implementing the project is a joint venture of Becamex Group and Deo Ca Group Joint Stock Company.

ĐÌNH TRỌNG
RELATED NEWS

The progress of public investment disbursement has improved, but has only reached more than 60.6% of the plan

|

By November 30, 2025, public investment disbursement reached VND553,250 billion, equivalent to 60.6% of the plan assigned by the Prime Minister and higher than the same period last year.

Integrating 3 national target programs for faster disbursement

|

According to the 10th Session agenda, on December 5, the National Assembly will discuss in the hall the investment policy for the National Target Program on New Rural Areas, Sustainable Poverty Reduction, Socio-economic Development of Ethnic Minorities and Mountainous Areas until 2035. The goal is to integrate policies to improve implementation efficiency, while still maintaining the entire policy, subjects, and rights of the people.

Nghe An disburses public investment capital to only reach 44.71% of the plan

|

Nghe An - By the end of the year, the disbursement of public investment capital reached 44.71% of the plan, the Provincial People's Committee requested units to speed up and completely handle the backlog of projects.

Ukrainian President warns of new airstrikes

|

Ukraine faces a harsh winter as energy infrastructure is attacked and the risk of airstrikes reoccur.

Iran ready for war but opens negotiations with the US

|

Iran declares it does not want conflict but has prepared for a high-level war scenario, while still leaving open negotiations with the US.

Peeling leaves at the right time, Hai Phong peach growers wait for Tet flowers to bloom

|

Hai Phong - Currently, peach gardens in Tan Hung ward are entering the peak of peeling leaves, a key stage that determines the flowering time of the Tet crop.

Pension and social insurance allowance payment schedule: Changes people need to pay attention to

|

Vietnam Social Security guides the organization of pension and social insurance allowance payments for the February 2026 pension payment period, with noteworthy changes that people need to know.

It's a bit of a bit of a bit of a bit of a bit of a bit.

U23 Jordan arrives at hotel to celebrate with U23 Vietnam

|

After winning tickets to the U23 Asian Cup 2026 quarter-finals together, U23 Jordan went to the hotel where U23 Vietnam was stationed to celebrate together.

The progress of public investment disbursement has improved, but has only reached more than 60.6% of the plan

Lục Giang |

By November 30, 2025, public investment disbursement reached VND553,250 billion, equivalent to 60.6% of the plan assigned by the Prime Minister and higher than the same period last year.

Integrating 3 national target programs for faster disbursement

Bảo Trung |

According to the 10th Session agenda, on December 5, the National Assembly will discuss in the hall the investment policy for the National Target Program on New Rural Areas, Sustainable Poverty Reduction, Socio-economic Development of Ethnic Minorities and Mountainous Areas until 2035. The goal is to integrate policies to improve implementation efficiency, while still maintaining the entire policy, subjects, and rights of the people.

Nghe An disburses public investment capital to only reach 44.71% of the plan

QUANG ĐẠI |

Nghe An - By the end of the year, the disbursement of public investment capital reached 44.71% of the plan, the Provincial People's Committee requested units to speed up and completely handle the backlog of projects.