Hai Phong accelerates the progress of industrial clusters and urban clusters

Băng Tâm |

Hai Phong - On April 15, Hai Phong City leader chaired the meeting on the implementation of industrial clusters and urban areas in the city.

At the meeting, the city leaders heard the report on the implementation of industrial clusters that had decided to policy of investment and establishment decisions, including: Tien Cuong II, Dai Thang and Quang Phuc Industrial Cluster (Tien Lang District); Dung Tien - Giang Bien (Vinh Bao district); An Tho, Victory, Cam Van, Cua Hoat - Quan Thang (An Lao district); Thuy Nguyen Mechanical and Casting Village; Tan Trao (Kien Thuy district); Le Thien - headquarters, auxiliary industrial clusters (An Duong district). At the same time, reports on industrial clusters are being considered for decisions on investment policies and establishment.

Speaking at the meeting, Secretary of the City Party Committee Le Tien Chau suggested the City People's Committee, departments, branches and investors determined to speed up the implementation of industrial cluster projects in the city to soon have land fund to attract production facilities.

The Secretary of the City Party Committee assigned specific progress to each industrial cluster that had made investment decisions and establishment decisions. On that basis, the city clearly identifies responsibilities for each agency, unit and individual to slow progress. Local leaders tried in site clearance; Research and propose to complete the criteria to select investors.

For industrial clusters being considered for investment policies, units formulate plans, determine the priority order for industrial clusters, select competent investors. For projects of urban areas in the area, it is necessary to urgently review and focus on accelerating the progress.

The Secretary of the City Party Committee asked the City Party Committee to direct the inspection, examination and handling according to the regulations if the schedule is behind schedule; Investors also need to focus resources and maximum efforts to soon put the project into operation.

Băng Tâm
RELATED NEWS

Forced land acquisition for implementation of a new urban area project in Duong Kinh, Hai Phong

|

Hai Phong - On April 15, the People's Committee of Duong Kinh District (Hai Phong) organized a coercive land acquisition of 5 households to implement the investment project to build a new urban area.

Speeding up the transport project of more than 920 billion dong in Hai Phong

|

Hai Phong - The project of investing in construction of provincial road 354 through Kien Thuy industrial park to coastal road has reached 70% of progress.

The largest largest freshwater lake in Hai Phong

|

Hai Phong - Since Storm Yagi in 2024, the pearl freshwater reservoir (Hai Phong) has been eroded, degraded, affected by the supply of daily -life water for Cat Ba Island.

Cash flow returns to stocks, VN-Index increases sharply

|

Under the leadership of Vingroup and banking stocks, the stock market had a strong increase with excellent liquidity.

Earaches show how to protect health when air pollution

|

The North is in the period of air pollution, people need to proactively monitor air quality and adjust their daily activities to protect their health.

3 outstanding faces of Army sports at SEA Games 33

|

The Army Sports contributed many results to the final group of the Vietnam Sports Delegation at the 33rd SEA Games.

Many iPhones Suspected of being used for fraud were found near the Cambodian border

|

A backpack containing an iPhone and a Hong Kong sim card (China) was discovered at a sugar plantation, suspected of serving online fraud.

42 cases of food poisoning suspected to be caused by eating bread in Ho Chi Minh City

|

HCMC - Many people with severe abdominal pain due to food poisoning suspected to be from eating bread have gone to Ba Ria General Hospital for treatment.

Forced land acquisition for implementation of a new urban area project in Duong Kinh, Hai Phong

Hoàng Khôi |

Hai Phong - On April 15, the People's Committee of Duong Kinh District (Hai Phong) organized a coercive land acquisition of 5 households to implement the investment project to build a new urban area.

Speeding up the transport project of more than 920 billion dong in Hai Phong

Hoàng Khôi |

Hai Phong - The project of investing in construction of provincial road 354 through Kien Thuy industrial park to coastal road has reached 70% of progress.

The largest largest freshwater lake in Hai Phong

Mai Dung |

Hai Phong - Since Storm Yagi in 2024, the pearl freshwater reservoir (Hai Phong) has been eroded, degraded, affected by the supply of daily -life water for Cat Ba Island.