Phu Thuan Industrial Park has reached more than 60% of its volume

Thành Nhân |

Ben Tre - The total construction volume of 6 packages of the Phu Thuan Industrial Park project under construction has reached 60.5%.

According to Lao Dong Newspaper reporters at noon on October 9, hundreds of workers were working at the Phu Thuan Industrial Park project site (Binh Dai district, Ben Tre province).

Mr. Pham Thanh Phong - Deputy Head of Project Management Department 3 (Project Management Board for Investment and Construction of Civil and Industrial Works of Ben Tre Province) - said that currently, 6 construction packages of the Phu Thuan Industrial Park project are under construction.

"Specifically, the volume of roads N3, D1 and D3 (section from N3 to N4) reached 94.8% of the contract value. Up to now, the contractor has completed the asphalt concrete paving and is completing the installation of lighting, road painting and signs.

As for D2 traffic road, the volume has reached 81.9% of the contract value. The construction unit is currently paving the sidewalk, installing lighting, painting the road, and signs.

For N1 - N4 road, the volume reached 23.9% of the contract value, the contractor is installing stormwater drainage, completing sand pumping on the roadbed, and spreading graded stone on the roadbed" - Mr. Phong said.

According to Mr. Phong, currently, contractors are constructing the filling lots (B1, KT-T, KT-R) and the centralized wastewater treatment plant package, with a capacity of 4,500 m3/day and night, the volume reaching 1.8% of the contract value.

Cong nhan trien khai thi cong goi thau Tram xu ly nuoc thai tap trung trong du an khu cong nghiep Phu Thuan. Anh: Thanh Nhan
Workers deploy the construction of the Centralized Wastewater Treatment Plant package in the Phu Thuan Industrial Park project. Photo: Thanh Nhan

Mr. Bui Van Hiep - Director of the Project Management Board for Investment and Construction of Civil and Industrial Works of Ben Tre Province - said that the People's Committee of Ben Tre Province has approved the contractor selection plan for 11 construction packages of the Phu Thuan Industrial Park project. Of which, 6 packages are being implemented, the total construction volume of these 6 packages is 60.5%.

"The 2 bidding packages for traffic routes N2-D1-D3 (N1-N4) and the filling of lots, drainage ditches and trees have been opened for bidding and are evaluating bidding documents. The filling package is expected to be implemented in October 2024. The remaining 3 bidding packages (including: Transformer station; Fence of the entire area, guard house; 2 filling lots adjacent to Cua Dai river bank) are scheduled to select contractors in the first quarter of 2025 before bidding is organized," said Mr. Hiep.

The Phu Thuan Industrial Park project has a total investment of more than 3,539 billion VND, invested by the Ben Tre Province Civil and Industrial Construction Investment Project Management Board. Of which, the provincial budget is more than 3,443 billion VND, the remaining from non-budgetary sources is more than 96.3 billion VND. The project implementation period is from 2017-2025, the construction site is in Phu Thuan and Long Dinh communes (Binh Dai district, Ben Tre province).

Thành Nhân
RELATED NEWS

Teachers in the highlands of Quang Ngai wade through dozens of landslides to get to school

|

Quang Ngai - The rain and floods have separated, the roads have landslides, many teachers still wade through dozens of landslides every day to go to school to take care of students in mountainous areas.

Minister Nguyen Kim Son: The glory of the profession is created with the efforts of each teacher

|

Minister Nguyen Kim Son emphasized that the glory and noblest of the teaching profession does not come naturally, but is only created by the efforts of each teacher.

Ho Chi Minh City has no more than 8 Vice Chairmen of the People's Committee

|

According to the new regulations of the Government, Ho Chi Minh City has no more than 8 Vice Chairmen of the People's Committee, Hanoi has no more than 5 Vice Chairmen of the People's Committee.

Hanoi requires units to ensure salaries and Tet bonuses for workers

|

Hanoi requires units to prepare well the conditions to serve people to celebrate the Lunar New Year 2026, ensuring salaries and Tet bonuses for workers.

Multiple accidents on Dien Chau - Mai Son Expressway, many vehicles were severely damaged

|

The series of accidents that occurred on the Dien Chau - Mai Son Expressway caused severe damage to many vehicles, causing traffic congestion in the area.

The Party Committee of the Fatherland Front and Central organizations promote solutions to promote great national unity in the new era

|

On November 18, 2025, General Secretary To Lam wrote an important article on "Promoting the strength of great national unity to develop the country", emphasizing that great national unity is a strategic line, a precious tradition, the origin of strength and the decisive factor for all victories of the Vietnamese revolution over 95 years of building and maturing of the United National Front.

Billionaire Pham Nhat Vuong increases 5 places in the list of the richest people in the world

|

The sharp increase in assets has helped billionaire Pham Nhat Vuong continuously rise in the list of the richest billionaires on the planet.

Land clearance of Phu Thuan Industrial Park in October

Thành Nhân |

Ben Tre - Binh Dai District People's Committee will carry out site clearance for the remaining 2 households of Phu Thuan Industrial Park project in October 2024.

Khu công nghiệp bị ngập úng, công nhân bì bõm lội nước ra về

Thành Nhân |

Một số khu vực trong Khu công nghiệp Giao Long (huyện Châu Thành, tỉnh Bến Tre) bị ngập úng, khiến công nhân khá vất vả khi đi làm về.

Dự án khu công nghiệp Phú Thuận bị vướng mặt bằng

Thành Nhân |

Dự án khu công nghiệp Phú Thuận đang vướng mặt bằng do các hộ dân bị ảnh hưởng bởi dự án chưa nhận tiền bồi thường và chưa bàn giao mặt bằng.