Phu Thuan Industrial Park has reached more than 60% of its volume

Thành Nhân |

Ben Tre - The total construction volume of 6 packages of the Phu Thuan Industrial Park project under construction has reached 60.5%.

According to Lao Dong Newspaper reporters at noon on October 9, hundreds of workers were working at the Phu Thuan Industrial Park project site (Binh Dai district, Ben Tre province).

Mr. Pham Thanh Phong - Deputy Head of Project Management Department 3 (Project Management Board for Investment and Construction of Civil and Industrial Works of Ben Tre Province) - said that currently, 6 construction packages of the Phu Thuan Industrial Park project are under construction.

"Specifically, the volume of roads N3, D1 and D3 (section from N3 to N4) reached 94.8% of the contract value. Up to now, the contractor has completed the asphalt concrete paving and is completing the installation of lighting, road painting and signs.

As for D2 traffic road, the volume has reached 81.9% of the contract value. The construction unit is currently paving the sidewalk, installing lighting, painting the road, and signs.

For N1 - N4 road, the volume reached 23.9% of the contract value, the contractor is installing stormwater drainage, completing sand pumping on the roadbed, and spreading graded stone on the roadbed" - Mr. Phong said.

According to Mr. Phong, currently, contractors are constructing the filling lots (B1, KT-T, KT-R) and the centralized wastewater treatment plant package, with a capacity of 4,500 m3/day and night, the volume reaching 1.8% of the contract value.

Cong nhan trien khai thi cong goi thau Tram xu ly nuoc thai tap trung trong du an khu cong nghiep Phu Thuan. Anh: Thanh Nhan
Workers deploy the construction of the Centralized Wastewater Treatment Plant package in the Phu Thuan Industrial Park project. Photo: Thanh Nhan

Mr. Bui Van Hiep - Director of the Project Management Board for Investment and Construction of Civil and Industrial Works of Ben Tre Province - said that the People's Committee of Ben Tre Province has approved the contractor selection plan for 11 construction packages of the Phu Thuan Industrial Park project. Of which, 6 packages are being implemented, the total construction volume of these 6 packages is 60.5%.

"The 2 bidding packages for traffic routes N2-D1-D3 (N1-N4) and the filling of lots, drainage ditches and trees have been opened for bidding and are evaluating bidding documents. The filling package is expected to be implemented in October 2024. The remaining 3 bidding packages (including: Transformer station; Fence of the entire area, guard house; 2 filling lots adjacent to Cua Dai river bank) are scheduled to select contractors in the first quarter of 2025 before bidding is organized," said Mr. Hiep.

The Phu Thuan Industrial Park project has a total investment of more than 3,539 billion VND, invested by the Ben Tre Province Civil and Industrial Construction Investment Project Management Board. Of which, the provincial budget is more than 3,443 billion VND, the remaining from non-budgetary sources is more than 96.3 billion VND. The project implementation period is from 2017-2025, the construction site is in Phu Thuan and Long Dinh communes (Binh Dai district, Ben Tre province).

Thành Nhân
RELATED NEWS

Sweden forced to release oil tanker departing from Russia due to insufficient evidence

|

The oil tanker Flora 1, originally departing from Russia, was released by Sweden because no evidence of violation was found.

Mass clam deaths in Quang Ninh, many households suffered damage from 20 to 80%

|

Quang Ninh - Mass clam deaths in Quang Ha commune caused many farming households to suffer losses from 20-80%; the results determined that the cause was infection with the parasite Perkinsus sp.

East-West oil pipeline: Saudi Arabia's high-handed move

|

The escalating conflict and the risk of the Hormuz Strait being controlled for a long time further highlight the role of Saudi Arabia's East-West oil pipeline.

Arsenal eliminated in FA Cup

|

In the early morning of April 5 (Vietnam time), Arsenal unexpectedly lost to Southampton 1-2 and stopped in the FA Cup quarter-finals.

Enrollment 2026: Many universities adjust admission plans

|

In 2026, many universities simultaneously announced enrollment plans with a series of new points, from expanding training majors, adjusting admission methods.

Ministry of Education and Training: Schools must publicize food suppliers

|

The Ministry of Education and Training has directed the inspection of all contracts with catering and food suppliers; requiring schools to publicize food suppliers.

Land clearance of Phu Thuan Industrial Park in October

Thành Nhân |

Ben Tre - Binh Dai District People's Committee will carry out site clearance for the remaining 2 households of Phu Thuan Industrial Park project in October 2024.

Khu công nghiệp bị ngập úng, công nhân bì bõm lội nước ra về

Thành Nhân |

Một số khu vực trong Khu công nghiệp Giao Long (huyện Châu Thành, tỉnh Bến Tre) bị ngập úng, khiến công nhân khá vất vả khi đi làm về.

Dự án khu công nghiệp Phú Thuận bị vướng mặt bằng

Thành Nhân |

Dự án khu công nghiệp Phú Thuận đang vướng mặt bằng do các hộ dân bị ảnh hưởng bởi dự án chưa nhận tiền bồi thường và chưa bàn giao mặt bằng.