A series of abandoned projects cause waste in Bac Ninh

Vân Trường |

Some projects in Bac Ninh such as the Nhan Hoa - Phuong Lieu Industrial Park project and the Science - Education Union Project are behind schedule and have been abandoned for many years, causing waste of resources and public outrage.

Abandoned, wasteful

In 2008, the family of Mr. Nguyen Toan, 68 years old, in Nhan Hoa ward, Que Vo town, Bac Ninh and many households agreed to transfer land to the enterprise to implement the Nhan Hoa - Phuong Lieu Industrial Park Project, hoping for the socio-economic development of the locality. However, after 17 years, the project is still abandoned, without construction activities, causing land waste while many families and businesses are lacking land for production.

According to the reporter, many areas in the abandoned project are now being used as places for raising chickens, dropping ducks, and raising buffaloes.

The Nhan Hoa Small and Medium Industrial Park Infrastructure Investment, Construction and Business Project has been granted an investment certificate since 2008, with a scale of about 453,664.9m2, with a total investment capital of more than 143 billion VND.

Up to now, the project has cleared the land, built the operator's house, the main road of the industrial park and leveled most of the project implementation area.

However, according to the general planning orientation of Bac Ninh urban area and the determined subdivision planning, the project area has the function of urban development. Therefore, this project must carry out procedures to implement urban development as planned. Currently, investors complete the project conversion procedure to urban development function, leading to the project delay.

Similarly, the Science - Training Union Project in Dinh Bang Ward (Tu Son City, Bac Ninh Province) was approved for detailed planning in 2012, with the Vietnam Economic Science Association as the investor.

The project has a total area of over 204,000m2, including 3 subdivisions, with a total investment of 461 billion VND. The project has a number of violations related to compliance with regulations on investment; land management and use, construction planning, and construction order.

The People's Committee of Bac Ninh province requested Tu Son city to coordinate with relevant units and strictly handle according to regulations. Currently, the investor is implementing a plan to adjust the Detailed Planning and adjust the Investment Certificate but has not been approved by competent authorities.

The above project has a favorable location, the delay in project implementation has caused huge waste, affecting the socio-economic development of the province.

The Nhan Hoa - Phuong Lieu Industrial Park Project and the Science - Training Union Project are on the list of projects that are behind schedule, have beenengthened for a long time, and have low efficiency, causing great loss and waste, which the Chairman of the People's Committee of Bac Ninh province has directed the Department of Finance to review recently.

Request for final handling

On April 8, Bac Ninh Provincial Party Secretary Nguyen Anh Tuan directly inspected the status of the two above-mentioned projects.

For the Nhan Hoa - Phuong Lieu Industrial Park project, Bac Ninh Provincial Party Secretary Nguyen Anh Tuan requested the investor to coordinate with departments, branches and localities to complete the dossier to pilot the commercial housing project through an agreement on receiving land use rights or having land use rights.

Mr. Nguyen Anh Tuan suggested that Que Vo town conduct detailed planning, make plans to relocate and convert adjacent projects affecting the urban development policy of the surrounding area. Relevant departments and branches are assigned to support and guide localities and investors to carry out procedures for urban conversion and development.

For the project of science and training complex, the Secretary of the Provincial Party Committee emphasized that the province will issue a written notice of the implementation of the implementation to overcome the shortcomings, requiring the Vietnam Economic Science Association and the University of Business - Technology to coordinate closely with the province to completely solve the shortcomings, violations and problems related to.

Vân Trường
RELATED NEWS

Quang Tri urgently handles a series of abandoned public offices

|

Many projects worth billions of dong in Quang Tri have been abandoned for many years, causing waste, potential safety risks and making the public angry.

Chairman of the Vietnam General Confederation of Labor presents Tet gifts to workers at Ninh Binh Fertilizer Company

|

Ninh Binh - Chairman of the Vietnam General Confederation of Labor Nguyen Dinh Khang visited and presented 84 gifts to workers at Ninh Binh Fertilizer One Member Limited Liability Company.

Near Tet, Hanoi streets are still crowded with vehicles at midnight

|

Hanoi - 10 pm on February 12, many streets in the Capital are still crowded with vehicles passing by because of the flow of people going out to play and shop for Tet.

Erecting the Neu tree to welcome Tet, many people in Nghe An are electrocuted

|

Nghe An - In just a short time before Tet, electric shock incidents occurred continuously when erecting the Neu tree in Nghe An, causing many people to be severely burned.

Ho Chi Minh City Spring Flower Festival opens brilliantly at Tao Dan Park

|

Ho Chi Minh City - The 46th City Spring Flower Festival opened on the evening of February 12th at Tao Dan Park, attracting a large number of people to visit and check-in to welcome Binh Ngo Tet 2026.

Warm spring comes to pediatric patients at the National Institute of Hematology and Blood Transfusion

|

Approaching Tet, many pediatric patients at the National Institute of Hematology and Blood Transfusion are still staying for treatment. On February 12, the Golden Heart Charity Social Fund presented 120 gifts, bringing the warmth of early spring to children and families.

Ho Chi Minh City opens a sea-crossing delivery route Can Gio - Vung Tau by UAV

|

Ho Chi Minh City officially operates a sea-crossing delivery route using UAV connecting Can Gio - Vung Tau, shortening the time to 15 minutes/way, 6 times more optimal than roads.

Quang Tri urgently handles a series of abandoned public offices

HƯNG THƠ |

Many projects worth billions of dong in Quang Tri have been abandoned for many years, causing waste, potential safety risks and making the public angry.

Hiểm họa từ xưởng gỗ trong dãy nhà công nhân bỏ hoang ở Bắc Kạn

Nguyễn Hoàn |

Bắc Kạn - Bên trong dãy nhà công nhân, nhà điều hành bỏ hoang đã lâu nay thành xưởng gỗ hoạt động rầm rộ, tiềm ẩn nguy cơ về an toàn và cháy nổ.

Lãnh đạo Cần Thơ kiểm tra dự án bệnh viện nghìn tỉ bỏ hoang

Phong Linh |

Cần Thơ - Lãnh đạo thành phố kiểm tra dự án Bệnh viện Ung bướu Cần Thơ đã dừng thi công hơn 2 năm nay.