Reasons for slow site clearance for a series of projects in the West of Hai Phong

Mai Dung |

Hai Phong - Vice Chairman of the City People's Committee Vu Tien Phung inspected the site clearance of a number of projects in the West of the city.

According to the report of the People's Committee of Bac An Phu Ward, the investment project to build a road and Van bridge connecting National Highway 37 with the approach road to Trieu Bridge through the ward has currently completed 0.9 km/1.6 km. To date, there are 14 households whose land has been recovered to implement the project that have not yet handed over the site.

For the project of the National Highway 17B Construction Investment Project with Provincial Road 352 through Nguyen Dai Nang Ward with a length of 5.44 km, up to now, Nguyen Dai Nang Ward has approved a compensation plan for 6 households with agricultural land; has not completed site clearance for 43 households. 17 households are eligible for resettlement, the ward has arranged 2 resettlement locations for households with recovered land areas.

In addition, the ward is also implementing 2 projects, the Project to invest in the construction of technical infrastructure for the Residential Area and the resettlement area of Minh Hoa commune (now Nguyen Dai Nang ward), with a scale of 2 hectares, a total investment of 39.6 billion VND. The project is submitting for appraisal the construction design after the basic design and implementing site clearance.

Ảnh: Cong TTDT Hai Phong
Construction of the investment project to build the road and Van bridge connecting National Highway 37 with the Trieu Bridge approach road. Photo: Hai Phong Portal

The Cua Lang residential area and resettlement area project, Hien Thanh ward, the old Kinh Mon town (now Nguyen Dai Nang ward) has a scale of 3.79 hectares, with a total investment of VND25.021 billion. The unit has selected a construction unit; is organizing site clearance. It is expected that before November 20, the contractor will carry out infrastructure construction.

Localities also pointed out a number of limitations, difficulties and obstacles in site clearance for project implementation. In which the main reason for the problem of site clearance is that some households do not agree with the compensation plan to support site clearance, the level of support for assets, trees, and crops on the land.

After checking and listening to the report, Vice Chairman of the City People's Committee Vu Tien Phung requested localities to focus on resolving problems in site clearance for projects and works under implementation. Departments and branches strengthen coordination and support localities and units in disbursing public investment capital, site clearance, and speeding up the progress of projects.

Pho Chu tich UBND thanh pho Vu Tien Phung kiem tra tien do giai phong mat bang mot so du an trong diem. Ảnh: Cong TTDT Hai Phong
Vice Chairman of the City People's Committee Vu Tien Phung inspects the site clearance progress of a number of key projects. Photo: Hai Phong Portal
Mai Dung
RELATED NEWS

Hai Phong allocates land to implement a social housing project worth over VND1,400 billion

|

Hai Phong - The City People's Committee has just handed over nearly 3 hectares of land to implement the Social Housing Project in the Residential Area, Workers' Housing and Tan Truong Industrial Park Services.

Hai Phong plans to invest more than VND3,000 billion to renovate and repair commune-level public offices

|

Hai Phong - The Standing Committee of the City Party Committee has just given its opinion on the development of a Plan for investment, renovation, repair, and arrangement of commune-level public headquarters.

Handover of land for industrial park projects in Hai Phong

|

Hai Phong - On November 11, An Phong ward handed over land on site to serve the An Duong Industrial Park project.

Hanoi will develop bus routes on the basis of BRT fast bus routes

|

In the 2030-2035 period, Hanoi will develop bus routes on the BRT express bus route and urban railway, attracting people to use public transport.

Experts talk about the issue of increasing retirement age

|

Many opinions say that it is necessary to improve the skills and productivity of young workers to promote economic growth instead of extending the retirement age.

Mr. Tran Huy Tuan was elected to hold the position of Chairman of the Ninh Binh Provincial People's Committee

|

Ninh Binh - On the afternoon of November 12, Mr. Tran Huy Tuan - Deputy Secretary of the Ninh Binh Provincial Party Committee was elected by the Provincial People's Council to hold the position of Chairman of the Provincial People's Committee with 100% of the votes.

Current status of Can Tho Stadium proposed to be relocated

|

Can Tho - After being renovated in 2019, Can Tho Stadium now has many items that are gradually deteriorating.

Da Nang discusses solutions to urgently salvage the ancient ship that was just discovered on Hoi An coast

|

The Hoi An Cultural Heritage Conservation Center and the Department of Culture, Sports and Tourism of Da Nang City discuss and find solutions to salvage and relocate ancient ships on the coast of Cam An.

Hai Phong allocates land to implement a social housing project worth over VND1,400 billion

Mai Dung |

Hai Phong - The City People's Committee has just handed over nearly 3 hectares of land to implement the Social Housing Project in the Residential Area, Workers' Housing and Tan Truong Industrial Park Services.

Hai Phong plans to invest more than VND3,000 billion to renovate and repair commune-level public offices

Hoàng Khôi |

Hai Phong - The Standing Committee of the City Party Committee has just given its opinion on the development of a Plan for investment, renovation, repair, and arrangement of commune-level public headquarters.

Handover of land for industrial park projects in Hai Phong

Hoàng Khôi |

Hai Phong - On November 11, An Phong ward handed over land on site to serve the An Duong Industrial Park project.