Binding of key transport projects in Tuyen Quang

Việt Bắc |

Many key transport projects in Tuyen Quang province are facing difficulties in site clearance, which risks affecting the completion progress.

The road project from My Lam Mineral Spring Tourist Area to National Highway 2D connecting to Tuyen Quang - Phu Tho Expressway was started at the end of 2021. With a total length of nearly 9km, the total investment is 487 billion VND according to urban road standards.

It is expected that this route will be completed and put into use in early 2025. However, due to land clearance problems, construction work is facing difficulties, and the project is at risk of not being able to finish on time.

By the end of March 2025, nearly 7 out of a total of 8.9km of the entire route have been completed, and auxiliary items such as sidewalks, trees, and lighting are under construction.

However, about 2km of the section through Tuyen Quang City is being constructed in a "sticky rice and bean" style because the site has not been handed over. The reason is that some households have not agreed to the compensation plan and have not accepted relocation.

According to the Land Fund Development Center of Tuyen Quang City, there are still over 20 households in the area that have not approved the handover of land for 2 key transport projects.

Currently, the authorities of Tuyen Quang City are actively mobilizing and mobilizing resources to clear the land (GPMB), ensuring the progress of the projects.

Cao toc Tuyen Quang - Ha Giang (doan qua Tuyen Quang) co nguy co cham tien do do mat bang cham ban giao. Anh: Viet Bac.
Tuyen Quang - Ha Giang Expressway (section through Tuyen Quang) is at risk of being behind schedule due to slow site handover. Photo: Viet Bac.

Similarly, the Tuyen Quang - Ha Giang expressway project (section through Tuyen Quang province) with a total investment of nearly 6,800 billion VND) is also facing difficulties due to many locations that cannot be cleared, causing contractors to be slow.

According to the report of the Tuyen Quang Province Traffic Construction Investment Project Management Board (representative of the investor of Tuyen Quang - Ha Giang Expressway), the entire route has been handed over 64.4 km, reaching 92.40%, and there are still 5.3 km that have not been cleared.

The site clearance work still has 65 bottlenecks related to unresolved problems with 439 households. Many families have not agreed to receive compensation and have not relocated to hand over the site.

This has more or less affected the construction progress when the total implementation value has reached 28% of the contract value and is about 7% behind schedule. Not to mention arising problems such as lack of soil materials for roadbed construction and lack of stone materials for the Project.

Recently, on March 21, Chairman of Tuyen Quang Provincial People's Committee Nguyen Van Son, when inspecting the progress of Tuyen Quang - Ha Giang expressway, stated that if the site clearance work of 100% of the site was not completed in March 2025, it would affect the construction progress and there was a risk that the project would be behind schedule.

Previously, on December 18, 2025, the Government Office issued Notice No. 118 on the conclusion of Deputy Prime Minister Bui Thanh Son for the Tuyen Quang - Ha Giang expressway project (section through Tuyen Quang province) requesting the People's Committee of Tuyen Quang province to commit to completing the site clearance work and handing it over in March 2025 according to the direction of the Prime Minister.

Việt Bắc
RELATED NEWS

Proposing Tuyen Quang to commit to site clearance for expressway projects in March

|

Deputy Prime Minister Bui Thanh Son has just requested the People's Committee of Tuyen Quang province to commit to site clearance for the Tuyen Quang - Ha Giang expressway project in March.

slow construction of the only road leading to the capital Tuyen Quang

|

Tuyen Quang - The sluggish construction situation has caused the road from Tan Thanh commune to Phu Luu commune to be bumpy and littered with construction materials.

12 traffic projects face difficulties

|

12 transport projects with a total length of 402 km are facing difficulties in site clearance, and construction materials need to be drastically resolved and focused on removing them.

Famous Australian candy found to contain foreign objects, Ministry of Health immediately intervenes

|

After Australia urgently recalled a number of Allen's iNSiDE OUTS candies due to the discovery of plastic foreign objects, the Ministry of Health requested a review and suspension of business of this product.

Stock market liquidity unexpectedly drops sharply

|

The stock market still maintained green color but liquidity was quite low with a trading value of less than 14,000 billion VND in the trading session.

Overview of the 692 billion VND road connecting 2 expressways in Phu Tho

|

Phu Tho - The 2.7km longer route connecting Noi Bai - Lao Cai expressway with Tuyen Quang - Phu Tho expressway is in the process of being completed.

Official exam questions and answers for Literature subject of the 10th grade exam in Ho Chi Minh City

|

On the afternoon of June 5, the Ho Chi Minh City Department of Education and Training (GDĐT) announced the official exam questions and answers for Literature in the 10th grade entrance exam for the 2026-2027 school year.

Ministry of Education appoints many directors and principals of directly affiliated universities and colleges

|

The Ministry of Education and Training has completed nearly 95% of the plan to consolidate heads at affiliated educational institutions, with 51/54 units completing the arrangement of leadership personnel.

Proposing Tuyen Quang to commit to site clearance for expressway projects in March

Xuyên Đông |

Deputy Prime Minister Bui Thanh Son has just requested the People's Committee of Tuyen Quang province to commit to site clearance for the Tuyen Quang - Ha Giang expressway project in March.

slow construction of the only road leading to the capital Tuyen Quang

Lam Thanh |

Tuyen Quang - The sluggish construction situation has caused the road from Tan Thanh commune to Phu Luu commune to be bumpy and littered with construction materials.

12 traffic projects face difficulties

PHẠM ĐÔNG |

12 transport projects with a total length of 402 km are facing difficulties in site clearance, and construction materials need to be drastically resolved and focused on removing them.