ĐÌNH TRỌNG |

Binh Duong - A building weighing over 1,000 tons is being relocated 40 m by the "genie" to give up the construction site of Ho Chi Minh City Ring Road 3.

On May 12, the construction unit is focusing on human resources to urgently relocate the building in the Tan Van fish hatchery area, Binh Thang ward, Di An city, Binh Duong province.

This is one of the houses in the construction planning area of the Ho Chi Minh City Ring Road 3 project through Binh Duong province.

At the Tan Van intersection of the Ho Chi Minh City Ring Road 3 project, there is a building about 1,000 m2 wide, previously used as a restaurant. The building is located in an area that must be relocated to make way for the construction site of the Tan Van intersection of the Ho Chi Minh City Ring Road 3 project.

Toa nha nang khoang 1.000 tan dang duoc di doi. Anh: Duong Binh
The building weighing about 1,000 tons is being relocated. Photo: Duong Binh

Mr. Nguyen Minh Tai - Director of Thien Loc Light Company (the construction unit of the relocation of the building) said that the building with an area of about 1,000 m2, built about 20 years ago, was partially removed, the remaining area of about 400 m2 was relocated to give up the construction site of Ho Chi Minh City Ring Road 3.

The remaining part of the building (about 25 m wide, about 15 m long). This building has 3 usable floors and 1 roof floor. The total weight is over 1,000 tons, requiring relocation of about 40 m.

The unit had to use iron bars to support and weld iron to strengthen the building's structure. Then, they dug the foundation and used the hydraulic shock to lift the building.

After 1 month of implementation, the building was successfully raised to 1.7 m from the original location.

Toa nha da di doi duoc khoang 15m. Anh: Dinh Trong
The building has been relocated about 15m. Photo: Dinh Trong

Next, it is necessary to make new nails for the building and pour concrete as the ground to relocate the building. This unit is using rollers to relocate the building. Currently, the building has relocated about 15 m compared to the original position. About 15 days, the building moved into a new location, yielding the entire ground for construction of Ring Road 3 of Ho Chi Minh City.

Toa nha duoc di doi de nhuong mat bang thi cong du an duong Vanh dai 3 TPHCM. Anh: Dinh Trong
The building was relocated to make way for the construction site of the Ho Chi Minh City Ring Road 3 project. Photo: Dinh Trong

Previously, at the end of March 2025, when giving up the site for the parallel road project at Tan Van intersection, a house was tilted. The house is being reinforced and upgraded to balance it for continued use.

It is known that the Ho Chi Minh City Ring Road 3 project has a total length of 76.34 km, passing through 4 localities including Ho Chi Minh City, Dong Nai, Binh Duong and Long An. The total investment of this project is 75,378 billion VND, including 33,788 billion VND for construction costs and 41,590 billion VND for site clearance.

Du kien trong thang 5.2025 se di doi xong toa nha. Anh: Dinh Trong
It is expected that the building will be relocated in May 2025. Photo: Dinh Trong

The Ho Chi Minh City Ring Road 3 passing through Binh Duong province is about 26.6 km long, with a total investment of VND 19,280 billion. Of which, the Tan Van intersection construction package will start construction at the end of April 2024.

According to the People's Committee of Binh Duong province, the site clearance progress for the construction of Tan Van intersection has reached 99%. In May 2025, the relocation of technical infrastructure will be completed to make way for the Ho Chi Minh City Ring Road 3 project. Binh Duong province will ensure construction progress and put the route into operation in 2026.

Hinh anh di doi toa nha. Anh: Dinh Trong
Image of the building relocation. Photo: Dinh Trong

ĐÌNH TRỌNG
TIN LIÊN QUAN

Hot Saigon: Relocating the high-speed train terminal to build a 1,000 billion VND pedestrian bridge in Ho Chi Minh City

|

Hot Saigon News on May 6: The time when the South officially enters the rainy season; Relocating the high-speed wharf at Bach Dang wharf to build a 1,000 billion VND pedestrian bridge;...

Ho Chi Minh City Ring Road 3 still lacks sand for filling, affecting construction progress

|

The Ho Chi Minh City Ring Road 3 project - a key traffic route that plays a regional linkage role between Ho Chi Minh City and neighboring provinces is facing great difficulties in the supply of sand for filling, affecting the construction progress of the entire route.

Compensation of 7,770 billion VND for Ho Chi Minh City Ring Road 3 through Binh Duong

|

The component project of compensation, site clearance and resettlement for the construction of Ho Chi Minh City Ring Road 3 through Binh Duong has a total investment of 13,528 billion VND.

Chairman of Lao Cai issued a letter of the week about many units that owe banks billions of dong

|

Lao Cai - After the reflection, the Chairman of Lao Cai Provincial People's Committee issued instructions on resolving debts for printing houses in Bao Yen district.

Victim of a horrifying accident on the highway tries to squeeze through the driver's body to escape

|

Quang Nam - After the accident between a passenger bus and a tractor-trailer on the highway, the victims trembled over the bodies of the two drivers who died in the cabin to escape.

Admiring the new name signs of wards, communes, and special zones in Quang Ninh

|

Quang Ninh - Many new commune-level administrative units in Quang Ninh have completed the attachment of new name signs after merging administrative units.

Fire in a house and office for rent in Ho Chi Minh City, rescued 2 people trapped

|

HCMC - A fire broke out on the ground floor of a house on Nguyen Gia Tri Street (Binh Thanh District). Fire police promptly rescued 2 trapped people.

Strong earthquake in Japan, raising concerns about predicting Tsunami disasters

|

A 6.1-magnitude earthquake hit off the Nemuro peninsula, southeast of Japan, on the morning of June 19.

Hot Saigon: Relocating the high-speed train terminal to build a 1,000 billion VND pedestrian bridge in Ho Chi Minh City

NGỌC ÁNH - NGỌC LÊ |

Hot Saigon News on May 6: The time when the South officially enters the rainy season; Relocating the high-speed wharf at Bach Dang wharf to build a 1,000 billion VND pedestrian bridge;...

Ho Chi Minh City Ring Road 3 still lacks sand for filling, affecting construction progress

MINH QUÂN |

The Ho Chi Minh City Ring Road 3 project - a key traffic route that plays a regional linkage role between Ho Chi Minh City and neighboring provinces is facing great difficulties in the supply of sand for filling, affecting the construction progress of the entire route.

Compensation of 7,770 billion VND for Ho Chi Minh City Ring Road 3 through Binh Duong

ĐÌNH TRỌNG |

The component project of compensation, site clearance and resettlement for the construction of Ho Chi Minh City Ring Road 3 through Binh Duong has a total investment of 13,528 billion VND.