Progress of 2 trillion-dong highway projects passing through Khanh Hoa

Bình Quý |

Khanh Hoa – Currently, the two expressway projects Khanh Hoa - Buon Ma Thuot and Van Phong - Nha Trang expressway are speeding up progress, aiming to reach the finish line soon.

The Van Phong - Nha Trang Expressway, part of the North - South Expressway in the eastern part of the 2021 - 2025 period, is over 83km long and is expected to be basically completed by April 30, 2025. According to the report of Project Management Board 7 (Ministry of Transport), up to now, the site clearance work of the Van Phong - Nha Trang Expressway Project has basically completed the main expressway section.

However, there is still 1.44km that has not been constructed due to technical infrastructure problems and problems with site clearance at some local locations; the entire project has only completed the relocation of 146/164 technical infrastructure locations; the remaining 18 locations include: 1 medium voltage location, 2 lighting locations, 3 telecommunications locations, 12 high voltage locations of 110kV and 220kV.

In addition, there are 2 transformer station locations of rooftop solar power projects in Van Ninh district that have not been relocated. The main remaining problem is the relocation of high-voltage power lines with 12 locations that have not been relocated, making it impossible to complete construction items.

In particular, the locations are critical roads that greatly affect the progress of the main route, including: 2 intersections (Van Gia, National Highway 26); Tan Lam bridge; approach road to pier A of Song Cai 1 bridge; section Km333 + 550 - Km333 + 700.

In order to strive to complete the Van Phong - Nha Trang expressway project 8 months ahead of schedule, Project Management Board 7 proposed that the leaders of Khanh Hoa province direct the People's Committee of Ninh Hoa town to continue working and mobilizing the handover of the site to the construction unit while waiting for approval of the additional compensation plan.

Meanwhile, according to the Khanh Hoa Provincial Traffic Construction Investment Project Management Board, the 2024 public investment capital plan for the Khanh Hoa - Buon Ma Thuot Expressway Project, component 1, is VND 1,600 billion, but so far only more than VND 370 billion has been disbursed.

Du an cao toc Khanh Hoa - Buon Ma Thuot co quy mo du an co 4 lan xe, dau tu giai doan tu 2021 - 2025, van toc thiet ke 80 - 100km/h. Anh: Huu Long
The Khanh Hoa - Buon Ma Thuot Expressway project has a scale of 4 lanes, invested in the period from 2021 - 2025, with a design speed of 80 - 100km/h. Photo: Huu Long

Currently, Ninh Hoa Town People's Committee has approved the transfer of investors in 77 batches with 815/1,043 cases of payment, reaching 78.14%, corresponding to the project area of ​​171/228ha.

The Ninh Hoa Town Land Fund Development Center has handed over the site for on-site construction of 28.17/31.5km (89.42%). Currently, contractors are leveling the newly handed over sections. However, some sections through residential areas with houses on the land must be resettled, so the board has coordinated with the Ninh Hoa Town Land Fund Development Center to continue to mobilize households to open public roads.

Regarding the relocation of technical infrastructure at the Khanh Hoa - Buon Ma Thuot Expressway Project, the construction unit has completed the relocation of the 35kV line and the 110kV line; the remaining 2 locations of the 220kV line are under construction.

For Ha Thanh Resettlement Area, up to now, Ninh Hoa Town Land Fund Development Center has handed over more than 6.7ha/7,182ha (93.5%). Currently, the investor has completed phase 1 with 120 lots/200 lots.

Bình Quý
TIN LIÊN QUAN

Khánh Hòa dự chi 75 tỉ đồng hỗ trợ học phí cho học sinh nhiều cấp

Hữu Long |

Khánh Hòa - Địa phương đang xây dựng chính sách hỗ trợ học phí cho học sinh phổ thông, học viên giáo dục thường xuyên học ở cơ sở giáo dục công lập.

Gấp rút hoàn thành cao tốc Khánh Hòa - Buôn Ma Thuột

BẢO TRUNG |

Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính đã phát động đợt thi đua cao điểm 500 ngày đêm để hoàn thành 3.000km đường bộ cao tốc trong đó có tuyến Khánh Hòa - Buôn Ma Thuột. Tại công trường dự án này, công nhân lao động đang ngày đêm hăng say lao động để góp phần hoàn thiện mạng lưới cao tốc, thúc đẩy phát triển kinh tế xã hội vùng Tây Nguyên cũng như trên cả nước.

Khánh Hòa xây 48.700 nhà ở xã hội cho người thu nhập thấp

Hữu Long |

Khánh Hòa - Địa phương đặt mục tiêu đến năm 2030 sẽ xây dựng được 48.749 căn hộ nhà ở xã hội cho người thu nhập thấp, công nhân trong các khu công nghiệp.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Phá đường dây cờ bạc nghìn tỉ qua mạng, tạm giam 12 người

Thành Nhân |

Bến Tre - Lực lượng Công an vừa triệt xóa đường dây cờ bạc trên không gian mạng với tổng số tiền giao dịch hơn 1.800 tỉ đồng.

Nổ nồi hấp tinh dầu, 1 bé gái bị thương, 5 căn nhà ảnh hưởng

LÝ LINH |

TPHCM - Ngày 15.10, Công an huyện Bình Chánh đang điều tra vụ nổ nồi hấp tại một cơ sở sản xuất tinh dầu trên địa bàn xã Vĩnh Lộc A khiến một bé gái bị thương.

Nguyên chủ tịch xã ở Thái Bình bị tố lạm quyền để trục lợi

TRUNG DU |

Thái Bình - Nguyên Chủ tịch UBND xã Quỳnh Hải, huyện Quỳnh Phụ bị tố lợi dụng chức vụ quyền hạn để tư lợi, trục lợi cho bản thân, gia đình.

Khánh Hòa dự chi 75 tỉ đồng hỗ trợ học phí cho học sinh nhiều cấp

Hữu Long |

Khánh Hòa - Địa phương đang xây dựng chính sách hỗ trợ học phí cho học sinh phổ thông, học viên giáo dục thường xuyên học ở cơ sở giáo dục công lập.

Gấp rút hoàn thành cao tốc Khánh Hòa - Buôn Ma Thuột

BẢO TRUNG |

Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính đã phát động đợt thi đua cao điểm 500 ngày đêm để hoàn thành 3.000km đường bộ cao tốc trong đó có tuyến Khánh Hòa - Buôn Ma Thuột. Tại công trường dự án này, công nhân lao động đang ngày đêm hăng say lao động để góp phần hoàn thiện mạng lưới cao tốc, thúc đẩy phát triển kinh tế xã hội vùng Tây Nguyên cũng như trên cả nước.

Khánh Hòa xây 48.700 nhà ở xã hội cho người thu nhập thấp

Hữu Long |

Khánh Hòa - Địa phương đặt mục tiêu đến năm 2030 sẽ xây dựng được 48.749 căn hộ nhà ở xã hội cho người thu nhập thấp, công nhân trong các khu công nghiệp.