Continue to reclaim land for a project worth over 900 billion VND in Hai Phong

Hoàng Khôi |

Hai Phong - Thuy Nguyen District (Hai Phong) has just held a meeting to deploy land acquisition and site clearance for the technical infrastructure project of the resettlement area North of Cam River.

Based on the Decision approving the project adjustment of the City People's Committee, the People's Committee of Thuy Nguyen district together with the Hai Phong Civil Construction Investment Project Management Board has prepared and submitted for appraisal the Cadastral Extract map according to the adjusted scope; and publicly posted it at the Headquarters of the People's Committee of Duong Quan commune, the Cultural House of Chan Lam village, and the Cultural House of Tay Nha Tho village.

Accordingly, the project adjusted the land use area from 38.86 ha to 33.122 ha. The investment in building technical infrastructure for the resettlement area on a total area of ​​33.122 ha of land divided into 4 resettlement areas (A, B, C, D) formed 1,222 residential plots to serve the lives of local people. The road system within the project has a scale of: 26m, 15m, and 13m. The total investment of the project was adjusted to 910,771,553,000 VND.

Regarding the project's site clearance work, the number of households that must continue site clearance work is 37 households, on an area of ​​1.72 hectares.

At the conference, households whose land was recovered expressed their agreement and high consensus on the project implementation policy. At the same time, they requested the government to consider and calculate a reasonable compensation price to ensure the rights of the people...

Mr. Nguyen Van Vien - Vice Chairman of the District People's Committee said that the compensation and support policy for the Project will be applied according to the 2024 Land Law. From October 14, specialized agencies will conduct an inventory and determine the land origin for each household. The district hopes that households will actively coordinate with the district's specialized agencies to declare, inventory, and develop compensation and support plans according to the provisions of law, ensuring the progress of site clearance for project implementation.

Hoàng Khôi
RELATED NEWS

Factory fire near gas station in Ho Chi Minh City

|

Ho Chi Minh City - Ho Chi Minh City Police have controlled a factory fire near a gas station in Tan Hiep ward.

Ho Chi Minh City People's Committee headquarters nearly 120 years old will become a tourist attraction

|

Ho Chi Minh City - The headquarters of the People's Council - People's Committee of Ho Chi Minh City on Le Thanh Ton Street (nearly 120 years old) will be preserved and exploited as a tourist and educational destination.

Hanoi Party Secretary sets deadline for completion of "most expensive road on the planet

|

Hanoi - Regarding the progress of the Ring Road 1 project (Hoang Cau - Voi Phuc section), the Hanoi Party Secretary requested to complete the entire roadbed before September 2, 2026; complete the construction of 2 overpasses on the route before December 31, 2026.

Gia Lai drought, people dredge to find water sources to save crops

|

Gia Lai - The western region of the province is entering the dry season, many localities are facing severe water shortages.

Hanoi Traffic Police show trainees videos of accidents before driving test

|

Hanoi - Before the test, traffic police show trainees videos recording serious traffic accidents, thereby making them more aware of their responsibilities when holding the steering wheel.

Complete the installation of medical equipment at facility 2 of Bach Mai and Viet Duc Hospitals before June 30

|

Ninh Binh - The investor of Bach Mai Hospital and Viet Duc Friendship Hospital facility 2 project committed to complete the installation of equipment before June 30.

Salary reform from the Central to local levels, implemented in all 3 blocs

|

The Ministry of Home Affairs is assigned to carefully prepare the reform of salaries, allowances and other regimes from the Central to local levels, implemented in all 3 blocs.

Forecast of the risk of receiving strong storms and super typhoons in 2026

|

According to a representative of the meteorological agency, ENSO phase transition along with the impact of climate change leads to the risk of strong storms and super typhoons in 2026.

Launching a movement for workers to classify garbage in Hai Phong

Mai Dung |

Hai Phong - On the morning of October 13, the Tien Lang District Labor Federation (Hai Phong) held a launching ceremony for "Trade Union with the work of classifying solid waste at source".

Closing ceremony of the Hai Phong Economic Zone Trade Union Men's and Women's Football Tournament

Mai Dung |

Hai Phong - On the morning of October 13, the Hai Phong Economic Zone Trade Union organized the final and closing ceremony of the 2024 men's and women's football tournament.

A series of food streets were born, promoting Hai Phong's night economy

Mai Dung |

Hai Phong - Hai Phong has just continued to launch the Phung Chi Kien culinary culture street (Ngo Quyen district), promoting the night economy in the central area.