HCMC breaks land acquisition plan for expressway construction, 2,193 households have not been compensated

MINH QUÂN |

HCMC - The HCMC - Moc Bai Expressway project needs to reclaim land from 2,193 households, but the compensation payment progress is nearly 3 months behind schedule.

According to the Department of Agriculture and Environment of Ho Chi Minh City, component project 3 - compensation, support, and resettlement of the Ho Chi Minh City - Moc Bai expressway section through Ho Chi Minh City is about 24.7 km long, passing through 5 communes: Phu Hoa Dong, Nhuan Duc, Thai My, Tan An Hoi and Cu Chi, with a total land area to be recovered of 220 hectares.

The total number of affected cases is 2,193 households with compensation, support and resettlement costs of about VND 4,333 billion.

Of which, Phu Hoa Dong commune has the largest number of affected households with 1,159 cases, followed by Nhuan Duc commune (669), Thai My commune (256), Cu Chi town (77) and Tan An Hoi commune (32).

According to the plan of the Ho Chi Minh City People's Committee, the project will approve the compensation, support, resettlement plan and issue a decision to reclaim land, and make payments from April 2025.

The handover of the site will be implemented from April 2025 and is expected to be completed in December 2025.

However, according to the latest report from the Department of Agriculture and Environment, this plan has been "disrupted". By the end of June 2025, specific land prices as well as compensation plans have not been approved.

The People's Committee of Cu Chi district (old) has just confirmed the origin of land use in 156/2,193 cases (only about 7%).

Khu vuc noi du an cao toc TPHCM - Moc Bai di qua. Anh: Minh Quan
The area where the Ho Chi Minh City - Moc Bai Expressway project passes through. Photo: Minh Quan

Faced with this situation, the Department of Agriculture and Environment of Ho Chi Minh City proposed that the People's Committee of Ho Chi Minh City direct the Chairmen of the People's Committees of 5 communes to urgently establish a Compensation, Support and Resettlement Council for each locality to promote progress.

The Department proposes the deadline for completing the verification of the origin and legality of real estate as follows: Thai My, Tan An Hoi, Cu Chi communes to complete before August 30.7; Nhuan Duc commune before August 10.8; Phu Hoa Dong commune before August 15.

To have a basis for making compensation plans, the Department also recommends that communes establish specific Land Valuation Councils and announce unit prices applicable in each locality. The Department of Agriculture and Environment proposes to be given the right to balance land prices in these areas to ensure fairness and unity.

The draft compensation plan needs to be publicly posted at the headquarters of the People's Committee at the commune level and community activity locations from August 1 to September 1.

The approval of the compensation and resettlement plan for the Ho Chi Minh City - Moc Bai Expressway project must be completed before September 5.

Compensation work is divided into 2 phases:

Phase 1: Compensation, support, and resettlement for cases with pure agricultural land and cases with residential land but agreeing to reclaim land in advance. The compensation payment period ends before September 30, 2025.

Phase 2: Applicable to the remaining cases with residential land, payment ends before February 28, 2026.

Phoi canh nut giao cao toc TPHCM - Moc Bai.  Anh: Ban Giao thong TPHCM
Perspective of the Ho Chi Minh City - Moc Bai Expressway Intersection. Photo: Ho Chi Minh City Traffic Department

The project needs about 458 resettlement plots, of which 267 cases affected by residential land need to be arranged for resettlement plots, the rest are households building houses on agricultural land (191 cases).

Therefore, the Department of Agriculture and Environment proposed that the Ho Chi Minh City People's Committee assign the Department of Construction to direct the Cu Chi area Investment and Construction Project Management Board to coordinate with the Ho Chi Minh City Traffic Construction Investment Project Management Board to speed up the implementation of resettlement areas to promptly arrange accommodation for affected people and hand over the site to the construction unit.

The Ho Chi Minh City - Moc Bai Expressway Project Phase 1 has a total length of more than 50 km, designed with 4 lanes, with a total investment of more than VND 19,600 billion.

Ho Chi Minh City plans to start construction of a bidding package for bomb and mine clearance and relocation of technical infrastructure on August 19.

The items of the residential access road and the expressway overpass using state budget capital will start construction at the end of 2025.

The main expressway under the BOT form will start construction in January 2026 and be completed by the end of 2027.

MINH QUÂN
TIN LIÊN QUAN

HCMC reclaims 110 hectares of land, clears 61 households to build the North-South high-speed railway

|

Ho Chi Minh City will reclaim more than 110 hectares of land, clear 61 households with compensation and site clearance costs of more than VND 2,100 billion to build the North-South high-speed railway section.

HCMC reclaims land from more than 3,300 households to build the largest road in the Southeast

|

Ho Chi Minh City will reclaim land from more than 3,300 households, including households in Binh Duong and Ba Ria - Vung Tau (old), to implement the Ho Chi Minh City Ring Road 4 project, more than 200 km long.

HCMC spends VND1,800 billion to open a 6-lane Saigon River road across the central golden land

|

Ho Chi Minh City speeds up investment procedures for a nearly 2km long, 6-lane Saigon River road, with a total investment of VND1,800 billion, connecting from Ba Son Bridge to Saigon Bridge.

Bich Tuyen and her husband will submit new evidence to the court in the lawsuit with Dam Vinh Hung

|

According to singer Bich Tuyen, she and her husband will submit new evidence to a court in the US in the lawsuit with Dam Vinh Hung.

Storm leaves 2 people missing in Ha Tinh, 58 fishing boats sunk

|

Ha Tinh - On the afternoon of July 20, according to a quick report from the province, the storm that occurred on the evening of July 19 left 2 people missing, damaging a number of houses and infrastructure.

List of schools announcing admission floor scores in 2025

|

The list of universities announcing the 2025 admission floor score is updated by Lao Dong as quickly as possible.

People in the story tell the moment a painter clings to an apartment window in the middle of a storm and heavy rain

|

Hanoi - The Head of the Management Board of Tower C, Vinaconex 2 apartment building has just shared information with Lao Dong about the case of a paint worker clinging to the windows of an apartment building in the midst of a storm and heavy rain on the afternoon of July 19.

Dien Bien requests commune authorities to report on workers' salary debt

|

Dien Bien - The Provincial Party Committee's Propaganda and Mass Mobilization Committee requested the People's Committee of Nu Ngam commune to report the case of dozens of workers being owed wages after being reported by Lao Dong Newspaper.

HCMC reclaims 110 hectares of land, clears 61 households to build the North-South high-speed railway

MINH QUÂN |

Ho Chi Minh City will reclaim more than 110 hectares of land, clear 61 households with compensation and site clearance costs of more than VND 2,100 billion to build the North-South high-speed railway section.

HCMC reclaims land from more than 3,300 households to build the largest road in the Southeast

MINH QUÂN |

Ho Chi Minh City will reclaim land from more than 3,300 households, including households in Binh Duong and Ba Ria - Vung Tau (old), to implement the Ho Chi Minh City Ring Road 4 project, more than 200 km long.

HCMC spends VND1,800 billion to open a 6-lane Saigon River road across the central golden land

MINH QUÂN |

Ho Chi Minh City speeds up investment procedures for a nearly 2km long, 6-lane Saigon River road, with a total investment of VND1,800 billion, connecting from Ba Son Bridge to Saigon Bridge.