Urgently constructing, striving to energize the 500kV power line on August 19

NHÓM PHÓNG VIÊN |

The 500kV Lao Cai - Vinh Yen transmission line project, nearly 230km long, is entering the final stage, striving to energize on August 19 under the direction of the Prime Minister.

In the hot days of early August, at the construction site of the 500kV Lao Cai - Vinh Yen transmission line project, there are hundreds of engineers and workers working day and night with the determination to "not delay a minute". Working groups of the Khanh Hoa, Lam Dong, Gia Lai, and Dak Lak Power Transmission Teams also traveled thousands of kilometers to support construction at key locations of the power line.

The project passes through the two provinces of Lao Cai and Phu Tho, with a total investment of more than 7,400 billion VND. When put into operation, the project will release about 2,000MW from the hydropower plant in the Northwest region, reducing transmission losses and increasing the stability of the national power system.

At the construction site, electricity workers are not only under pressure in terms of time, but also facing extreme weather difficulties due to the early rainy season, the impact of storms and storm circulation...

In package No. 2 in the communes of Thuong Ha, Bao Yen, Xuan Hoa, Phuc Khanh (Lao Cai), the teams are simultaneously constructing the final pillar locations. "Up to now, we have completed 100% of the foundation casting, have completed 27 pillars, and have 20 locations still in progress. All preparations for pulling the rope are ready, said engineer Trieu Quoc Truong.

According to Mr. Truong, many construction locations are extremely difficult, located on high, rugged mountain peaks. Prolonged heavy rain increases the risk of lightning and landslides, while turning the road into mud, causing great obstacles for moving materials and cranes.

"There were days when it rained heavily, the road to the top was as slippery as grease, vehicles could not enter. The brothers had to carry each iron bar, each cable coil, and sometimes pull their hands through the stone mortar. It is hard work but everyone says they are trying, not missing the progress, continued Mr. Tran Van Thanh - the team worker.

In Minh Chuan commune (Lao Cai), Power Transmission Company 2 (PTC2) is constructing locations VT106, VT111, VT116 with 3 teams, including 72 engineers and workers. "The terrain is mountainous and rugged, transporting equipment takes a lot of effort. Sometimes, we have to cut each steel pipe and then carry it to the construction site. Power Transmission Company 3 (PTC3) also sent more than 90 people to locations in Minh Xuan commune, deploying both the erection of poles and the preparation of ropes at the same time," said Mr. Nguyen Dang Quang, Head of PTC2 Technical Department.

Forecasting the unstable weather in the coming days, the Executive Board has fully implemented the "4 on-site" motto (on-site command; on-site forces; on-site vehicles and supplies; on-site logistics), ready to respond to natural disasters and heavy rains. The equipment and materials system is distributed evenly and stored safely. All technical staff and commanders are on duty on site, maintaining communication and controlling each construction site.

"Up to now, 100% of foundation construction has been completed, 259/468 pole locations have been erected; The corridor section of the route has been handed over 190/242 anchorages. The entire route is entering the final stage, mobilizing all resources to construct the "shelving room".

It is expected that after August 12, the official cable pulling points will be carried out simultaneously to energize on August 19, Mr. Do Quang Khai, Deputy Director of Power Project Management Board 1, Director of the Project Management Board informed the reporter of Lao Dong Newspaper.

The National Power Transmission Corporation's Trade Union encourages construction support forces

The Party Committee and the Trade Union of the National Power Transmission Corporation (EVNNPT) have just organized a working group to inspect, visit and encourage engineers and workers constructing the Lao Cai - Vinh Yen 500kV transmission line project in Lao Cai and Phu Tho. EVNNPT leaders affirmed that this is a key and urgent project under the direction of the Prime Minister, requiring all construction forces to be highly concentrated, strictly comply with safety and quality assurance. EVNNPT Trade Union calls on each cadre, employee, and worker to promote the spirit of "line 3" - joining hands and being unanimous - to bring the project to the finish line on schedule.

NHÓM PHÓNG VIÊN
RELATED NEWS

Nearly 600 engineers and workers deploy the construction of poles for the 500kV Lao Cai - Vinh Yen transmission line project

|

Nearly 600 engineers and workers urgently deploy the erection of poles for the 500kV Lao Cai - Vinh Yen transmission line project.

Total efforts to bring the Lao Cai - Vinh Yen 500kV transmission line project to the finish line

|

The 500kV Lao Cai - Vinh Yen transmission line project is being accelerated every day to complete on August 19.

Ensuring safety at the Lao Cai - Vinh Yen 500kV transmission line construction site during the rainy and stormy season

|

The 500kV Lao Cai - Vinh Yen transmission line project is facing many difficulties due to the harsh terrain and the Northwest beginning of the rainy and stormy season.

Overcoming the difficult terrain of the Lao Cai - Vinh Yen 500kV transmission line project

|

100 officers and soldiers of Military Region 2 were present at the project's difficult locations to work with construction units to speed up the progress.

Container truck catches fire on My Phuoc - Tan Van road in Ho Chi Minh City

|

HCMC - A container truck caught fire on My Phuoc - Tan Van road. The authorities quickly put out the fire and regulated traffic.

20h News: People complain about the sudden increase in electricity bills in July despite being absent

|

People complain about the sudden increase in electricity bills in July despite being absent; The Ministry of Home Affairs responds to recommendations on the arrangement of concurrent commune accountants...

Early resignation is no longer a strategic move for Ms. Paetongtarn

|

August is considered a turning point in the political fortunes of Ms. Paetongtarn Shinawatra and Mr. Thaksin Shinawatra.

In the next 4 days, many streets in Hanoi will ban vehicles from circulating during certain time frames

|

Hanoi - Some routes will completely ban vehicles from circulating during certain time frames (from August 7 to August 10, 2025).

Nearly 600 engineers and workers deploy the construction of poles for the 500kV Lao Cai - Vinh Yen transmission line project

Kiều Vũ |

Nearly 600 engineers and workers urgently deploy the erection of poles for the 500kV Lao Cai - Vinh Yen transmission line project.

Total efforts to bring the Lao Cai - Vinh Yen 500kV transmission line project to the finish line

Bảo Nguyên |

The 500kV Lao Cai - Vinh Yen transmission line project is being accelerated every day to complete on August 19.

Ensuring safety at the Lao Cai - Vinh Yen 500kV transmission line construction site during the rainy and stormy season

Nhóm PV |

The 500kV Lao Cai - Vinh Yen transmission line project is facing many difficulties due to the harsh terrain and the Northwest beginning of the rainy and stormy season.

Overcoming the difficult terrain of the Lao Cai - Vinh Yen 500kV transmission line project

Nhóm PV |

100 officers and soldiers of Military Region 2 were present at the project's difficult locations to work with construction units to speed up the progress.