Hoa Lu University gradually completed after 15 years of abandonment

NGUYỄN TRƯỜNG |

Ninh Binh - After 15 years of unfinished and abandoned construction, the Hoa Lu University construction project is gradually being completed and put into use.

The Hoa Lu University construction project (Ninh Binh) was approved for investment and construction since 2007 with a total area of ​​25 hectares in Ninh Binh city with a total investment of over 488 billion VND from the state budget.

The project was invested by Hoa Lu University, however, due to difficulties in funding, the project had to be temporarily suspended and abandoned for more than 15 years.

Anh: Nguyen Truong
The construction unit has mobilized more than 300 workers to work continuously to speed up the project's progress. Photo: Nguyen Truong

By 2019, this project was transferred to the Ninh Binh Provincial Civil and Industrial Construction Investment Project Management Board as the investor. To ensure the standards of facilities, meet national standards for higher education institutions, and at the same time meet the objectives of the Hoa Lu University Development Planning Project for the period 2021 - 2025 and orientation to 2030, the Ninh Binh Provincial People's Committee approved the adjustment and supplementation of the Hoa Lu University construction project with a scale from 25.2 hectares to 17.3 hectares.

The total investment of the project after adjustment is nearly 770 billion VND, an increase of nearly 300 billion VND compared to before adjustment from the central budget, national target program capital and Ninh Binh province's budget; the project implementation period is until the end of 2025.

On October 29, speaking with Lao Dong Newspaper reporter, Mr. Tong Duc Long - Deputy Director of the Ninh Binh Province Civil and Industrial Construction Investment Project Management Board - Project Investor - said that the Hoa Lu University construction project is one of 16 key projects identified by Ninh Binh province that need focused leadership and direction for implementation.

According to Mr. Long, after a long period of abandonment, the project was restarted in August 2023. Currently, the Project Management Board and the construction contractor are focusing on all solutions to overcome difficulties, striving to complete the items ahead of schedule, and committed to implementing the progress ahead of schedule.

Theo du kien, du an Truong Dai hoc Hoa Lu se hoan thanh va dua vao su dung vao thang 9.2025. Anh: Nguyen Truong
As planned, Hoa Lu University project will be completed and put into use in September 2025. Photo: Nguyen Truong

With the responsible participation of the investor, the construction unit, 30 technical staff and more than 300 workers working continuously and urgently, up to now, 60% of the work volume has been basically completed.

“From now until the end of 2024, we will strive to complete 80% of the volume and basically complete the items of the headquarters building, two lecture halls, library, medical building, dining room, and practice workshop. Other items such as the gymnasium, conference hall, and swimming pool will complete the rough construction of the first part of the project before September 2025," said Mr. Long.

NGUYỄN TRƯỜNG
RELATED NEWS

Fireworks light up, people flock to Hoan Kiem Lake to welcome the New Year

|

Many people flocked to Hoan Kiem Lake pedestrian street to watch fireworks to welcome the Binh Ngo Lunar New Year 2026.

Touching moment of soldiers celebrating New Year's Eve on the deck for 3 years

|

On New Year's Eve, on the deck of the ship in the middle of the ocean, Senior Lieutenant Nguyen Tien Thanh chatted on the online screen with his family, choked up listening to his mother's instructions.

Ho Chi Minh City residents eagerly await to watch fireworks to welcome the new year Binh Ngo

|

On the evening of the 29th of Tet, thousands of Ho Chi Minh City residents were present at Nguyen Hue flower street, Saigon River Tunnel Park... to have fun and watch fireworks to welcome the new year.

Tho oi!!" by Tran Thanh achieved revenue 1.5 times higher than 3 Vietnamese Tet movies combined

|

The box office race for the 2026 Tet movie is heating up every hour as opening revenue figures are continuously updated. Tran Thanh's "Thỏ ơi!!" leads.

Year-end reunion meal of female workers after 27 years away from home

|

Hung Yen - After 27 years away from home, the year-end meal of Ms. Dao Thi Thinh's family in Tien Lu commune became more crowded, warm and bustling than ever.

Minister Tran Hong Minh inspects transportation, requests to limit delays and cancellations

|

On the afternoon of the 29th of Tet (February 16th of the solar calendar), Minister of Construction Tran Hong Minh inspected aviation, roads, railways, and metro; visited traffic police.

Russia is considering aid options for Cuba

|

The Russian Ambassador said that contact is taking place both directly and through the Russian Embassy in Havana and the Cuban Embassy in Moscow.

Excited atmosphere spread throughout Hanoi streets on the afternoon of the 29th of Tet

|

Hanoi - 29th Tet, many people have chosen to temporarily put aside work, to dress up and enjoy the warm spring atmosphere in the late afternoon of the year.

Dự án bệnh viện hơn 8 năm bỏ hoang ở Bến Tre vẫn chờ để triển khai

Thành Nhân |

Đấu thầu lần 1 không lựa chọn được nhà thầu, Bến Tre đang thực hiện công tác đấu thầu lần 2, dự kiến đến cuối năm 2024 sẽ lựa chọn được nhà thầu để thực hiện dự án bệnh viện đa khoa.

Bắc Ninh rà soát dự án Bệnh viện 1.500 tỉ đồng bỏ hoang

Trần Tuấn |

Tỉnh Bắc Ninh sẽ rà soát dự án Bệnh viện Cuộc sống mới để xem xét việc chấm dứt hoạt động với dự án này.

Rót thêm 120 tỉ đồng để cứu vãn bệnh viện bỏ hoang nhiều năm

NGUYỄN TRƯỜNG |

Sau nhiều năm bỏ hoang, tỉnh Ninh Bình quyết định rót thêm 120 tỉ đồng để cải tạo Bệnh viện Sản - Nhi (cũ) thành Bệnh viện y học Cổ truyền tỉnh Ninh Bình.