Hoa Lu University gradually completed after 15 years of abandonment

NGUYỄN TRƯỜNG |

Ninh Binh - After 15 years of unfinished and abandoned construction, the Hoa Lu University construction project is gradually being completed and put into use.

The Hoa Lu University construction project (Ninh Binh) was approved for investment and construction since 2007 with a total area of ​​25 hectares in Ninh Binh city with a total investment of over 488 billion VND from the state budget.

The project was invested by Hoa Lu University, however, due to difficulties in funding, the project had to be temporarily suspended and abandoned for more than 15 years.

Anh: Nguyen Truong
The construction unit has mobilized more than 300 workers to work continuously to speed up the project's progress. Photo: Nguyen Truong

By 2019, this project was transferred to the Ninh Binh Provincial Civil and Industrial Construction Investment Project Management Board as the investor. To ensure the standards of facilities, meet national standards for higher education institutions, and at the same time meet the objectives of the Hoa Lu University Development Planning Project for the period 2021 - 2025 and orientation to 2030, the Ninh Binh Provincial People's Committee approved the adjustment and supplementation of the Hoa Lu University construction project with a scale from 25.2 hectares to 17.3 hectares.

The total investment of the project after adjustment is nearly 770 billion VND, an increase of nearly 300 billion VND compared to before adjustment from the central budget, national target program capital and Ninh Binh province's budget; the project implementation period is until the end of 2025.

On October 29, speaking with Lao Dong Newspaper reporter, Mr. Tong Duc Long - Deputy Director of the Ninh Binh Province Civil and Industrial Construction Investment Project Management Board - Project Investor - said that the Hoa Lu University construction project is one of 16 key projects identified by Ninh Binh province that need focused leadership and direction for implementation.

According to Mr. Long, after a long period of abandonment, the project was restarted in August 2023. Currently, the Project Management Board and the construction contractor are focusing on all solutions to overcome difficulties, striving to complete the items ahead of schedule, and committed to implementing the progress ahead of schedule.

Theo du kien, du an Truong Dai hoc Hoa Lu se hoan thanh va dua vao su dung vao thang 9.2025. Anh: Nguyen Truong
As planned, Hoa Lu University project will be completed and put into use in September 2025. Photo: Nguyen Truong

With the responsible participation of the investor, the construction unit, 30 technical staff and more than 300 workers working continuously and urgently, up to now, 60% of the work volume has been basically completed.

“From now until the end of 2024, we will strive to complete 80% of the volume and basically complete the items of the headquarters building, two lecture halls, library, medical building, dining room, and practice workshop. Other items such as the gymnasium, conference hall, and swimming pool will complete the rough construction of the first part of the project before September 2025," said Mr. Long.

NGUYỄN TRƯỜNG
RELATED NEWS

Ho Chi Minh City sets off 7-point fireworks on the evening of April 30

|

Ho Chi Minh City will set off fireworks simultaneously at 7 locations on the evening of April 30, from 9pm to 9:15pm.

Measles increases, many people actively get vaccinated before pregnancy

|

Faced with the increasing trend of suspected measles cases, many women planning to become pregnant have proactively vaccinated against the disease, protecting a safe pregnancy.

The case of the former principal collecting 15,000 VND for tutoring and being sentenced to 3 years in prison makes National Assembly deputies heartbroken

|

Referring to the case of the former principal collecting 15,000 VND for tutoring and being sentenced to 3 years in prison, delegate Pham Khanh Phong Lan (Ho Chi Minh City delegation) said that this is a "very painful" case.

Overnight control of forest fires in Lam Dong

|

Lam Dong - Dozens of people were mobilized overnight to extinguish the fire, promptly controlling the forest fire that occurred in Tan Hoi commune.

Iran wants oil tankers passing through the Strait of Hormuz paid by electronic money

|

Iran's new move shows efforts to adapt to financial sanctions pressure and global geopolitical volatility.

Stock market regains green color in last week's session

|

Cash flow returned with the focus being bank stocks, which helped the stock market regain its green color.

Live futsal selection Vietnam vs Indonesia in the semi-finals of the Southeast Asia tournament

|

Live football match of Vietnam futsal team vs Indonesia in the semi-finals of the 2026 Southeast Asian Futsal Championship at 5:00 PM today (April 10).

Dự án bệnh viện hơn 8 năm bỏ hoang ở Bến Tre vẫn chờ để triển khai

Thành Nhân |

Đấu thầu lần 1 không lựa chọn được nhà thầu, Bến Tre đang thực hiện công tác đấu thầu lần 2, dự kiến đến cuối năm 2024 sẽ lựa chọn được nhà thầu để thực hiện dự án bệnh viện đa khoa.

Bắc Ninh rà soát dự án Bệnh viện 1.500 tỉ đồng bỏ hoang

Trần Tuấn |

Tỉnh Bắc Ninh sẽ rà soát dự án Bệnh viện Cuộc sống mới để xem xét việc chấm dứt hoạt động với dự án này.

Rót thêm 120 tỉ đồng để cứu vãn bệnh viện bỏ hoang nhiều năm

NGUYỄN TRƯỜNG |

Sau nhiều năm bỏ hoang, tỉnh Ninh Bình quyết định rót thêm 120 tỉ đồng để cải tạo Bệnh viện Sản - Nhi (cũ) thành Bệnh viện y học Cổ truyền tỉnh Ninh Bình.