The Management Board of Transport Construction Investment Projects of Khanh Hoa province has reported on the construction progress of the Khanh Hoa - Buon Ma Thuot expressway project passing through Khanh Hoa province as of early August 2024.
The above project is expected to have a total of 1,043 cases with 2,256 plots of land affected.
To date, Ninh Hoa Town People's Committee has approved 61 transfers to the Project Management Board, with a total of 703/1,043 payment cases, reaching 67.66%; Disbursed value was more than 198 billion VND.
The locality has handed over the site to the Project Management Board so that contractors can carry out on-site construction seamlessly for 28.17/31.5km, reaching 89.42%. Regarding site clearance work in Ha Thanh resettlement area, up to now, the locality has handed over more than 6.7/nearly 7.2 hectares of land to the Project Management Board, reaching 93.5%.
For construction work, project component 1, Khanh Hoa - Buon Ma Thuot expressway includes 2 packages. Package No. 1 is implementing ground leveling, roadbed, and drainage for 19.6/22km. Construction package No. 2 is being deployed by the contractor to level the ground, roadbed, and drainage. Currently, the project still has some problems such as: There is no land price to compensate for cases affected by the Ha Thanh resettlement area project; Some locations on the route still have land problems...
At a recent site inspection in early August, Secretary of the Khanh Hoa Provincial Party Committee Nguyen Hai Ninh requested the locality to urgently complete site clearance to speed up construction progress. For some locations where there are still local problems affecting the project progress, there needs to be specific solutions to propagate and mobilize people and have appropriate measures to deal with intentional non-compliance. according to regulations.
Along with that, Mr. Nguyen Hai Ninh also requested departments, branches, and localities to quickly research to establish compensation land prices for the Ha Thanh resettlement area. For areas that have been handed over, investors need to request contractors to speed up construction progress, ensuring quality and progress...