Underground metro section Nhon - Hanoi station revealed

HỮU CHÁNH |

Hanoi - The progress of the underground metro section Nhon - Hanoi station has reached 50.27%, in which the TBM excavator has drilled more than 600m underground.

Regarding the overall progress of the Nhon - Hanoi Railway Station metro project, the Hanoi Urban Railway Management Board said that, up to now, the project has achieved 80.3% of the work volume (the elevated section has been completed, the underground section has reached 50.27%).

Currently, the underground ramp is 73.3% completed, Station S9 is 51.7% completed, the Vertical Well is 41.74% completed, Stations S10, S11, S12 (including lane change road and Garage) are 65.3%, 58.97%, 43.3% completed respectively.

Construction activities are taking place at all sites. At station S10, the external structure is being implemented, at station S11, the station base slab is completed, and at station S12, the construction is being carried out to partially fill the southern part of the top slab and the excavation of the transfer slab is underway.

The lane change and garage are starting to implement excavation and construction of the top slab in area I.2, construction of base layer 2/2 of garage I.1 and road restoration in area I.1, underground slope area while implementing excavation and construction of box tunnel structure.

Previously, at the end of July 2024, the TBM (Tunnel Boring Machine) excavator began drilling the underground section of the Nhon - Hanoi station metro line.

TBM1 (named Than Toc) drilled from Station S9 - Kim Ma at a depth of 17.8m. To date, TBM1 has constructed 631m of tunnel, 420 tunnel lining rings have been installed.

Currently, this excavator is stopped at the Well, one of the important items of the project. When TBM1 drilled about 900m, TBM2 (named Bold) started drilling.

Two robots dug two parallel tunnels from Station S9 - Kim Ma Station to Station S12 - Tran Hung Dao Station. The tunnel digging speed depends on the surrounding geological properties as well as logistics factors, to minimize the impact on above-ground structures.

According to plan, the 4km underground excavation of the Nhon - Hanoi station metro line will be completed in October 2025.

Cong truong thi cong doan di ngam Metro Nhon - ga Ha Noi. Anh: Huu Chanh
Construction site of the underground section of the Nhon - Hanoi Railway Station Metro. Up to now, the tunnel boring machine has traveled 631m, corresponding to the location of lane 391 Kim Ma. Photo: Huu Chanh
420 vong vo ham da duoc lap dat. Robot TBM khoan toi dau, lan luot vo ham cung se duoc lap toi do. Song song, cac hang muc khac cua cong trinh cung duoc hoan thien theo phuong phap cuon chieu. Anh: Huu Chanh
420 tunnel lining rings have been installed. As the TBM robot drills, the tunnel lining will be installed one by one. In parallel, other items of the project will also be completed in a rolling manner. Photo: Huu Chanh
Sau khi van chuyen he thong vach ham vao vi tri lap dat, he thong xe cong vu se co nhiem vu khac la nhan bun thai de van chuyen ra ben ngoai. Anh: Huu Chanh
After transporting the tunnel wall system to the installation location, the service vehicle system will have another task of receiving the waste sludge for transport outside. Photo: Huu Chanh
Dat khoan duoc se tap ket tai be chua va van chuyen di.
The mud will be collected in the tank and transported away. Photo: Huu Chanh
50 ky su, cong nhan co mat tai ga ngam tuyen duong sat Nhon - ga Ha Noi de trien khai thi cong van hanh may TBM, canh tay robot lap vo ham, thay dau cat…
150 engineers and workers were present at the underground station of the Nhon - Hanoi railway line to deploy the construction and operation of the TBM machine, the robot arm to install the tunnel lining, replace the cutting head... Photo: Huu Chanh
Cong nhan dang lap duong ray tuyen duong sat do thi Nhon - ga Ha Noi.
Workers are installing rails on the underground section of the Nhon - Hanoi Railway Station urban railway line. Photo: Huu Chanh
Duong ong dan khong khi, nuoc sach duoc dan vao ham.
Air and clean water pipes are led into the tunnel. Photo: Huu Chanh
a
Directional and warning signs at the underground construction site. Photo: Huu Chanh
Viec thi cong khoan ham se duoc tien hanh voi su can trong va giam sat nghiem ngat de dam bao an toan cho cac cong trinh hien huu va dam bao chat luong cho cong trinh dang thi cong. Anh: Huu Chanh
Tunnel boring will be carried out with caution and strict supervision to ensure the safety of existing structures and the quality of the works under construction. Photo: Huu Chanh
Du kien may TBM thu 2 se di vao hoat dong sau khi may TBM thu nhat khoan duoc 900m.
The second TBM is expected to be put into operation after the first TBM has drilled 900m. The pair of TBMs were specifically designed for the Nhon - Hanoi Railway Station project. The machines are manufactured by Herrenkecht (Germany), are more than 100m long, and weigh about 850 tons. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

Research on expanding Nhon - Hanoi station metro to Hoang Mai

|

The EU has mobilized 10 million euros to finance preparations for the extension of the Nhon - Hanoi Railway Station metro line to Hoang Mai district (Hanoi).

Hanoi holds commercial operation ceremony of Nhon - Hanoi Railway Station metro

|

On the morning of November 9, the Hanoi People's Committee held a commercial operation ceremony for the elevated section of the Nhon - Hanoi Railway Station metro line.

Russia reveals retaliation for Western asset seizures

|

The West has frozen $300 billion in Russian assets since the Ukraine conflict escalated in February 2022.

Hanoi finalizes plan to handle illegal recruitment of 170 students

|

The Hanoi Department of Education and Training has a plan to transfer 174 10th grade students illegally recruited by To Hien Thanh High School to Van Lang High School.

By the end of 2023, there will be about 33,000 workers with occupational diseases

|

On the morning of November 21, the Vietnam General Confederation of Labor held a meeting of the Research Group to develop the Project "Building a cultural movement and labor safety among workers".

Proposal for priority housing sale for officers and soldiers

|

The draft Resolution on piloting the implementation of commercial housing projects mentions the case of giving priority to selling houses to officers and soldiers of the armed forces.

2024 National Volleyball Championship Phase 2 Men's Group Prediction

|

Today (November 21), the second phase of the men's event at the 2024 National Volleyball Championship begins.

Ho Chi Minh City announces Ben Thanh - Suoi Tien Metro ticket prices

|

On November 21, the Ho Chi Minh City People's Committee issued a decision on ticket prices for public passenger transport services by train on Metro Line 1 (Ben Thanh - Suoi Tien).

Research on expanding Nhon - Hanoi station metro to Hoang Mai

Tô Thế |

The EU has mobilized 10 million euros to finance preparations for the extension of the Nhon - Hanoi Railway Station metro line to Hoang Mai district (Hanoi).

Hanoi holds commercial operation ceremony of Nhon - Hanoi Railway Station metro

Thế Kỷ |

On the morning of November 9, the Hanoi People's Committee held a commercial operation ceremony for the elevated section of the Nhon - Hanoi Railway Station metro line.

Metro Nhổn - Cầu Giấy gặp sự cố kỹ thuật phải dừng tàu

Minh Hạnh |

Do sự cố kỹ thuật đã khiến tuyến metro Nhổn - Cầu Giấy dừng gần 1 giờ, nguyên nhân sự cố trên là do lỗi hệ thống điện tại ga Lê Đức Thọ.