Underground metro section Nhon - Hanoi station revealed

HỮU CHÁNH |

Hanoi - The progress of the underground metro section Nhon - Hanoi station has reached 50.27%, in which the TBM excavator has drilled more than 600m underground.

Regarding the overall progress of the Nhon - Hanoi Railway Station metro project, the Hanoi Urban Railway Management Board said that, up to now, the project has achieved 80.3% of the work volume (the elevated section has been completed, the underground section has reached 50.27%).

Currently, the underground ramp is 73.3% completed, Station S9 is 51.7% completed, the Vertical Well is 41.74% completed, Stations S10, S11, S12 (including lane change road and Garage) are 65.3%, 58.97%, 43.3% completed respectively.

Construction activities are taking place at all sites. At station S10, the external structure is being implemented, at station S11, the station base slab is completed, and at station S12, the construction is being carried out to partially fill the southern part of the top slab and the excavation of the transfer slab is underway.

The lane change and garage are starting to implement excavation and construction of the top slab in area I.2, construction of base layer 2/2 of garage I.1 and road restoration in area I.1, underground slope area while implementing excavation and construction of box tunnel structure.

Previously, at the end of July 2024, the TBM (Tunnel Boring Machine) excavator began drilling the underground section of the Nhon - Hanoi station metro line.

TBM1 (named Than Toc) drilled from Station S9 - Kim Ma at a depth of 17.8m. To date, TBM1 has constructed 631m of tunnel, 420 tunnel lining rings have been installed.

Currently, this excavator is stopped at the Well, one of the important items of the project. When TBM1 drilled about 900m, TBM2 (named Bold) started drilling.

Two robots dug two parallel tunnels from Station S9 - Kim Ma Station to Station S12 - Tran Hung Dao Station. The tunnel digging speed depends on the surrounding geological properties as well as logistics factors, to minimize the impact on above-ground structures.

According to plan, the 4km underground excavation of the Nhon - Hanoi station metro line will be completed in October 2025.

Cong truong thi cong doan di ngam Metro Nhon - ga Ha Noi. Anh: Huu Chanh
Construction site of the underground section of the Nhon - Hanoi Railway Station Metro. Up to now, the tunnel boring machine has traveled 631m, corresponding to the location of lane 391 Kim Ma. Photo: Huu Chanh
420 vong vo ham da duoc lap dat. Robot TBM khoan toi dau, lan luot vo ham cung se duoc lap toi do. Song song, cac hang muc khac cua cong trinh cung duoc hoan thien theo phuong phap cuon chieu. Anh: Huu Chanh
420 tunnel lining rings have been installed. As the TBM robot drills, the tunnel lining will be installed one by one. In parallel, other items of the project will also be completed in a rolling manner. Photo: Huu Chanh
Sau khi van chuyen he thong vach ham vao vi tri lap dat, he thong xe cong vu se co nhiem vu khac la nhan bun thai de van chuyen ra ben ngoai. Anh: Huu Chanh
After transporting the tunnel wall system to the installation location, the service vehicle system will have another task of receiving the waste sludge for transport outside. Photo: Huu Chanh
Dat khoan duoc se tap ket tai be chua va van chuyen di.
The mud will be collected in the tank and transported away. Photo: Huu Chanh
50 ky su, cong nhan co mat tai ga ngam tuyen duong sat Nhon - ga Ha Noi de trien khai thi cong van hanh may TBM, canh tay robot lap vo ham, thay dau cat…
150 engineers and workers were present at the underground station of the Nhon - Hanoi railway line to deploy the construction and operation of the TBM machine, the robot arm to install the tunnel lining, replace the cutting head... Photo: Huu Chanh
Cong nhan dang lap duong ray tuyen duong sat do thi Nhon - ga Ha Noi.
Workers are installing rails on the underground section of the Nhon - Hanoi Railway Station urban railway line. Photo: Huu Chanh
Duong ong dan khong khi, nuoc sach duoc dan vao ham.
Air and clean water pipes are led into the tunnel. Photo: Huu Chanh
a
Directional and warning signs at the underground construction site. Photo: Huu Chanh
Viec thi cong khoan ham se duoc tien hanh voi su can trong va giam sat nghiem ngat de dam bao an toan cho cac cong trinh hien huu va dam bao chat luong cho cong trinh dang thi cong. Anh: Huu Chanh
Tunnel boring will be carried out with caution and strict supervision to ensure the safety of existing structures and the quality of the works under construction. Photo: Huu Chanh
Du kien may TBM thu 2 se di vao hoat dong sau khi may TBM thu nhat khoan duoc 900m.
The second TBM is expected to be put into operation after the first TBM has drilled 900m. The pair of TBMs were specifically designed for the Nhon - Hanoi Railway Station project. The machines are manufactured by Herrenkecht (Germany), are more than 100m long, and weigh about 850 tons. Photo: Huu Chanh
HỮU CHÁNH
RELATED NEWS

Research on expanding Nhon - Hanoi station metro to Hoang Mai

|

The EU has mobilized 10 million euros to finance preparations for the extension of the Nhon - Hanoi Railway Station metro line to Hoang Mai district (Hanoi).

Hanoi holds commercial operation ceremony of Nhon - Hanoi Railway Station metro

|

On the morning of November 9, the Hanoi People's Committee held a commercial operation ceremony for the elevated section of the Nhon - Hanoi Railway Station metro line.

Ministry of Education announces university admission regulations for 2026

|

The Ministry of Education and Training has just announced the university admission regulations for 2026 with many new points related to the number of aspirations, academic records, IELTS scores,...

Before Tet, workers are paid a part of their salary by Phuc Hung Mechanical and Electrical Joint Stock Company

|

Before the 2026 Lunar New Year, some people whose salaries were owed by Phuc Hung Mechanical and Electrical Joint Stock Company were partially paid.

Hanoi Police at risk of being defeated in AFC Champions League

|

Hanoi Police may be defeated for violating player registration regulations at AFC Champions League Two.

Nearly 200 workers in Son La have received full salaries

|

Son La - Nearly 200 workers owed late construction costs for the Chieng Khoong Inter-level Boarding School Project have received full wages.

The aura of the football field nurtures the personal brand of the player

|

With a breakthrough tournament in their football career, many football players have changed their lives and have a full life.

Vietnamese workers abroad eagerly welcome Tet in homesickness

|

Every time peach branches and apricot branches begin to show off their colors in their homeland, in a distant corner of the sky, many Vietnamese workers celebrate Tet with a feeling of emotion that is hard to name.

Research on expanding Nhon - Hanoi station metro to Hoang Mai

Tô Thế |

The EU has mobilized 10 million euros to finance preparations for the extension of the Nhon - Hanoi Railway Station metro line to Hoang Mai district (Hanoi).

Hanoi holds commercial operation ceremony of Nhon - Hanoi Railway Station metro

Thế Kỷ |

On the morning of November 9, the Hanoi People's Committee held a commercial operation ceremony for the elevated section of the Nhon - Hanoi Railway Station metro line.

Metro Nhổn - Cầu Giấy gặp sự cố kỹ thuật phải dừng tàu

Minh Hạnh |

Do sự cố kỹ thuật đã khiến tuyến metro Nhổn - Cầu Giấy dừng gần 1 giờ, nguyên nhân sự cố trên là do lỗi hệ thống điện tại ga Lê Đức Thọ.