Gianh Bridge Project, a new highlight for Quang Binh traffic

CÔNG SÁNG |

In the chilly air of the day before Tet, workers at Gianh bridge construction site are enthusiastically working, determined to complete the project on schedule.

Safety is our top priority

The Gianh Bridge construction project, connecting an important section of the Gianh River on National Highway 1, is becoming a highlight in the transport infrastructure in Quang Binh. The project starts at Km624+799 in Ba Don town and ends at Km626+901 in Ha Trach commune, Bo Trach district. The bridge is nearly 750m long, promising to enhance transport connectivity and economic development in the region.

The project road section is designed with a roadbed width of 20.5m, including 4 lanes for motor vehicles. The new bridge is 12m wide, including 2 lanes for motor vehicles and 2 lanes for non-motor vehicles. This modern design ensures the ability to serve future traffic.

According to Mr. Vu Van Hoa - Officer of Cau Gianh Management Board of Dat Phuong Group Joint Stock Company. Up to now, the project is constructing bored piles divided into 2 construction teams, while the 3rd team focuses on girder construction. It is expected that after the Lunar New Year holiday, the Project Management Board will mobilize maximum human resources and equipment for 4 teams to construct the pedestal, pier body and cantilever.

The project management board pays special attention to labor safety. Right from the start, workers are thoroughly trained in safety, provided with labor protection equipment and necessary equipment. Before each shift, workers are clearly assigned and reminded of risks that may arise during the construction process.

At the construction site, the management board arranges nutritious meals to ensure the health of all workers and laborers. These are necessary steps to maintain construction progress and efficiency.

In the days before Tet, the atmosphere at Gianh Bridge construction site becomes even more bustling as the team of workers and management team work together to complete the proposed items.

Mr. Vu Van Hoa shared: "We not only focus on progress but also pay special attention to the lives of workers during the days before Tet."

According to Mr. Hoa, the management board has coordinated to organize special meals at the end of the year, bringing the Tet atmosphere to the construction site.

Contribute to economic and social development

Mr. Vu Duy Hinh (born in 1974, from Hai Duong), a construction worker at Gianh Bridge construction site, shared that workers here were instructed to be provided with full equipment from the beginning.

"At the construction site, we always focus on ensuring absolute safety while working. We understand that every small mistake can affect the progress and safety of the project. We all have the same goal of completing the project on schedule," said Mr. Hinh.

Mr. Hinh added that not only does the management ensure safety at work, it also cares about the lives of the workers. Meals are prepared with full nutrition, and the resting place is also very clean and comfortable. This helps workers feel secure in their work and devote themselves to the project.

He expressed his hope that this project will be a milestone for many workers to be recognized for their efforts and have more opportunities to develop in the future.Gianh Bridge is not only a traffic connection but also a testament to the collective efforts of the whole team.
Gianh Bridge project is an important step forward in developing traffic infrastructure in Quang Binh.The new bridge not only helps connect traffic between regions but also acts as an economic link, contributing to promoting outstanding development for the entire region.

CÔNG SÁNG
TIN LIÊN QUAN

Traffic project to relieve congestion on many roads in Hanoi

|

Hanoi - The temporary opening of a 1.9km section of the Le Quang Dao extended road construction project helps reduce traffic pressure on some roads around the area.

More than 80 households draw lots for resettlement of expressway project in Dong Nai

|

Dong Nai - The first 80 households in Bien Hoa City were selected for resettlement land to build the Bien Hoa - Vung Tau expressway.

Union Newsletter: Pension Transfer Schedule for April 2025

|

Today's union newsletter includes: Pension transfer schedule for April 2025 via ATM; Difficulty in recruiting workers, businesses in Hai Phong mobilize overtime...

Volleyball players regrettably absent from the Hung Vuong Cup 2025

|

Considered an "All Stars" tournament, the Hung Vuong Cup 2025 volleyball tournament still lacks some regrettable faces.

Progress of implementation of 2 social housing projects in Dong Anh

|

Hanoi - The city has established a working group to evaluate the implementation registration documents and approve the documents inviting interest in 2 social housing construction projects in Dong Anh district.

Dai Ngai 2 Bridge is ahead of schedule, waiting for opening date

|

Soc Trang - Dai Ngai 2 Bridge is being urgently completed to open to technical traffic in time for the April 30 holiday.

List of 185 countries and territories subject to US counterpart tax

|

President Donald Trump announced the US counterpart tariffs that 185 countries and territories face.

Traffic project to relieve congestion on many roads in Hanoi

HỮU CHÁNH |

Hanoi - The temporary opening of a 1.9km section of the Le Quang Dao extended road construction project helps reduce traffic pressure on some roads around the area.

More than 80 households draw lots for resettlement of expressway project in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - The first 80 households in Bien Hoa City were selected for resettlement land to build the Bien Hoa - Vung Tau expressway.

Chỉ đạo "nóng" về dự án đường Vành đai 2,5, vốn 1.300 tỉ

Anh Tuấn |

Chủ tịch Hà Nội chỉ đạo tháo gỡ cho dự án đường giao thông khu tưởng niệm danh nhân Chu Văn An và dự án đầu tư xây dựng đường Vành đai 2,5.