Long Bien-Gia Lam bridge project faces major obstacles

HỮU CHÁNH |

Hanoi - The road bridge project across the Duong River connecting Long Bien with Gia Lam, with an investment capital of nearly 590 billion VND, cannot be completed by 2025 due to delays in site handover.

In July 2023, the road bridge under the Duong River waterway upgrade project started construction. In September, the contractor began construction on the site.

The project starts at the old Duong bridge intersection on Ngo Gia Tu street, Long Bien district; ends at the intersection between Ha Huy Tap street and Phan Dang Luu street, Gia Lam district, about 100m downstream from the old Duong bridge.

Cau duong bo vuot song Duong noi quan Long Bien voi huyen Gia Lam (Ha Noi) khi hoan thanh. Anh: Don vi thiet ke
The road bridge over Duong River connecting Long Bien District with Gia Lam District (Hanoi) when completed. Photo: Design unit
Vi tri xay dung cau duong bo vuot song Duong. Anh: Huu Chanh
Construction site of the road bridge across the Duong River. Photo: Huu Chanh

The road bridge is 382m long, combined with cable-stayed, 18.5m wide, with clearance under the bridge of 4.75m. The approach road is 318m long, with a design speed of 80km/h, 6 motor lanes, 2 mixed lanes, and in the immediate phase, the scale will be 4 motor lanes.

The project has a total investment of nearly 590 billion VND, invested by the Railway Project Management Board, Ministry of Transport. When completed, the project will help improve traffic conditions connecting across the Duong River on the main artery north of Hanoi.

After more than 15 months of construction, the road bridge project across the Duong River has reached about 35% progress. According to the Lao Dong Newspaper's reporter at the project site in late December 2024, the contractor is completing the construction of the T5 and T4 pillars.

This is the most difficult part of the road bridge project across the Duong River because the contractor must construct in an area with complex geology, requiring high technology and construction techniques.

With the site already handed over for construction, the contractor representative said that construction will be completed in about 2 months.

Cau duong bo vuot song Duong dat 35% tien do sau hon 15 thang thi cong. Anh: Huu Chanh
The road bridge over the Duong River has reached 35% progress after more than 15 months of construction. Photo: Huu Chanh
Mot so tru cau dang duoc thi cong hoan thien. Anh: Huu Chanh
Barges and machinery are gathered to construct project items. Photo: Huu Chanh

The road bridge project across the Duong River needs to build 3 more piers, 2 abutments and approach roads at both ends of the bridge before completing the bridge deck, towers and cables. However, some items can only be implemented when the contractor is handed over the site by the locality.

A representative of the Railway Project Management Board (Ministry of Transport - investor) said that to implement the road bridge project across the Duong River, Long Bien district and Gia Lam district will have to reclaim a total land area of ​​about 5 hectares.

So far, the two localities have only cleared a portion of the public land. The remaining area, which involves about 130 households, of which 110 are resettled, has not yet been cleared.

a
Two piers of the bridge in the middle of the Duong River are being completed. Photo: Huu Chanh
a
A residential area in Duc Giang ward (Long Bien district) located within the construction boundary of the road bridge over Duong river has not yet been cleared. Photo: Huu Chanh

Initially, Long Bien and Gia Lam districts were expected to hand over the entire cleared land for the project by July 2025, but due to Hanoi City having to adjust and supplement the resettlement sub-project, this timeline was forced to be postponed.

According to the plan, the resettlement project will be implemented in the period of 2026-2028. With the above progress, the road bridge of the Duong River waterway upgrade project will be at least 3 years behind the approved schedule of completion in 2025.

HỮU CHÁNH
RELATED NEWS

Two new roads to be expanded and built in Soc Son and Dan Phuong

|

Hanoi plans to reclaim about 676,000 square meters of land to expand National Highway 3 through Soc Son and build Tay Thang Long Road in Dan Phuong, with a capital of nearly VND2,800 billion.

27-span flyover on Hanoi's Ring Road 4 to be completed in 2025

|

Hanoi - It is expected that by the second quarter of 2025, the North-South railway overpass, nearly 590m long, with 27 spans (part of the Ring Road 4 parallel road project through Me Linh) will be completed.

Hai Tien sea dyke seriously subsides: No basis to confirm due to natural disaster

|

Thanh Hoa - Regarding the incident of Hai Tien sea dyke subsidence, functional agencies have initially identified the initial cause and responsibilities of relevant parties.

List of 12 members participating in the Standing Committee of the 11th Central Committee of the Vietnam Fatherland Front

|

On the morning of May 13, a press conference was held to inform about the results of the 11th National Congress of the Vietnam Fatherland Front, term 2026 - 2031.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Two new roads to be expanded and built in Soc Son and Dan Phuong

HỮU CHÁNH |

Hanoi plans to reclaim about 676,000 square meters of land to expand National Highway 3 through Soc Son and build Tay Thang Long Road in Dan Phuong, with a capital of nearly VND2,800 billion.

Hà Nội chính thức chốt phương án, vị trí xây cầu Thượng Cát

Anh Tuấn |

UBND TP Hà Nội đã có Quyết định số 6316 phê duyệt phương án, vị trí cầu Thượng Cát và đường hai đầu cầu kết nối phường Thượng Cát.

27-span flyover on Hanoi's Ring Road 4 to be completed in 2025

NHÓM PV |

Hanoi - It is expected that by the second quarter of 2025, the North-South railway overpass, nearly 590m long, with 27 spans (part of the Ring Road 4 parallel road project through Me Linh) will be completed.