1,300 billion VND road in Hanoi stalls before the finish line

HỮU CHÁNH |

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, has stopped construction since 2020 when it reached over 90% of the volume and there is no date yet for resumption of construction.

The construction project of Ring Road 2.5, Dam Hong - National Highway 1A section (Hoang Mai district, Hanoi) is invested in the form of BT (build - transfer) contract with a length of 2.06km, total investment of more than 1,300 billion VND.

The project started in 2014, but had to be temporarily suspended in 2020 when it reached over 90% of the volume. The reason was due to many difficulties in site clearance and the BT contract expired.

a
The starting point of the project is at Dam Hong (border area between Thanh Xuan and Hoang Mai districts, Hanoi). Photo: Huu Chanh

Regarding project progress, package 1 has been constructed with a volume of about 1,270m/1,381.7m.

Many items such as wastewater drainage, rainwater drainage, roadbed have been completed or are under construction, including sections that have been constructed to the crushed stone layer and asphalt concrete pavement.

a
The construction site is unfinished and has been suspended for many years. Photo: Huu Chanh

Package No. 2 of the bridge over the Lu River has constructed 20 bored piles, all bridge piers and cast all beams. The remaining items are under construction.

The construction items were exposed to the sun and rain, the rusty iron and steel made many people in the area feel sorry.

Residents of Dinh Cong Ward (Hoang Mai District) are upset because the project has been delayed for many years, while the population in this area is quite dense, making travel difficult. Besides, there is concern about environmental pollution.

"The project being "shelved" like this will lead to many consequences. I just hope the government will soon have a definitive solution" - said Mr. Le Huy Khoa (38 years old).

a
L3 bridge over Lu river has not been completed for many years, only the iron frame remains. Photo: Huu Chanh

According to the investigation of Lao Dong Newspaper reporters, over the past 4 years, the project enterprise has been forced to temporarily suspend all construction activities on the road while waiting for the Hanoi People's Committee to extend the contract implementation period.

By February 2024, Hoang Mai District authorities had completed site clearance for the last 14 households within the project area. However, this area has not been handed over to the investor.

Currently, construction machinery is still "shelved" waiting for the BT contract extension, while the Ring Road 2.5 underpass project, which started construction in October 2022 with an investment of more than 770 billion VND, is ensuring completion in 2025.

It is very likely that the Ring Road 2.5 tunnel project will "go behind and come back first" if the Ring Road 2.5 construction project (Dam Hong - National Highway 1A section) does not soon have its contract extended and construction urgently started.

a
People in this area have to temporarily travel through unfinished construction areas without any traffic organization plan. Photo: Huu Chanh
a
The end point of the project will connect to the Ring Road 2.5 - Giai Phong underpass. Photo: Huu Chanh

The investor said that it is continuing to submit documents to extend the contract with the Hanoi People's Committee. If approved in the fourth quarter of 2024 and the Hoang Mai District People's Committee hands over the remaining site, the unit will focus all its efforts on construction, striving to basically complete and connect with the Ring Road 2.5 underpass project in October 2025.

HỮU CHÁNH
TIN LIÊN QUAN

Hà Nội tập trung làm 3 dự án giao thông lớn ở phía Nam

HỮU CHÁNH |

Hà Nội đang tập trung triển khai 3 dự án quan trọng ở phía Nam, góp phần hoàn thiện hạ tầng giao thông theo quy hoạch, phát triển kinh tế - xã hội Thủ đô.

Hà Nội mở rộng trục huyết mạch lên 50m, gấp 5 lần đường cũ

HỮU CHÁNH |

Hà Nội - Tuyến đường huyết mạch có mặt cắt ngang 8-10m sắp được mở rộng lên 50m giúp giảm ùn tắc, tăng kết nối liên vùng.

Nút giao nổi tiếng ùn tắc ở Hà Nội chờ cầu vượt giải cứu

Hữu Chánh |

Hà Nội - Khổ sở với ùn tắc mỗi ngày tại nút giao đường Phạm Tu - Tỉnh lộ 70, người dân mong công trình cầu vượt tại đây sớm được thi công hoàn thiện.

Giờ thứ 9: Đứa con bất hạnh - Phần 1

Nhóm PV |

Giờ thứ 9 - Bé gái trong câu chuyện ngày hôm nay phải ở với bố dượng của mình sau khi mẹ đẻ ly hôn. Đứa bé sẽ lớn lên như thế nào và có cuộc sống ra sao?

Diễn biến mới vụ hóa đơn nước cao bất thường ở Thái Bình

TRUNG DU |

Thái Bình - Trước hàng loạt hành động khó hiểu từ phía Công ty CP Nước sạch Thái Bình, khách hàng cho biết sẽ tiếp tục kiến nghị đến các cơ quan chức năng.

Phụ huynh cho con đi học trở lại sau khi nhà trường nhận sai

NGUYỄN TRƯỜNG |

Ninh Bình - Sau 2 ngày cho con nghỉ học để làm rõ thông tin nhà trường dùng sữa hết hạn cho học sinh uống, ngày 23.10, các phụ huynh đã cho con đi học trở lại.

Biển Đông vẫn là điểm nóng với các tranh chấp lãnh thổ

Ngọc Vân |

Biển Đông vẫn là điểm nóng với các vấn đề tranh chấp lãnh thổ và khác biệt về yêu sách biển, cùng với tình hình quân sự hoá tại khu vực.

Giám đốc Sở ở Hà Nam lý giải về 130 lần trễ hạn xử lý hồ sơ

Thu Giang |

Ông Bùi Đức Thái - Giám đốc Sở Tư pháp Hà Nam cho rằng, việc trễ hạn 130 lần xử lý hồ sơ là do lỗi trùng lặp trên hệ thống.

Hanoi focuses on 3 major transport projects in the South

HỮU CHÁNH |

Hanoi is focusing on implementing three important projects in the South, contributing to completing the planned traffic infrastructure and developing the capital's economy and society.

Hanoi expands main artery to 50m, 5 times wider than old road

HỮU CHÁNH |

Hanoi - The main artery with a cross-section of 8-10m is about to be expanded to 50m to help reduce congestion and increase inter-regional connectivity.

Famous traffic jam at Hanoi intersection waiting for overpass to rescue

Hữu Chánh |

Hanoi - Suffering from daily traffic jams at the intersection of Pham Tu Street and Provincial Road 70, people hope that the overpass project here will be completed soon.