6.7km road connecting 2 highways in Hanoi after nearly 1 year of construction

HỮU CHÁNH |

Most of the land has not been handed over, forcing the contractor to only construct a small area of ​​the road connecting two expressways in Hanoi, with a capital of 5,200 billion VND.

Returning to the construction site of the Thang Long Avenue expressway, the section connecting National Highway 21 to the Hanoi - Hoa Binh expressway in early September 2024, Lao Dong Newspaper reporters noted that the project had not made much progress compared to 4 months ago (May 2024).

After nearly a year of construction, the contractor has only started construction on a small area in Tien Xuan commune (Thach That district, Hanoi). At the construction site, there are only a few machines and workers.

The main tasks at the construction site are mainly the construction of bored piles and casting concrete components for the construction of the overpass. The remaining section of the route, which is more than 6km long, has not been constructed due to lack of land.

The investment project to build the Thang Long Avenue expressway, the section connecting National Highway 21 to Hanoi - Hoa Binh expressway, will start construction in October 2023.

The project has a total investment of VND5,249 billion, invested by the Hanoi Civil Construction Investment Project Management Board. The city plans to complete the 6.7km long road with a cross-section of 120-180m by 2026.

According to the assessment of the Hanoi People's Committee, the implementation of the project investment will gradually complete the entire Hanoi - Hoa Binh highway; develop and expand the capital Hanoi to the West, meeting the rapidly increasing transportation demand; and be the driving force for the development of Hoa Lac satellite urban area and the western satellite urban chain.

The Hanoi Civil Construction Investment Project Management Board said that to implement the project, about 105.8 hectares of land must be reclaimed and cleared. To date, the Project Management Board has received 7.6 hectares of land in Tien Xuan commune (Thach That district).

Here, the contractor is currently implementing the construction of bored piles (45/68 piles), casting concrete components (13/128 beams) to serve the construction of the overpass of the planned road Km2+522.5 (belonging to package No. 31).

Currently, the investor and contractor are waiting for the site to continue construction. However, with the large volume of project site, if it is not handed over soon, it will be difficult to ensure the project progress to be completed in 2026 as required by the Hanoi People's Committee.

Some images recorded at the project site:

Sau mot nam thi cong, nha thau moi chi trien khai xay dung tren khu dat thuoc xa, huyen Thach That, Ha Noi. Anh: Huu Chanh
After nearly a year of construction, the project has only been implemented on land in Tien Xuan commune, Thach That district, Hanoi. Photo: Huu Chanh
Cac cong viec chinh tren cong truong chu yeu la thi cong hang muc coc khoan nhoi, duc cau kien betong phuc vu thi cong hang muc cau vuot. Anh: Huu Chanh
The main tasks at the construction site are mainly bored pile construction and concrete casting for the overpass construction. Photo: Huu Chanh
a
A flyover pier in the process of completion is the most obvious result of this project after nearly 1 year of construction. Photo: Huu Chanh
a
Machinery gathered at the project site. Photo: Huu Chanh
a
To date, the investor has only received 7.6/105.8 hectares from the locality and is waiting for the site to continue construction. Photo: Huu Chanh
Hien doan 6,7 km tu dai lo Thang Long di cao toc Ha Noi - Hoa Binh la duong dong bang nho hep, xuong cap, gay kho khan cho phuong tien
Thang Long Avenue route to Hanoi - Hoa Binh expressway has many means of transport. Photo: Huu Chanh
Du an hoan thanh (du kien nam 2026) se giup thong suot tuyen cao toc tu dai lo Thang Long di Hoa Binh, hoan thien quy hoach mang luoi cao toc tu Ha Noi di Hoa Binh.
The project's completion (expected in 2026) will help smooth the expressway from Thang Long Avenue to Hoa Binh, completing the planning of the expressway network from Hanoi to Hoa Binh. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

Đường rộng 40m nối hai quận Hà Nội trước tháng thông xe

HỮU CHÁNH |

Hà Nội - Dự án đường Lê Quang Đạo kéo dài nối quận Nam Từ Liêm với Hà Đông sắp hoàn thành, dự kiến thông xe kỹ thuật ngày 10.10 sau gần 2 năm thi công.

Mong chờ dự án mở đường rộng 80m, vốn gần 19.000 tỉ đồng ở Hà Nội

HỮU CHÁNH |

Người Hà Nội mong dự án mở rộng Quốc lộ 21 sớm được phê duyệt chủ trương đầu tư và triển khai thi công để giải quyết tình trạng ùn tắc, tai nạn giao thông.

Cảnh tượng đìu hiu công trường dự án chống ùn tắc ở Hà Nội

HỮU CHÁNH |

Hà Nội - Công trường dự án "giải cứu" ùn tắc cửa ngõ phía Nam thời gian qua rơi vào cảnh đìu hiu, thi công cầm chừng vì thiếu mặt bằng.

Tăng trợ cấp thất nghiệp lên 75% giúp người lao động yên tâm

MINH HÀ - HOÀNG XUYẾN |

Tăng mức hưởng trợ cấp thất nghiệp lên 75% lương bình quân là mong mỏi của rất nhiều người lao động.

Ngôi làng hơn 20 năm bị “bỏ quên” vì quy hoạch treo

Hoàng Bin |

Quảng Nam - Con đường đất bụi bặm, quanh co, dẫn vào khu nhà cấp 4 lụp sụp - là nơi cư ngụ của 28 hộ dân “bị bỏ quên” trong vùng quy hoạch treo suốt 20 năm qua.

Barcelona mất người, thua trận ra quân tại Champions League

tam nguyên |

Eric Garcia sớm nhận thẻ đỏ khiến Barcelona không thể có điểm trên sân AS Monaco.

Nỗ lực định hình tên tuổi từ cái bóng “ngôi sao nhí”

Ngọc Dủ |

Thị trường nhạc Việt từng có không ít sân chơi dành cho các tài năng nhí, nổi bật trong số đó phải kể đến Thần tượng âm nhạc nhí, Giọng hát Việt nhí... Đây được xem là bệ phóng cho không ít tài năng trẻ phát triển và theo đuổi sự nghiệp của mình.

Chợ đêm Ninh Kiều sáng đèn trở lại sau thời gian tạm dừng

VÂN HI - NGÂN TÂM |

Cần Thơ - Người dân bày tỏ sự phấn khởi khi chợ đêm Ninh Kiều đã hoạt động trở lại.

40m wide road connecting two districts of Hanoi before opening month

HỮU CHÁNH |

Hanoi - The Le Quang Dao extended road project connecting Nam Tu Liem district with Ha Dong is nearing completion, expected to open to technical traffic on October 10 after nearly 2 years of construction.

Looking forward to the project of opening an 80m wide road with a capital of nearly 19,000 billion VND in Hanoi

HỮU CHÁNH |

Hanoians hope that the National Highway 21 expansion project will soon be approved for investment and construction to resolve traffic congestion and accidents .

Desolate scene at the construction site of the anti-congestion project in Hanoi

HỮU CHÁNH |

Hanoi - The construction site of the project to "rescue" traffic jams at the southern gateway has recently fallen into a state of disrepair, with construction at a standstill due to lack of land .