Traffic roads in Quang Tri are stuck with land clearance, consider enforcement for construction

HƯNG THƠ |

Quang Tri - The Hung Vuong extended road project is facing problems with site clearance, the provincial leaders requested to consider enforcement for construction.

The Hung Vuong road project connecting the East-West economic corridor and the Southeast Quang Tri Economic Zone (called Hung Vuong extended road), is a key infrastructure project, but is still facing site clearance problems. In this situation, the People's Committee of Quang Tri province has strongly directed localities and related units to focus on solutions to speed up progress.

The project consists of two routes: Hung Vuong and Bao Dai, passing through 3 villages of Ai Tu, Tan Kien and Ha Xa in Ai Tu commune, affecting 212 households with a reclaimed area of over 134,500m2. Of which, 21 households were directly affected in their housing. The total adjusted investment of the project is 130.3 billion VND, the total length of the route is nearly 4.2km.

The People's Committee of the old Trieu Phong district has approved 8 compensation and support packages of nearly 24.3 billion VND for 209 households, the area has been decided to be recovered at 132,925m2. However, there are still 3 households that have not issued a decision to reclaim and 7 households have not agreed to receive money and hand over the site, mostly due to problems with converting land use purposes or proposing to adjust the design.

Mot doan duong Hung Vuong noi dai dang duoc thi cong. Anh: H.Nguyen
A section of Hung Vuong Street extension is under construction. Photo: H.Nguyen

The consortium of contractors including Manh Linh Construction Company Limited, Thanh An Joint Stock Company and Quang Tri General Construction Joint Stock Company is currently implementing the construction of a package with a contract value of more than 118.8 billion VND. Of which, the construction and installation of the extended Hung Vuong road alone is more than 73.6 billion VND. Statistics up to July 10, the implementation value has only reached about 26.5 billion VND, equivalent to 23.04%.

Specifically, on Hung Vuong Street, the crushed stone layer from Km0+123 to Km0+900 has been completed, 6 round culverts and the box culvert body at Km1+230, construction of embankment, drainage and Khe Su bridge deck sections. Bao Dai route is spreading crushed stone, filling K95 soil in some sections, constructing 2/4 cross-culverts and casting concrete components.

Mr. Nguyen Thanh Binh - Director of the Quang Tri Provincial Construction Investment Project Management Board - said that there is not much time left to complete the project, until September 30, 2025, which is the end, while the site clearance work has not yet been completed: "If not handled in time, the progress will be affected".

At the site inspection on July 18, Chairman of the People's Committee of Quang Tri province Tran Phong requested the leaders of Ai Tu commune and related units to continue to propagate and mobilize people to clearly understand the project's goals to coordinate the handover of the site.

Mr. Tran Phong emphasized that in cases of intentional non-resettlement despite being fully explained and supported in accordance with policies, it is necessary to resolutely apply construction protection measures and organize enforcement. The provincial chairman also requested contractors to urgently organize construction as soon as there is a clean site, ensuring the quality, technical and aesthetic aspects of the project.

The Hung Vuong extended road project is part of the overall Basic infrastructure project for comprehensive development of Quang Tri province, playing a strategic role in regional linkages and expanding urban space south of Vinh Phuoc river. When completed, the route will create a strong development momentum for the southern central area of the province. Although the project started in 2021, due to the contractor's capacity and land clearance problems, the project has been delayed for many years, causing voters to be upset. Quang Tri province has changed the contractor of the project because it does not meet the capacity.

HƯNG THƠ
TIN LIÊN QUAN

The Chairman of the new People's Committee at the commune level was decided to enforce, revoke, and appraise the land price list

|

Decree 151/2025/ND-CP stipulates that the Chairman of the People's Committee at the commune level is responsible for implementing State management of the contents of the Land Law.

Restarting the Hung Vuong extended road project in Quang Tri

|

Quang Tri - After a period of stagnation, the extended Hung Vuong road has started construction, expected to be completed in September 2025.

New developments in the case of a series of leaders of Apatit Tam Dinh Company being suspended from work

|

Lao Cai - The Board of Supervisors of Apatit Tam Dinh Joint Stock Company has just issued a preliminary verification report on the " scandals" that occurred at this company.

Strongly spreading the patriotic emulation movement of the working class

|

During the resistance war against the US (1954 - 1975), the Vietnam General Confederation of Labor gathered, united, and promoted the pioneering role of the working class in overcoming countless difficulties, hardships, and sacrifices, contributing to the army and people of the whole country in the victory on April 30, 1975 .

HCMC reclaims 110 hectares of land, clears 61 households to build the North-South high-speed railway

|

Ho Chi Minh City will reclaim more than 110 hectares of land, clear 61 households with compensation and site clearance costs of more than VND 2,100 billion to build the North-South high-speed railway section.

Vietnam successfully stayed in the league after the Davis Cup

|

At the end of the Davis Cup Group III tennis tournament - Asia/Pacific in 2025, the Vietnam men's tennis team successfully stayed in the league.

Russia bombs Ukraine's strategic city in 6 hours

|

On the morning of July 19 (local time), Russia launched an unprecedented airstrike on the city of Pavlohrad, in eastern Ukraine.

A major fire broke out again after extinguishing and burning down 10 hectares of production forest in Da Nang

|

Da Nang - On the morning of July 20, the authorities mobilized nearly 100 people to control the overnight production forest fire, burning down more than 10 hectares.

The Chairman of the new People's Committee at the commune level was decided to enforce, revoke, and appraise the land price list

PHƯƠNG LY |

Decree 151/2025/ND-CP stipulates that the Chairman of the People's Committee at the commune level is responsible for implementing State management of the contents of the Land Law.

Restarting the Hung Vuong extended road project in Quang Tri

HƯNG THƠ |

Quang Tri - After a period of stagnation, the extended Hung Vuong road has started construction, expected to be completed in September 2025.

Cử tri Quảng Trị đề nghị xử lý dự án đường Hùng Vương nối dài chậm thi công

HƯNG THƠ |

Dự án đường Hùng Vương nối dài ở tỉnh Quảng Trị khởi công năm 2021, bàn giao mặt bằng cho đơn vị thi công năm 2022, nhưng đến nay chỉ mới bốc phong hóa.