Land clearance for highway overpass in Quang Tri faces difficulties

HƯNG THƠ |

Quang Tri - Some cases within the Van Ninh - Cam Lo expressway overpass have not received compensation because they believe the compensation is low.

On January 11, the People's Committee of Cam Lo district (Quang Tri province) confirmed that the locality is implementing the construction of 2 overpasses on the Van Ninh - Cam Lo expressway, and the site clearance is undertaken by Cam Lo district.

Up to this point, the site clearance work has not been completed, because some cases have not agreed to receive compensation.

Accordingly, the National Highway 9 overpass through Cam Hieu commune (Cam Lo district) has 88 households affected. Currently, 40/52 cases within the approved overpass area; 29/36 cases outside the approved overpass area. The cases that have not been approved for site clearance are due to disagreement on unit prices and are still in the process of requesting support.

Regarding the National Highway 9 overpass in Cam Thuy commune (Cam Lo district), there are 30 affected cases. Of which, 13 cases are within the scope of the overpass, and 11 cases have been approved for site clearance; 2 cases have not agreed on the support price. 17 cases are outside the scope of the overpass and are affected, of which 14 cases have been approved and 3 cases have not agreed on the housing compensation price.

Cases affected by the construction of the two above-mentioned expressway overpasses requested price support and social security after the project was completed.

Mr. Le Duc Tien - Vice Chairman of Quang Tri Provincial People's Committee - said that site clearance for the construction of National Highway 9 overpasses is very important, aiming to speed up the progress of the Van Ninh - Cam Lo expressway project to open the expressway in April 2025. Regarding the opinions of people affected by the construction of the overpass, Cam Lo District People's Committee is requested to coordinate with relevant departments, branches and sectors to review each specific petition, to advise on early solutions, in case the petition exceeds the authority, it must be compiled and submitted to the Provincial People's Committee for consideration and decision.

Previously, at the end of August 2024, to ensure the construction progress of the Van Ninh - Cam Lo expressway overpass, Cam Lo district coordinated with relevant agencies and units to organize forces to support and protect the construction on the land managed by the State, passing through Cam Hieu commune.

HƯNG THƠ
RELATED NEWS

Enrollment 2026: Series of universities announce admission plans

|

To date, many universities across the country have announced their expected enrollment plans for 2026.

President Donald Trump orders 10% global tax

|

On February 20, President Donald Trump announced a 10% tariff on all imports into the US after a Supreme Court ruling.

Short Tet holiday of the Vietnamese women's team

|

The Tet holiday of the Vietnamese women's team is short, less than 3 days to prepare for the journey to conquer a ticket to the 2027 Women's World Cup.

Mai Thu Huyen: My husband and son cook very well

|

Producer and actress Mai Thu Huyen shared about her family and Tet memories.

Driver violates alcohol concentration, no driver's license while carrying dozens of passengers

|

Quang Tri - Functional forces are handling a driver who violated alcohol concentration and did not have a driver's license while carrying dozens of passengers to Ho Chi Minh City.

At the beginning of the year, people flock to spring festivals

|

Nghe An - In the early days of Binh Ngo 2026, tens of thousands of tourists flocked to relics and scenic spots in Nghe An to offer incense and admire the scenery.

Infrastructure creates leverage for Ho Chi Minh City tourism to accelerate in 2026

|

Ho Chi Minh City - Infrastructure is one of the important factors, creating momentum for Ho Chi Minh City tourism to accelerate in 2026.

Hanoi welcomes nearly 594,000 visitors, earning more than 2,200 billion VND from tourism

|

Hanoi welcomed nearly 594,000 visitors in 5 days of Tet holiday, international visitors increased sharply, total tourism revenue reached more than 2,200 billion VND.

Người dân không đồng tình thi công cầu QL9 vượt cao tốc

HƯNG THƠ |

Cho rằng việc thi công cầu Quốc lộ 9 vượt cao tốc Vạn Ninh – Cam Lộ (đoạn qua tỉnh Quảng Trị) sẽ ảnh hưởng đến đời sống, sinh kế, nên người dân không đồng tình.

17km cao tốc Vạn Ninh-Cam Lộ đoạn qua Quảng Trị đã thảm nhựa

HƯNG THƠ |

Giải phóng mặt bằng sắp hoàn thành, Ban quản lý dự án đường Hồ Chí Minh đang đẩy nhanh tiến độ để thi công cao tốc Vạn Ninh – Cam Lộ đoạn qua tỉnh Quảng Trị.

Rầm rộ thi công trên công trường cao tốc Vạn Ninh – Cam Lộ đoạn qua Quảng Trị

HƯNG THƠ |

Ở những đoạn đã hoàn tất đền bù giải phóng mặt bằng và bàn giao, các đơn vị thi công đã huy động máy móc, nhân lực để thi công các hạng mục của cao tốc Vạn Ninh – Cam Lộ đoạn qua tỉnh Quảng Trị.