Land clearance for highway overpass in Quang Tri faces difficulties

HƯNG THƠ |

Quang Tri - Some cases within the Van Ninh - Cam Lo expressway overpass have not received compensation because they believe the compensation is low.

On January 11, the People's Committee of Cam Lo district (Quang Tri province) confirmed that the locality is implementing the construction of 2 overpasses on the Van Ninh - Cam Lo expressway, and the site clearance is undertaken by Cam Lo district.

Up to this point, the site clearance work has not been completed, because some cases have not agreed to receive compensation.

Accordingly, the National Highway 9 overpass through Cam Hieu commune (Cam Lo district) has 88 households affected. Currently, 40/52 cases within the approved overpass area; 29/36 cases outside the approved overpass area. The cases that have not been approved for site clearance are due to disagreement on unit prices and are still in the process of requesting support.

Regarding the National Highway 9 overpass in Cam Thuy commune (Cam Lo district), there are 30 affected cases. Of which, 13 cases are within the scope of the overpass, and 11 cases have been approved for site clearance; 2 cases have not agreed on the support price. 17 cases are outside the scope of the overpass and are affected, of which 14 cases have been approved and 3 cases have not agreed on the housing compensation price.

Cases affected by the construction of the two above-mentioned expressway overpasses requested price support and social security after the project was completed.

Mr. Le Duc Tien - Vice Chairman of Quang Tri Provincial People's Committee - said that site clearance for the construction of National Highway 9 overpasses is very important, aiming to speed up the progress of the Van Ninh - Cam Lo expressway project to open the expressway in April 2025. Regarding the opinions of people affected by the construction of the overpass, Cam Lo District People's Committee is requested to coordinate with relevant departments, branches and sectors to review each specific petition, to advise on early solutions, in case the petition exceeds the authority, it must be compiled and submitted to the Provincial People's Committee for consideration and decision.

Previously, at the end of August 2024, to ensure the construction progress of the Van Ninh - Cam Lo expressway overpass, Cam Lo district coordinated with relevant agencies and units to organize forces to support and protect the construction on the land managed by the State, passing through Cam Hieu commune.

HƯNG THƠ
RELATED NEWS

Officials working abroad and integrating regularly internationally will be supported with 100% of their salary

|

The Government proposes that people working in foreign affairs and international integration who are regularly supported with 100% of their salary according to the current coefficient (excluding allowances).

Ho Chi Minh City Department of Construction speaks out about the proposal to convert gasoline motorbikes to electricity

|

HCMC - The renovation of gasoline motorbikes to electric vehicles to be officially implemented needs to continue to perfect the legal basis, technical regulations, safety standards...

Hai Phong Lung Hospital is seriously degraded after half a century of operation

|

Hai Phong - After 50 years of use, 7 works at Hai Phong Lung Hospital have seriously degraded, not ensuring medical examination and treatment.

The risk of landslides still lurks on the La Son - Hoa Lien Expressway

|

HUE - Historical floods caused rocks and soil from the mountain slopes to fall down, burying many sections of the La Son - Hoa Lien Expressway and Provincial Road 14B, and the risk of landslides still exists.

Stories are deserted, shops are closed, Quang Ngai prepares to face storm No. 13

|

On the afternoon of November 6, Quang Ngai center was deserted, shops closed. More than 18,000 people have been evacuated, all anxiously facing storm No. 13.

Proposal to clarify the basis for calculating the investment rate of Gia Binh airport project

|

The Gia Binh airport project has a total investment of about VND196,378 billion; of which phase 1 is about VND141,236 billion, phase 2 is about VND55,142 billion.

Người dân không đồng tình thi công cầu QL9 vượt cao tốc

HƯNG THƠ |

Cho rằng việc thi công cầu Quốc lộ 9 vượt cao tốc Vạn Ninh – Cam Lộ (đoạn qua tỉnh Quảng Trị) sẽ ảnh hưởng đến đời sống, sinh kế, nên người dân không đồng tình.

17km cao tốc Vạn Ninh-Cam Lộ đoạn qua Quảng Trị đã thảm nhựa

HƯNG THƠ |

Giải phóng mặt bằng sắp hoàn thành, Ban quản lý dự án đường Hồ Chí Minh đang đẩy nhanh tiến độ để thi công cao tốc Vạn Ninh – Cam Lộ đoạn qua tỉnh Quảng Trị.

Rầm rộ thi công trên công trường cao tốc Vạn Ninh – Cam Lộ đoạn qua Quảng Trị

HƯNG THƠ |

Ở những đoạn đã hoàn tất đền bù giải phóng mặt bằng và bàn giao, các đơn vị thi công đã huy động máy móc, nhân lực để thi công các hạng mục của cao tốc Vạn Ninh – Cam Lộ đoạn qua tỉnh Quảng Trị.