Land clearance for highway overpass in Quang Tri faces difficulties

HƯNG THƠ |

Quang Tri - Some cases within the Van Ninh - Cam Lo expressway overpass have not received compensation because they believe the compensation is low.

On January 11, the People's Committee of Cam Lo district (Quang Tri province) confirmed that the locality is implementing the construction of 2 overpasses on the Van Ninh - Cam Lo expressway, and the site clearance is undertaken by Cam Lo district.

Up to this point, the site clearance work has not been completed, because some cases have not agreed to receive compensation.

Accordingly, the National Highway 9 overpass through Cam Hieu commune (Cam Lo district) has 88 households affected. Currently, 40/52 cases within the approved overpass area; 29/36 cases outside the approved overpass area. The cases that have not been approved for site clearance are due to disagreement on unit prices and are still in the process of requesting support.

Regarding the National Highway 9 overpass in Cam Thuy commune (Cam Lo district), there are 30 affected cases. Of which, 13 cases are within the scope of the overpass, and 11 cases have been approved for site clearance; 2 cases have not agreed on the support price. 17 cases are outside the scope of the overpass and are affected, of which 14 cases have been approved and 3 cases have not agreed on the housing compensation price.

Cases affected by the construction of the two above-mentioned expressway overpasses requested price support and social security after the project was completed.

Mr. Le Duc Tien - Vice Chairman of Quang Tri Provincial People's Committee - said that site clearance for the construction of National Highway 9 overpasses is very important, aiming to speed up the progress of the Van Ninh - Cam Lo expressway project to open the expressway in April 2025. Regarding the opinions of people affected by the construction of the overpass, Cam Lo District People's Committee is requested to coordinate with relevant departments, branches and sectors to review each specific petition, to advise on early solutions, in case the petition exceeds the authority, it must be compiled and submitted to the Provincial People's Committee for consideration and decision.

Previously, at the end of August 2024, to ensure the construction progress of the Van Ninh - Cam Lo expressway overpass, Cam Lo district coordinated with relevant agencies and units to organize forces to support and protect the construction on the land managed by the State, passing through Cam Hieu commune.

HƯNG THƠ
RELATED NEWS

Expecting the Digital Front to promote the effectiveness of connecting and uniting people

|

Ho Chi Minh City delegates expect the Vietnam Fatherland Front to continue to strongly innovate its activities in a modern direction, promote digital transformation, and promote the effectiveness of the Digital Front.

Story about the connection in a rural area with more than 21 churches in Ninh Binh

|

Ninh Binh - In a rural area with more than 87% of the Catholic population, free religious life is nurtured by the solidarity and companionship between the government, the church and the people.

Monitoring and criticizing early and remotely to make policies more practical

|

The 11th National Congress of the Vietnam Fatherland Front (VFF), term 2026-2031, takes place from May 11-13 in Hanoi Capital. The Congress is a historical milestone, opening the term of operating the apparatus with a new stature and development path when socio-political organizations and mass associations assigned tasks by the Party and State are directly under the VFF.

Barcelona wins La Liga

|

In the early morning of May 11 (Vietnam time), Barcelona officially successfully defended the La Liga throne after a 2-0 victory over Real Madrid.

Earthquake of magnitude 4.0 occurred in Son La

|

Son La - An earthquake with a magnitude of 4.0 occurred in the Muong Hung commune area.

Người dân không đồng tình thi công cầu QL9 vượt cao tốc

HƯNG THƠ |

Cho rằng việc thi công cầu Quốc lộ 9 vượt cao tốc Vạn Ninh – Cam Lộ (đoạn qua tỉnh Quảng Trị) sẽ ảnh hưởng đến đời sống, sinh kế, nên người dân không đồng tình.

17km cao tốc Vạn Ninh-Cam Lộ đoạn qua Quảng Trị đã thảm nhựa

HƯNG THƠ |

Giải phóng mặt bằng sắp hoàn thành, Ban quản lý dự án đường Hồ Chí Minh đang đẩy nhanh tiến độ để thi công cao tốc Vạn Ninh – Cam Lộ đoạn qua tỉnh Quảng Trị.

Rầm rộ thi công trên công trường cao tốc Vạn Ninh – Cam Lộ đoạn qua Quảng Trị

HƯNG THƠ |

Ở những đoạn đã hoàn tất đền bù giải phóng mặt bằng và bàn giao, các đơn vị thi công đã huy động máy móc, nhân lực để thi công các hạng mục của cao tốc Vạn Ninh – Cam Lộ đoạn qua tỉnh Quảng Trị.