Land clearance for highway overpass in Quang Tri faces difficulties

HƯNG THƠ |

Quang Tri - Some cases within the Van Ninh - Cam Lo expressway overpass have not received compensation because they believe the compensation is low.

On January 11, the People's Committee of Cam Lo district (Quang Tri province) confirmed that the locality is implementing the construction of 2 overpasses on the Van Ninh - Cam Lo expressway, and the site clearance is undertaken by Cam Lo district.

Up to this point, the site clearance work has not been completed, because some cases have not agreed to receive compensation.

Accordingly, the National Highway 9 overpass through Cam Hieu commune (Cam Lo district) has 88 households affected. Currently, 40/52 cases within the approved overpass area; 29/36 cases outside the approved overpass area. The cases that have not been approved for site clearance are due to disagreement on unit prices and are still in the process of requesting support.

Regarding the National Highway 9 overpass in Cam Thuy commune (Cam Lo district), there are 30 affected cases. Of which, 13 cases are within the scope of the overpass, and 11 cases have been approved for site clearance; 2 cases have not agreed on the support price. 17 cases are outside the scope of the overpass and are affected, of which 14 cases have been approved and 3 cases have not agreed on the housing compensation price.

Cases affected by the construction of the two above-mentioned expressway overpasses requested price support and social security after the project was completed.

Mr. Le Duc Tien - Vice Chairman of Quang Tri Provincial People's Committee - said that site clearance for the construction of National Highway 9 overpasses is very important, aiming to speed up the progress of the Van Ninh - Cam Lo expressway project to open the expressway in April 2025. Regarding the opinions of people affected by the construction of the overpass, Cam Lo District People's Committee is requested to coordinate with relevant departments, branches and sectors to review each specific petition, to advise on early solutions, in case the petition exceeds the authority, it must be compiled and submitted to the Provincial People's Committee for consideration and decision.

Previously, at the end of August 2024, to ensure the construction progress of the Van Ninh - Cam Lo expressway overpass, Cam Lo district coordinated with relevant agencies and units to organize forces to support and protect the construction on the land managed by the State, passing through Cam Hieu commune.

HƯNG THƠ
TIN LIÊN QUAN

40% of meat in Hanoi is not strictly controlled

|

The leaders of the Hanoi Department of Agriculture and Environment acknowledged that the amount of meat imported from localities for consumption in the city has not been strictly controlled.

Da Nang stops all paragliding activities in Son Tra mountain area

|

The Management Board of Son Tra Peninsula and Da Nang tourist beaches said that it has stopped all paragliding activities on Son Tra peninsula since July 9.

Dismantling a series of "tiger cages" after the fire that killed 8 people at Doc Lap residence

|

HCMC - After the tragic fire, many households in Doc Lap residence have proactively hired workers to dismantle the expansion items, encroaching on the corridor and balcony.

laughing balls are still hidden in a bar in Ho Chi Minh City, operating vigorously at midnight

|

HCMC - Under the shady lights and the music, laughter is hidden in new covers, bustling at midnight, just for customers to " want fun, I have it".

Cash flow enters strongly, stocks aim for 1,500 points

|

The Vietnamese stock market is having an impressive increase with the return of foreign investor capital.

Dam Vinh Hung officially continues the lawsuit with Bich Tuyen's husband

|

On July 8 (ie July 9, Vietnam time), the US court officially allowed Dam Vinh Hung to continue pursuing the lawsuit with Bich Tuyen's husband.

Người dân không đồng tình thi công cầu QL9 vượt cao tốc

HƯNG THƠ |

Cho rằng việc thi công cầu Quốc lộ 9 vượt cao tốc Vạn Ninh – Cam Lộ (đoạn qua tỉnh Quảng Trị) sẽ ảnh hưởng đến đời sống, sinh kế, nên người dân không đồng tình.

17km cao tốc Vạn Ninh-Cam Lộ đoạn qua Quảng Trị đã thảm nhựa

HƯNG THƠ |

Giải phóng mặt bằng sắp hoàn thành, Ban quản lý dự án đường Hồ Chí Minh đang đẩy nhanh tiến độ để thi công cao tốc Vạn Ninh – Cam Lộ đoạn qua tỉnh Quảng Trị.

Rầm rộ thi công trên công trường cao tốc Vạn Ninh – Cam Lộ đoạn qua Quảng Trị

HƯNG THƠ |

Ở những đoạn đã hoàn tất đền bù giải phóng mặt bằng và bàn giao, các đơn vị thi công đã huy động máy móc, nhân lực để thi công các hạng mục của cao tốc Vạn Ninh – Cam Lộ đoạn qua tỉnh Quảng Trị.