Land clearance for highway overpass in Quang Tri faces difficulties

HƯNG THƠ |

Quang Tri - Some cases within the Van Ninh - Cam Lo expressway overpass have not received compensation because they believe the compensation is low.

On January 11, the People's Committee of Cam Lo district (Quang Tri province) confirmed that the locality is implementing the construction of 2 overpasses on the Van Ninh - Cam Lo expressway, and the site clearance is undertaken by Cam Lo district.

Up to this point, the site clearance work has not been completed, because some cases have not agreed to receive compensation.

Accordingly, the National Highway 9 overpass through Cam Hieu commune (Cam Lo district) has 88 households affected. Currently, 40/52 cases within the approved overpass area; 29/36 cases outside the approved overpass area. The cases that have not been approved for site clearance are due to disagreement on unit prices and are still in the process of requesting support.

Regarding the National Highway 9 overpass in Cam Thuy commune (Cam Lo district), there are 30 affected cases. Of which, 13 cases are within the scope of the overpass, and 11 cases have been approved for site clearance; 2 cases have not agreed on the support price. 17 cases are outside the scope of the overpass and are affected, of which 14 cases have been approved and 3 cases have not agreed on the housing compensation price.

Cases affected by the construction of the two above-mentioned expressway overpasses requested price support and social security after the project was completed.

Mr. Le Duc Tien - Vice Chairman of Quang Tri Provincial People's Committee - said that site clearance for the construction of National Highway 9 overpasses is very important, aiming to speed up the progress of the Van Ninh - Cam Lo expressway project to open the expressway in April 2025. Regarding the opinions of people affected by the construction of the overpass, Cam Lo District People's Committee is requested to coordinate with relevant departments, branches and sectors to review each specific petition, to advise on early solutions, in case the petition exceeds the authority, it must be compiled and submitted to the Provincial People's Committee for consideration and decision.

Previously, at the end of August 2024, to ensure the construction progress of the Van Ninh - Cam Lo expressway overpass, Cam Lo district coordinated with relevant agencies and units to organize forces to support and protect the construction on the land managed by the State, passing through Cam Hieu commune.

HƯNG THƠ
RELATED NEWS

UAV attack, Dubai airport temporarily closed

|

A series of UAV attacks on Dubai airport in the United Arab Emirates killed 1 person.

Accelerate completion of Ring Road 2.5 section Kim Dong - Dam Hong before handover date

|

Hanoi - Ring Road 2.5 Kim Dong - Dam Hong section gradually reveals a new face when the final items are being urgently constructed before the handover time.

Rumors spread that Iran's Supreme Leader secretly went abroad for treatment

|

Iranian Supreme Leader Mojtaba Khamenei is believed to have been injured in the airstrike on February 28 and may have been taken abroad for treatment.

Starlink satellite Internet subscribers in Vietnam are expected to pay 2.2 million VND per month

|

Starlink satellite Internet service in Vietnam is expected to have a monthly subscription fee of about 2.2 million VND.

Da River dries up to the bottom, in many sections people can stroll in the middle of the river

|

The water level of the Da River downstream of Hoa Binh Hydropower Plant is low, revealing many sandbanks and gravel in the middle of the river, people can wade through the water or walk quite far into the middle of the stream.

Người dân không đồng tình thi công cầu QL9 vượt cao tốc

HƯNG THƠ |

Cho rằng việc thi công cầu Quốc lộ 9 vượt cao tốc Vạn Ninh – Cam Lộ (đoạn qua tỉnh Quảng Trị) sẽ ảnh hưởng đến đời sống, sinh kế, nên người dân không đồng tình.

17km cao tốc Vạn Ninh-Cam Lộ đoạn qua Quảng Trị đã thảm nhựa

HƯNG THƠ |

Giải phóng mặt bằng sắp hoàn thành, Ban quản lý dự án đường Hồ Chí Minh đang đẩy nhanh tiến độ để thi công cao tốc Vạn Ninh – Cam Lộ đoạn qua tỉnh Quảng Trị.

Rầm rộ thi công trên công trường cao tốc Vạn Ninh – Cam Lộ đoạn qua Quảng Trị

HƯNG THƠ |

Ở những đoạn đã hoàn tất đền bù giải phóng mặt bằng và bàn giao, các đơn vị thi công đã huy động máy móc, nhân lực để thi công các hạng mục của cao tốc Vạn Ninh – Cam Lộ đoạn qua tỉnh Quảng Trị.