Hanoi reclaims land from more than 800 households to open a 40m wide road

HỮU CHÁNH |

Hanoi - Linh Nam Street (Hoang Mai District) is over 3km long and will be widened to 22.5-40m, with 829 households and 19 organizations having their land recovered.

Speaking with Lao Dong, Mr. Vu Tuan Dat, Director of the Hoang Mai District Land Fund Development Center (Hanoi) said that the Hoang Mai District People's Committee has assigned this unit to coordinate with relevant parties to complete the procedures to restart the Linh Nam Road Upgrade and Expansion Project.

According to Mr. Dat, the project to upgrade and expand Linh Nam Street was approved for investment by the Hanoi People's Committee in 2013.

The project is about 3.4km long, starting at Tam Trinh intersection and ending at Nguyen Khoi embankment intersection. Part of the route (from Vinh Hung intersection to Nguyen Khoi embankment) is part of Hanoi's Ring Road 2.5.

According to the plan, Linh Nam road will be expanded based on the existing road, with 2 sections with cross-sections of 22.5m and 40m respectively.

By August 2024, the Hanoi People's Committee approved the adjustment of the implementation time of the Linh Nam Road Upgrade and Expansion Project according to the planning, to be completed in 2027.

The reason for the adjustment is due to difficulties and problems in site clearance, leading to the project not ensuring progress.

Giam doc Trung tam phat trien quy dat quan Hoang Mai Vu Tuan Dat trao doi voi Lao Dong. Anh: Huu Chanh
Director of Hoang Mai District Land Fund Development Center Vu Tuan Dat talks with Lao Dong. Photo: Huu Chanh

According to Mr. Vu Tuan Dat, to implement the project, Hoang Mai district will reclaim and clear 98,300 square meters of land, involving 829 households and 19 organizations in 4 wards, including Mai Dong, Vinh Hung, Linh Nam and Tran Phu.

Based on the resolution of the Hanoi People's Council, the Hoang Mai District People's Council plans to hold a meeting in October 2024 to allocate funds to implement the project in 2024.

The Land Fund Development Center is assigned to organize the selection of a unit to measure and map the site clearance, coordinate with the People's Committees of the wards to continue to organize the issuance of land recovery notices, investigation and inventory.

In the immediate future, the People's Committee of Hoang Mai district will prepare documents and approve specific land prices for site clearance compensation in October 2024.

Hoang Mai District People's Committee strives to start construction by June 2025 and complete the project by 2027.

When completed, Linh Nam Road expansion will play an important role in connecting Ring Road 2.5 with Ring Road 3.

The upgrading and expansion of Linh Nam Street will facilitate traffic from Thanh Tri Bridge - Ring Road 3 to Dam Hong - Nguyen Trai; help reduce traffic congestion on main roads at the southern gateway, contributing to the socio-economic development of Hoang Mai district.

HỮU CHÁNH
RELATED NEWS

Disciplining officials last week at Hanoi, Gia Lai, Thai Nguyen Police

|

Hanoi Police handle disciplinary action against a number of officers and soldiers who violated regulations; reprimand the Vice Principal for abuse of power... are information about official discipline last week.

Malaysian football fined over 15.5 billion VND in 2025

|

A series of penalties from FIFA, AFC and domestic leagues have caused Malaysian football to fall into crisis with record high fines in history.

Many officials of the Department of Finance of Dak Lak apply for transfer or resignation

|

Dak Lak - For about the past month, many heads and deputy heads of departments at the Department of Finance have applied for job transfer or resignation.

Trade union news: 4-day Tet holiday, pension payment schedule for January 2026 may change

|

Trade union news on December 28: 4-day Tet holiday, pension payment schedule for January 2026 may change; New graduates struggle to find jobs;...

Transferring and appointing personnel in the Central Organization Committee, 2 ministries, 1 agency

|

The Central Organization Committee, the Ministry of Agriculture and Environment, the Social Insurance Management Council... have just made decisions on personnel appointments.

Cold air and storms affect millions of people during the New Year holiday

|

It is forecast that cold air and strong storms could last for many days, right at the peak of the New Year holiday, affecting millions of people in the US.

Arsenal returns to the top of the Premier League table

|

On the night of December 27 (Vietnam time), Arsenal reclaimed the top spot in the Premier League table from Man City after a 2-1 victory over Brighton.

Health status of 7 victims of the overturned truck carrying a charity delegation in Lao Cai

|

On the afternoon of December 27, Viet Duc Friendship Hospital received 7 victims in the overturned truck carrying a charity delegation that occurred in Lao Cai.

Hanoi is about to forcibly reclaim land to widen the central road to 21m

HỮU CHÁNH |

Hanoi - Authorities are preparing to enforce land acquisition to expand a 720m road, costing about 400 billion VND, after many years of delay.

Two projects worth nearly 1,000 billion VND change the face of West Lake traffic

HỮU CHÁNH |

Hanoi - The completion of the Au Co Street expansion project and the Xuan Dieu Street upgrade project will help reduce traffic congestion and contribute to changing the traffic landscape of Tay Ho district.

Completed expansion of chronically congested road in Hanoi

HỮU CHÁNH |

Hanoi - The Xuan Dieu Street upgrade project, with an investment capital of nearly 400 billion VND, has reached its completion after many years of sluggish construction.