Two expressways worth over VND72,000 billion in the West still lack sand

Tạ Quang - Yến Phương |

The Chau Doc - Can Tho - Soc Trang Expressway and the Can Tho - Hau Giang Expressway are still in a state of sand shortage, leading to slow progress.

According to Lao Dong Newspaper reporters at the Chau Doc - Can Tho - Soc Trang expressway construction site through Can Tho City, many workers, engineers and machinery are focusing on casting bridge girders and other items.

Mr. Truong Vu Thang - Construction Commander of Dat Phuong Group Joint Stock Company - said that the unit has mobilized all human resources and equipment to urgently construct after Tet.

Ong Truong Vu Thang - Chi huy Truong cong truong Cong ty co phan Tap doan Dat Phuong. Anh: Ta Quang
Mr. Truong Vu Thang - Commander of the construction site of Dat Phuong Group Joint Stock Company. Photo: Ta Quang

According to Mr. Truong Vu Thang, the sand source is scarce, affecting the project's progress. The contractor hopes to solve this problem soon.

Mr. Truong Vu Thang said that favorable weather in the dry season helps the bridge construction be effective. The unit mobilizes all human resources, 3 shifts/day (about 30 people/shift) to ensure progress.

The Chau Doc - Can Tho - Soc Trang Expressway project through Can Tho City has a total of 5 construction packages (including 4 construction packages and 1 construction package for the construction of the traffic safety system). The value of the construction volume reached about 23%.

Cong nhan hoi ha duc dam cau. Anh: Ta Quang
Workers are rushing to cast bridge girders. Photo: Ta Quang

Previously, the Ministry of Transport issued a document responding to the petition of voters in An Giang province regarding the construction progress of the Chau Doc - Can Tho - Soc Trang transversal expressway. Up to now, the project has achieved certain results (land clearance and resettlement work has reached 99%, construction volume has reached about 30%...).

However, the implementation progress is still slower than the plan due to a shortage of sand materials for roadbed construction (to date, only about 23 million m3/total demand of the project of about 29 million m3 has been identified). Localities are speeding up procedures for granting mining licenses and reviewing additional sources of sand lacking, while considering the option of using sea sand in Soc Trang province to build roadbeds.

On the Can Tho - Hau Giang expressway, part of the Can Tho - Ca Mau expressway project, Mr. Nguyen Phuong Nam - Construction Supervisor of the site, part of Construction Corporation No. 1 (CC1) - informed that the contractor in charge of the construction from Km34 (+100) to Km38 (+880), after the Lunar New Year, the unit focused on the construction of loading items, on the main route, the unit has completed the sand loading, speeding up the volume of crushed stone loading.

Nut giao IC4 thuoc cao toc Can Tho - Ca Mau. Anh: Ta Quang
IC4 intersection on Can Tho - Ca Mau Expressway. Photo: Ta Quang

The IC4 intersection location includes 2 branch routes connecting directly to National Highway 61. Due to the pressure of the remaining sandload, the exploitation period is only about 10 days, so we are focusing on developing a plan and working overtime to meet the progress of completing and handing over the project for use by the end of this year," said Mr. Nguyen Phuong Nam.

Regarding the main route, Mr. Nguyen Phuong Nam added that the CC1 contractor is in charge of about 4km, the branch route is about 3.2km. There are 6 large culvert locations along the entire route, and 5 culverts have been concreted, the remaining one is expected to be completed this month.

According to the My Thuan Project Management Board, up to now, the Can Tho - Hau Giang expressway has basically completed 100% of site clearance. Regarding the construction situation, the accumulated output reached about 66% of the contract value.

The Can Tho - Ca Mau Expressway is over 110km long, with a total investment of over VND 27,500 billion. The project is divided into two component projects including the Can Tho - Hau Giang section (over 37km) and the Hau Giang - Ca Mau section (over 73km).

The Chau Doc - Can Tho - Soc Trang Expressway Project Phase 1 is over 188km long, passing through 4 provinces/cities: An Giang, Can Tho, Hau Giang and Soc Trang. The total investment of the project is about 44,700 billion VND.

Tạ Quang - Yến Phương
TIN LIÊN QUAN

Can Tho - Ca Mau Expressway seen from above has gradually taken shape

|

Can Tho - Ca Mau Expressway has completed the handover of the entire route, reaching 100%. Construction has reached about 58%.

Workers work through Tet on the North-South Expressway

|

Quang Binh - Even though it was the days before and during Lunar New Year, workers still stayed at the construction site, working through the holiday to ensure the progress of the expressway project.

"Sleepless" days and nights with Can Tho - Ca Mau expressway during Tet

|

Can Tho - In the days leading up to Lunar New Year 2025, engineers and workers are still working tirelessly day and night to construct the Can Tho - Ca Mau expressway.

A buffalo kills two injured people in Binh Chanh

|

HCMC - On February 23, the leader of the People's Committee of Vinh Loc A commune, Binh Chanh district confirmed that a buffalo had just occurred in the area, injuring 2 people.

Current status of the project worth over 1 billion USD Hanoi Chairman orders to start construction

|

Hanoi - After 17 years since its approval, up to now, the Hanoi Biotechnology High-Tech Park Project is still just a place to grow vegetables.

The old Government apparatus will operate until the end of February 2025

|

After having a Decree on functions, tasks, and powers, the new apparatus of ministries, ministerial-level agencies, and government agencies will come into operation from March 1, 2025.

Current state of degradation in the old apartment complex on Hanoi's prime land

|

Kim Lien apartment complex is located on prime land in Hanoi but is now seriously degraded, greatly affecting people's lives.

Risk of Ukraine being controlled when the conflict ends

|

Hungarian Prime Minister Viktor Orban said that the conflict in Eastern Europe is essentially an effort by the West to put Ukraine under control.

Can Tho - Ca Mau Expressway seen from above has gradually taken shape

Tạ Quang |

Can Tho - Ca Mau Expressway has completed the handover of the entire route, reaching 100%. Construction has reached about 58%.

Workers work through Tet on the North-South Expressway

CÔNG SÁNG |

Quang Binh - Even though it was the days before and during Lunar New Year, workers still stayed at the construction site, working through the holiday to ensure the progress of the expressway project.

"Sleepless" days and nights with Can Tho - Ca Mau expressway during Tet

TẠ QUANG - YẾN PHƯƠNG |

Can Tho - In the days leading up to Lunar New Year 2025, engineers and workers are still working tirelessly day and night to construct the Can Tho - Ca Mau expressway.