The Ring Road 4 project of the Capital Region has a total length of nearly 113km, passing through 3 provinces and cities, including Hanoi (58km), Hung Yen (19.3km), Bac Ninh (36.2km). The starting point of the project is at the Hanoi - Lao Cai expressway connection point, the end point is at the Noi Bai - Ha Long expressway connection point.
The project is implemented in 7 component projects, operating independently. Of which, Hanoi implements 3 component projects: Compensation, support, resettlement; Construction of parallel roads (urban roads) in Hanoi and investment in the construction of the expressway system under the PPP method.
Hung Yen and Bac Ninh provinces are each responsible for two component projects: Compensation, support, resettlement and construction of parallel roads (urban roads) in each province's territory.
The project has a total investment of over VND 85,813 billion, of which the Ring Road 4 expressway is invested under PPP with an investment of VND 56,500 billion.
The project started in June 2023 and is scheduled to complete the parallel road according to project approval in 2026, and complete the expressway in 2027.

Regarding the implementation of the investment project to build Ring Road 4 through Hanoi, the Hanoi Traffic Construction Investment Project Management Board (investor) said that by the end of October 2024, Hanoi had approved and recovered 98.15% of the land area, completed all 13 resettlement areas and arranged resettlement for 337/818 households.
Currently, the investor is coordinating with the locality to strive to complete site clearance and hand over the entire site in Hanoi in 2024, and complete the relocation of underground and above-ground technical infrastructure items in the fourth quarter of 2024.

The parallel road of Ring Road 4, the section through Hanoi, is about 58km long, passing through localities including Soc Son, Me Linh, Dan Phuong, Hoai Duc districts, Ha Dong district, Thanh Oai and Thuong Tin districts.
Regarding the progress of component project 2.1 (parallel road of Ring Road 4 through Hanoi), after 15 months since the commencement date, 4 construction packages have been simultaneously implemented by contractors on the handed over area with 32 construction points (23 road points, 9 bridge points).
The contractor is currently handling the weak ground, constructing the bridge and the semi-hollow asphalt concrete pavement. The output to date has reached about 36.86%. The parallel road section through Hanoi is expected to be completed in the fourth quarter of 2025.
The completion of Ring Road 4 of the Capital Region will contribute to relieving traffic congestion, connecting provinces and creating new development space for the entire Capital Region, including Hanoi, Hung Yen and Bac Ninh.