Maximum mobilization for Chau Doc - Can Tho - Soc Trang Expressway

Tạ Quang |

Many bridge items on the Chau Doc - Can Tho - Soc Trang expressway are being mobilized with maximum human resources and equipment to speed up progress.

Speaking to Lao Dong Newspaper reporter, Mr. Truong Vu Thang - Commander of the construction site of Dat Phuong Group Joint Stock Company - said that the unit is in charge of constructing 2 bridges on the route including Thi Doi Bridge and Dong Phap Bridge. In particular, Dong Phap Bridge is preparing to construct the bridge deck structure ( install girders and complete the bridge deck); Thi Doi Bridge is constructing the lower structure, expected to reach about 80% of the volume by April 30 and the above structure is expected to be completed in November 2025.

Ong Truong Vu Thang – Chi huy truong cong truong Cong ty co phan Tap doan Dat Phuong. Anh: Ta Quang
Mr. Truong Vu Thang - Commander of the construction site of Dat Phuong Group Joint Stock Company. Photo: Ta Quang

Mr. Truong Vu Thang added that for the unit's work, it will be completed in 2025. However, the unit is currently mobilizing maximum human resources, machinery and equipment to further speed up the progress.

Mr. Dang Hoang Vinh - Director of the Expressway Management Board (under the Can Tho City Construction Investment Project Management Board - investor of Component Project 2) - informed that the project has 4 main construction packages and 1 construction package for the traffic safety system, up to now, reaching a rate of 25% of the construction volume value.

Nhan cong dang do dam cau. Anh: Ta Quang
Workers are pouring bridge girders. Photo: Ta Quang

Regarding the bridge, Mr. Dang Hoang Vinh said that there are a total of 30 bridges on the route, over 7.2km long. To date, 28/30 bridges have been constructed, the remaining 2 bridges (keday My Bridge and Ngan Hai Bridge) are single- span bridges, and will be constructed in 2025.

"If the progress is drastically accelerated, over 10 bridges will be completed in 2025, but to complete it, there must be a connecting route," said Mr. Dang Hoang Vinh.

For the section through Hau Giang province, as of March 17, component project 3 reached 35% of the contract value, basically meeting the requirements on output.

Regarding the bridge item on the route, Mr. Nguyen Van Hoa - Vice Chairman of Hau Giang Provincial People's Committee - said that currently, the contractor has simultaneously deployed 12/12 bridges on the route; of which, 9/12 bridge piers have been completed, beams have been installed, and 2 bridges have been poured. According to the plan to strive to complete the entire bridge section in July 2025, the progress of the bridge works on the route has so far met and exceeded the set schedule.

Cong nhan miet mai lam viec o cao toc truc ngang doan qua Can Tho. Anh: Ta Quang
Workers work hard on the expressway across the Can Tho section. Photo: Ta Quang

Previously, on the afternoon of March 18, Prime Minister Pham Minh Chinh chaired an online meeting with 4 provinces and cities in the Mekong Delta region including: An Giang, Hau Giang, Soc Trang, Can Tho on the progress of the Chau Doc - Can Tho - Soc Trang expressway project.

At the meeting, the Prime Minister requested to recover the delayed progress and further speed up the progress, completing the Chau Doc - Can Tho - Soc Trang expressway project in June 2026, while ensuring quality, because the earlier it is completed, the higher the efficiency.

The Chau Doc - Can Tho - Soc Trang (horizontal) expressway project phase 1 is over 188km long, passing through 4 provinces/cities: An Giang, Can Tho, Hau Giang and Soc Trang. The scale of phase 1 includes 4 lanes, with a design speed of 100km/h. The total investment of the project is about 44,700 billion VND. Component project 2 is located in Can Tho, over 37km long, with a total investment of over VND 9,700 billion; Component project 3 is invested by the Department of Transport (now the Department of Construction) of Hau Giang province, over 36km long, with a total investment of nearly VND 9,602 billion.

Tạ Quang
TIN LIÊN QUAN

deadline for completing the Chau Doc - Can Tho - Soc Trang expressway

|

The Prime Minister requested to restore the delayed progress, completing the Chau Doc - Can Tho - Soc Trang expressway in June 2026.

The highway lacks sand, the bridge has been installed but cannot yet build an approach road

|

To ensure the Chau Doc - Can Tho - Soc Trang (horizontal) expressway project is completed in 2026, the construction unit recommends that the investor promptly resolve the sand source.

Lack of sand and rocks, 2 expressways in the West construct bridge to compensate for progress

|

With a shortage of sand and stone, workers in two expressway projects in the West are speeding up the construction of bridges to ensure progress.

83 people who retired early in Bac Lieu received more than 90 billion VND

|

Bac Lieu - Implementing Decree 178, Bac Lieu province has resolved the first phase for 83 people who retired early and 9 people who quit their jobs.

The Vietnam team has found a stable and solid framework

|

In the Sports Perspective program No. 208, football expert Phan Anh Tu assessed that the Vietnamese team has found a stable framework after two matches in March.

Mr. Putin proposes the United Nations to temporarily manage Ukraine

|

Russian President Vladimir Putin proposed the establishment of a temporary government in Ukraine under the supervision of the United Nations and a number of other countries.

Rare photos of Ha Giang in the 2000s of early backpackers

|

Ha Giang in the photo album of the first backpacker recorded more than 20 years ago is still peaceful and a bit deserted.

Enterprises are aware of green transformation but still have many barriers

|

Many businesses are aware that green transformation is a mandatory choice, but also admit that they have to face many difficulties in terms of finance, resources, etc.

deadline for completing the Chau Doc - Can Tho - Soc Trang expressway

PHẠM ĐÔNG |

The Prime Minister requested to restore the delayed progress, completing the Chau Doc - Can Tho - Soc Trang expressway in June 2026.

The highway lacks sand, the bridge has been installed but cannot yet build an approach road

Tạ Quang |

To ensure the Chau Doc - Can Tho - Soc Trang (horizontal) expressway project is completed in 2026, the construction unit recommends that the investor promptly resolve the sand source.

Lack of sand and rocks, 2 expressways in the West construct bridge to compensate for progress

Tạ Quang - Yến Phương |

With a shortage of sand and stone, workers in two expressway projects in the West are speeding up the construction of bridges to ensure progress.