Construction of Nhon metro tunnel boring machine No. 2 starts in early 2025

HỮU CHÁNH |

It is expected that TBM tunnel boring machine No. 2 of the Nhon - Hanoi metro railway will start construction in January 2025.

Regarding the overall progress of the Urban Railway Project No. 3, Nhon - Hanoi Station section, the Hanoi Urban Railway Management Board said that up to now, the bidding packages CP01 - viaduct, CP02 - elevated stations, CP04 - depot infrastructure and CP05 - depot architecture have been basically completed.

Package CP03 - tunnels and underground stations reached 50.2%; package CP06 - railway 1 reached 91.5% (underground part not yet constructed according to plan); package CP07 - railway 2 reached 47.1% (underground part reached 10.61%); package CP08 - railway 3 reached 73.2% (underground part reached 1.33%) and package CP09 - ticket system reached 84% (underground part not yet constructed according to plan).

For the underground section, the contractor has completed 73.04% of the underground ramp; station S9 has completed 51.7%, the vertical shaft has completed 41.74%; stations S10, S11, S12 (including lane change and garage) have completed 65.2%, 58.97%, 43.2% respectively.

In addition, construction activities are taking place at all construction sites. At station S10, the external structure is being implemented. At station S11, the base slab is being constructed. At station S12, the waterproofing system is being constructed south of the top slab. The lane change and garage are being cut and the road is being restored; at the underground ramp area, excavation and construction of the box tunnel structure are being carried out at the same time.

Previously, at the end of July 2024, the TBM (Tunnel Boring Machine) excavator began drilling the underground section of the Nhon - Hanoi station metro line.

TBM No. 1 (named Than Toc) drilled from Station S9 - Kim Ma at a depth of 17.8 m. To date, TBM1 has constructed 625 m of tunnel, 420 tunnel lining rings have been installed.

TBM No. 2 (named Bold) is expected to start construction in January 2025.

Two robots are digging two parallel tunnels from Station S9 - Kim Ma Station to Station S12 - Tran Hung Dao Station. According to the plan, the 4km underground tunnel of Nhon - Hanoi Station metro will be completed in October 2025.

The Nhon - Hanoi Railway Station Metro is 12.5 km long, with 8 elevated stations and 4 underground stations. Of which, the elevated section from Nhon to Cau Giay is 8.5 km long and the underground section from Cau Giay to Hanoi Railway Station is 4 km long.

Route: Starting point Nhon - along National Highway 32 - Cau Dien - Mai Dich - intersection with Ring Road 3 - Cau Giay (intersection with Ring Road 2) - Kim Ma - Cat Linh - Quoc Tu Giam - Hanoi station (on Tran Hung Dao street).

Trains from Station S8 (Thu Le) will go down to the basement (the ramp has been built next to Daewoo Hotel) then enter tunnel S9, passing through S10, S11, S12 (last station, opposite Hanoi station).

The project started in 2009 and was scheduled to be completed in 2015, but the schedule was delayed several times. On August 8, 2024, the elevated section began commercial operations, and the entire line is expected to be completed in 2027.

HỮU CHÁNH
RELATED NEWS

Underground metro section Nhon - Hanoi station revealed

|

Hanoi - The progress of the underground metro section Nhon - Hanoi station has reached 50.27%, in which the TBM excavator has drilled more than 600m underground.

Research on expanding Nhon - Hanoi station metro to Hoang Mai

|

The EU has mobilized 10 million euros to finance preparations for the extension of the Nhon - Hanoi Railway Station metro line to Hoang Mai district (Hanoi).

Hanoi holds commercial operation ceremony of Nhon - Hanoi Railway Station metro

|

On the morning of November 9, the Hanoi People's Committee held a commercial operation ceremony for the elevated section of the Nhon - Hanoi Railway Station metro line.

Can Tho: Thousands of jobs waiting for workers

|

Can Tho - Recruitment demand continues to increase, but the number of job seekers cannot keep up, causing many businesses to fall into a shortage of human resources.

US attacks Iran for the 7th consecutive night

|

The conflict spread throughout the region as the US and Iran simultaneously targeted civilian and military infrastructure, pushing the Middle East to the brink of a full-scale escalation.

Heavy rain causes serious landslides in Mu Cang Chai, urgent evacuation of people

|

Lao Cai - Prolonged heavy rain has damaged dozens of houses in Mu Cang Chai and cut off many traffic routes.

2026 World Cup Final: Waiting for Messi to neutralize Spain's defense

|

Spain's solid defense will be tested by Messi's talent in the 2026 World Cup final.

7 Colonels, 1 Senior Colonel of the Army receive new assignments

|

7 Colonels, 1 Senior Colonel of the Army have just been transferred, appointed, and handed over new responsibilities and tasks.

Underground metro section Nhon - Hanoi station revealed

HỮU CHÁNH |

Hanoi - The progress of the underground metro section Nhon - Hanoi station has reached 50.27%, in which the TBM excavator has drilled more than 600m underground.

Research on expanding Nhon - Hanoi station metro to Hoang Mai

Tô Thế |

The EU has mobilized 10 million euros to finance preparations for the extension of the Nhon - Hanoi Railway Station metro line to Hoang Mai district (Hanoi).

Hanoi holds commercial operation ceremony of Nhon - Hanoi Railway Station metro

Thế Kỷ |

On the morning of November 9, the Hanoi People's Committee held a commercial operation ceremony for the elevated section of the Nhon - Hanoi Railway Station metro line.