Nearly 50% of the project site worth 1,500 billion VND in Dong Nai has just been handed over

HÀ ANH CHIẾN |

Dong Nai - The Bien Hoa City central axis road project has a total investment of more than 1,500 billion VND, started construction in early 2023 but so far only nearly 50% of the site has been handed over.

5 construction packages of the new Bien Hoa City central road project have reached more than 25%

On November 5, according to the Dong Nai Province Traffic Construction Investment Project Management Board, the progress of the Bien Hoa City central axis road construction project, from Vo Thi Sau Street to Dang Van Tron Street (Thong Nhat Bridge and the road connecting the two ends of the bridge) - so far only nearly 50% of the construction site area has been handed over.

Regarding implementation progress, the investor has signed contracts and implemented construction of 5 main construction packages (including 2 bridge packages and 3 road packages) with the implementation value of the packages reaching about 25.6%.

Du an duong truc trung tam TP Bien Hoa moi ban giao gan 50% mat bang. Anh: HAC
The Bien Hoa City central axis road project has just handed over nearly 50% of the land. Photo: HAC

According to the Dong Nai Province Traffic Construction Investment Project Management Board, only about 48.2% of the project's construction site has been handed over so far (16.09 hectares of residential land, traffic, rivers and streams).

However, the discontinuous site has led to the failure to synchronously implement construction items.

Dong Nai Province Traffic Construction Investment Project Management Board recommends that the Provincial Land Fund Development Center promptly complete site clearance compensation.

Regarding the dumping site serving the project construction, the Management Board recommends that the People's Committee of Bien Hoa City support the arrangement of public land and low-lying areas in the area to serve as dumping sites for the project (which are common wastes during the project construction process).

Construction started nearly 2 years ago and only 50% of the site has been handed over

The project to build the central axis road of Bien Hoa city is 5.4 km long, divided into 2 branches.

In which, branch 1 starts at the intersection of Vo Thi Sau Street and ends at the intersection of Dang Van Tron Street (at An Hao Bridge intersection) with a road section 3.1 km long, 60 m wide, and Thong Nhat Bridge section 563.8 m long, 31 m wide.

Branch 2 has its starting point at the roundabout intersection with branch 1 (Hiep Hoa ward), its ending point is at the intersection of Dang Van Tron street (at the intersection of Buu Hoa bridge head road) with a route length of about 1.7 km, roadbed width of 47 m.

Mat bang du an duong truc trung tam TP Bien Hoa ben phia phuong Hiep Hoa, TP Bien Hoa. Anh: HAC
Project site of Bien Hoa city central axis road on Hiep Hoa ward side, Bien Hoa city. Photo: HAC

The Bien Hoa City Central Axis Road Project with Thong Nhat Bridge and the road connecting the two ends of the bridge with a total investment of more than VND 1,506 billion was started on January 31, 2023 and is expected to be completed after nearly 3 years of construction.

The construction unit of Thong Nhat Bridge and the approach roads at both ends of the bridge is a joint venture of Mekong Construction Investment Joint Stock Company No. 1 - CII Infrastructure Construction Joint Stock Company - Vinadelta Joint Stock Company - SHC Joint Stock Company.

This is a key traffic project of Dong Nai province, but after nearly 2 years of construction, it still faces many difficulties regarding the site.

Mr. Ngo The An - Director of the Management Board of Traffic Construction Investment Projects of Dong Nai province - recently said that the Bien Hoa city central axis road project, Huong Lo 2 road project and Vam Cai Sut bridge all have an implementation period of 2020-2024.

If not completed in 2024, the project must continue to be adjusted, the implementation time must be extended, and the construction time must be prolonged.

Besides, the delay in completion and putting into operation will affect the socio-economic development of Bien Hoa city and Dong Nai province.

For construction contractors, having to extend construction time puts them at risk of being affected by fluctuations in construction material prices.

The Dong Nai Province Traffic Construction Investment Project Management Board said that the Bien Hoa City Central Road Construction Project requires clearing an area of ​​over 33 hectares with 380 households. Of which, 50 households are from Thong Nhat Ward and 330 households are from Hiep Hoa Ward, both in Bien Hoa City.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Hanoi gateway road to be expanded 6 times, capital of nearly 1,500 billion VND

|

The main gateway road to Hanoi is about to be widened from 7-8m to 52m to help reduce traffic congestion and contribute to the socio-economic development of the capital.

Fierce fire at rice husk warehouse in Dong Thap, expected to last all night

|

Dong Thap - The rice husk warehouse is burning fiercely and over a large area. Local authorities mobilized firefighting forces throughout the night to control the spread of the fire.

Dak Lak today has transformed and grown strongly

|

Dak Lak - In the period of 2021 - 2023, the province's economic growth will average 7%/year, and the economic scale will increasingly expand.

School health worker job position is "forgotten"

|

Ninh Binh - Currently, many school health officials in Ninh Binh city are still in the "support and service" group, which has affected their benefits.

Proposal to add monitoring activities for citizen reception

|

National Assembly delegates proposed adding activities to monitor citizen reception to reduce voters' petitions to the Central level.

Thai Binh Provincial Party Secretary appointed Deputy of Central Propaganda Department

|

Thai Binh Provincial Party Secretary Ngo Dong Hai was transferred and appointed to the position of Deputy Head of the Central Propaganda Department.

"3 cars in, 1 car out", parking lot violations face difficulty in finding a solution

|

Currently, many parking lots for vehicles in violation are overloaded because the owners have not come to claim them for a long time.

People look forward to walking on the 512 billion VND bridge connecting District 7 and Nha Be

|

HCMC - Local people are eagerly awaiting the day when traffic can travel on Rach Dia bridge connecting District 7 and Nha Be district after many years of waiting.

Hanoi gateway road to be expanded 6 times, capital of nearly 1,500 billion VND

HỮU CHÁNH |

The main gateway road to Hanoi is about to be widened from 7-8m to 52m to help reduce traffic congestion and contribute to the socio-economic development of the capital.

Dự án giao thông 1.500 tỉ đồng xuyên tâm TP Biên Hòa ì ạch do chờ mặt bằng

HÀ ANH CHIẾN |

Đồng Nai - Theo ghi nhận của phóng viên Báo Lao Động, dự án đường trục trung tâm TP Biên Hòa với hạng mục cầu Thống Nhất băng qua sông Cái cùng đường kết nối 2 đầu cầu (tổng mức đầu tư hơn 1.500 tỉ đồng) đến nay vẫn đang gặp vướng mắc do mặt bằng thi công không liên tục dẫn đến chưa triển khai thi công đồng bộ các hạng mục xây lắp.

Đường 1.500 tỉ đồng nối Biên Hòa và cao tốc TPHCM - Long Thành vướng 250m mặt bằng

HÀ ANH CHIẾN |

Đồng Nai - Ngày 27.5, theo thông tin từ Ban Quản lý dự án đầu tư xây dựng công trình giao thông tỉnh Đồng Nai, đến nay, Dự án Đầu tư xây dựng đường Hương Lộ 2 nối dài (đoạn 1 - giai đoạn 1), TP Biên Hoà vẫn còn vướng mặt bằng 250m đoạn qua xã Long Hưng, TP Biên Hòa. Dự án này kết nối với cao tốc TPHCM - Long Thành - Dầu Giây và giảm tải cho Quốc lộ 51.