Many sections of Hanoi's Ring Road 4 have not been handed over

HỮU CHÁNH |

Hanoi strives to complete the Ring Road 4 parallel road in 2025, but up to now, there are still 18 sections of the site that have not been handed over to the contractor for construction.

The Hanoi Traffic Construction Investment Project Management Board has just released information related to the progress of the Ring Road 4 project through the city.

According to the Project Management Board, the city has so far approved and reclaimed 787.75/798.65 hectares, reaching 98.64%, the remaining 10.9 hectares have not been cleared in Me Linh, Dan Phuong, Hoai Duc districts and Ha Dong district.

The city has received 776.97/785.42 hectares of land, equivalent to 48.36/52.73km, reaching 91.7%. However, there are still many interruptions and bean sprouts on the route (about 18 sections have not been handed over the site, about 4.38km long).

Mot so ho dan o xa Ha Mo (huyen Dan Phuong) chua ban giao mat bang cho du an. Anh: Huu Chanh
Some households in Ha Mo commune (Dan Phuong district) have not yet handed over the land for the project. Photo: Huu Chanh

Relevant units have completed 13/13 resettlement areas, handing over residential land to 346/1,079 households. The city strives to complete site clearance and hand over the entire site in the second quarter of 2025.

It is expected that the relocation of technical infrastructure items will be completed in the first quarter of 2025.

Regarding the progress of the implementation of component projects through Hanoi, after 20 months from the groundbreaking date, 4 construction packages of component project 2.1 - Construction of parallel roads (urban roads) have been simultaneously deployed by contractors on the area of land handed over, equivalent to 48.35/52.43km with 32 construction points (23 road points, 9 bridge points).

To date, the volume of roadbed sand filling is about 85.01%; roadbed filling is about 62.27%; crushed stone aggregate is about 35.04%.

In Me Linh, Dan Phuong, Hoai Duc districts, the contractor has constructed about 30km of asphalt concrete. The progress is expected to be completed in the fourth quarter of 2025.

Duong song hanh Vanh dai 4 doan qua huyen Van Khe (Me Linh) da duoc tham nhua mat duong. Anh: Huu Chanh
The parallel road of Ring Road 4 through Me Linh district has been paved with asphalt. Photo: Huu Chanh

For component project 3 - Investment in the construction of the expressway system under the public-private partnership method, the Project Management Board strives to complete the selection of investors and start the project in the second quarter of@2025.

The investment project to build the Ring Road 4 in the Capital Region has a total length of about 113.52km (of which 103.82km is the main route and 9.7km is the connecting route towards Noi Bai - Ha Long Expressway), starting point at Km3+695 of the Noi Bai - Lao Cai Expressway, ending point at Km40+500 of the Noi Bai - Ha Long Expressway.

The section in Hanoi is about 57.52km long; the section in Hung Yen province is about 19.3km; the section in Bac Ninh province is about 35.7km.

The completion of Ring Road 4 in the Capital Region will contribute to relieving traffic congestion, connecting provinces and creating new development space for the entire Capital Region, including Hanoi, Hung Yen and Bac Ninh.

HỮU CHÁNH
RELATED NEWS

Another delay in handing over the site for the Tam Trinh road expansion project

|

Hanoi - Hoang Mai District has postponed the site clearance progress of the Tam Trinh road expansion project until April 2025 due to some remaining difficulties and problems waiting to be resolved.

Hanoi to enforce land acquisition to open 30m wide road

|

Hanoi - The People's Committee of Thuong Tin district has planned to organize compulsory land recovery of some households that do not agree to hand over the land to implement the expansion of National Highway 1A.

Hanoi expels 14 Party members of the Central Institute of Forensic Psychiatry

|

Hanoi - The Inspection Committee of the City Party Committee expelled 14 Party members of the Central Institute of Forensic Psychiatry Party Committee and disciplined many related groups with warnings and reprimand.

Prime Minister directs strict handling of hoarding, price increase, gold smuggling

|

The Prime Minister requested the State Bank of Vietnam to strengthen inspection, examination, and strictly handle acts of hoarding, price increase, and gold smuggling.

The salary that Bich Thuy can receive if competing in Japan

|

Many predict that Tran Thi Bich Thuy will go to Japan, however, she still participates in the second phase of the 2025 National Volleyball Championship.

Controversy over "Red Rain" and the hardship of historical war films

|

Controversies about some fictional details in "Red Rain" show difficulties in producing historical films, even in world cinema.

Mr. Nguyen Khac Toan was elected to hold the position of Chairman of Khanh Hoa Provincial People's Committee

|

Khanh Hoa - Mr. Nguyen Khac Toan - Standing Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council, was elected to hold the position of Chairman of the Khanh Hoa Provincial People's Committee for the 2021 - 2026 term.

Another delay in handing over the site for the Tam Trinh road expansion project

HỮU CHÁNH |

Hanoi - Hoang Mai District has postponed the site clearance progress of the Tam Trinh road expansion project until April 2025 due to some remaining difficulties and problems waiting to be resolved.

Đường hơn 1km ở Nam Từ Liêm làm 5 năm chưa xong

HỮU CHÁNH |

Hà Nội - Thi công từ năm 2020 nhưng đến nay dự án xây dựng đoạn đường dài 1,2km ở Nam Từ Liêm vẫn chưa hoàn thiện, ảnh hưởng đến cuộc sống của người dân.

Hanoi to enforce land acquisition to open 30m wide road

HỮU CHÁNH |

Hanoi - The People's Committee of Thuong Tin district has planned to organize compulsory land recovery of some households that do not agree to hand over the land to implement the expansion of National Highway 1A.