Many sections of Hanoi's Ring Road 4 have not been handed over

HỮU CHÁNH |

Hanoi strives to complete the Ring Road 4 parallel road in 2025, but up to now, there are still 18 sections of the site that have not been handed over to the contractor for construction.

The Hanoi Traffic Construction Investment Project Management Board has just released information related to the progress of the Ring Road 4 project through the city.

According to the Project Management Board, the city has so far approved and reclaimed 787.75/798.65 hectares, reaching 98.64%, the remaining 10.9 hectares have not been cleared in Me Linh, Dan Phuong, Hoai Duc districts and Ha Dong district.

The city has received 776.97/785.42 hectares of land, equivalent to 48.36/52.73km, reaching 91.7%. However, there are still many interruptions and bean sprouts on the route (about 18 sections have not been handed over the site, about 4.38km long).

Mot so ho dan o xa Ha Mo (huyen Dan Phuong) chua ban giao mat bang cho du an. Anh: Huu Chanh
Some households in Ha Mo commune (Dan Phuong district) have not yet handed over the land for the project. Photo: Huu Chanh

Relevant units have completed 13/13 resettlement areas, handing over residential land to 346/1,079 households. The city strives to complete site clearance and hand over the entire site in the second quarter of 2025.

It is expected that the relocation of technical infrastructure items will be completed in the first quarter of 2025.

Regarding the progress of the implementation of component projects through Hanoi, after 20 months from the groundbreaking date, 4 construction packages of component project 2.1 - Construction of parallel roads (urban roads) have been simultaneously deployed by contractors on the area of land handed over, equivalent to 48.35/52.43km with 32 construction points (23 road points, 9 bridge points).

To date, the volume of roadbed sand filling is about 85.01%; roadbed filling is about 62.27%; crushed stone aggregate is about 35.04%.

In Me Linh, Dan Phuong, Hoai Duc districts, the contractor has constructed about 30km of asphalt concrete. The progress is expected to be completed in the fourth quarter of 2025.

Duong song hanh Vanh dai 4 doan qua huyen Van Khe (Me Linh) da duoc tham nhua mat duong. Anh: Huu Chanh
The parallel road of Ring Road 4 through Me Linh district has been paved with asphalt. Photo: Huu Chanh

For component project 3 - Investment in the construction of the expressway system under the public-private partnership method, the Project Management Board strives to complete the selection of investors and start the project in the second quarter of@2025.

The investment project to build the Ring Road 4 in the Capital Region has a total length of about 113.52km (of which 103.82km is the main route and 9.7km is the connecting route towards Noi Bai - Ha Long Expressway), starting point at Km3+695 of the Noi Bai - Lao Cai Expressway, ending point at Km40+500 of the Noi Bai - Ha Long Expressway.

The section in Hanoi is about 57.52km long; the section in Hung Yen province is about 19.3km; the section in Bac Ninh province is about 35.7km.

The completion of Ring Road 4 in the Capital Region will contribute to relieving traffic congestion, connecting provinces and creating new development space for the entire Capital Region, including Hanoi, Hung Yen and Bac Ninh.

HỮU CHÁNH
TIN LIÊN QUAN

Another delay in handing over the site for the Tam Trinh road expansion project

|

Hanoi - Hoang Mai District has postponed the site clearance progress of the Tam Trinh road expansion project until April 2025 due to some remaining difficulties and problems waiting to be resolved.

Hanoi to enforce land acquisition to open 30m wide road

|

Hanoi - The People's Committee of Thuong Tin district has planned to organize compulsory land recovery of some households that do not agree to hand over the land to implement the expansion of National Highway 1A.

Social housing is stalled due to procedures

|

HCMC - Many social housing projects have been widely announced, but cannot be implemented due to prolonged legal procedures.

Mercedes driver hits a series of vehicles waiting for red lights when having alcohol concentration

|

HCMC - On the evening of March 16, the authorities determined that the female Mercedes driver who caused the series of accidents at Thu Duc intersection had alcohol concentration on her body.

pine forest fire under Da Lat cable car, black smoke

|

Lam Dong - A major forest fire occurred in the pine forest area under the cable car route in Da Lat. Black smoke rose high and spread, causing suffocation and difficulty breathing for people.

Live football Arsenal 1-0 Chelsea: Second half

|

Live match between Arsenal vs Chelsea in round 29 of the Premier League takes place at 20:30 on March 16.

Coming to Hanoi is no longer a nightmare for international tourists

|

Hanoi - Thanks to improved infrastructure and traffic awareness, international tourists can now clearly feel the change when traveling on Hanoi streets.

5-storey hotel fire in Ho Chi Minh City, 6 people escaped

|

HCMC - A hotel in Thu Duc City suddenly caught fire, 6 people inside were fortunately rescued by firefighters.

Another delay in handing over the site for the Tam Trinh road expansion project

HỮU CHÁNH |

Hanoi - Hoang Mai District has postponed the site clearance progress of the Tam Trinh road expansion project until April 2025 due to some remaining difficulties and problems waiting to be resolved.

Đường hơn 1km ở Nam Từ Liêm làm 5 năm chưa xong

HỮU CHÁNH |

Hà Nội - Thi công từ năm 2020 nhưng đến nay dự án xây dựng đoạn đường dài 1,2km ở Nam Từ Liêm vẫn chưa hoàn thiện, ảnh hưởng đến cuộc sống của người dân.

Hanoi to enforce land acquisition to open 30m wide road

HỮU CHÁNH |

Hanoi - The People's Committee of Thuong Tin district has planned to organize compulsory land recovery of some households that do not agree to hand over the land to implement the expansion of National Highway 1A.