Quang Binh enforces land clearance for North-South expressway

CÔNG SÁNG |

The People's Committee of Le Thuy district ( Quang Binh ) has issued 5 decisions, 12 cases are completing documents for enforcement to return the land for the North-South expressway .

99.67% of the land has been delivered

The North-South Expressway construction project in the Eastern phase 2021 - 2025, the section through Quang Binh province, has 3 component projects, with a length of 126.43km, passing through 6 districts, towns, cities and 35 communes and wards.

Up to now, the length of Quang Binh province handed over to the Project Management Boards is 126.01km (accounting for 99.67%), currently there are 419m remaining in the land clearance (accounting for 0.33%).

Of which, Quang Trach district has handed over 25.29km/25.3km. Bo Trach district has handed over 29.03km/29.04km. Le Thuy district has handed over 31.553km/31.952km.

The North-South Expressway through Quang Binh, Le Thuy district, is still stuck. Photo: Cong Sang
The North-South Expressway through Quang Binh, Le Thuy district, is still stuck. Photo: Cong Sang

A representative of the Ho Chi Minh Project Management Board, the investor of the Van Ninh - Cam Lo component project, said that in Le Thuy district, there are still 399m of land acquisition problems, which affect the project's progress.

"We are looking forward to having a site to speed up progress because the rainy season is approaching," said this representative.

Mr. Nguyen Xuan Tuong - Vice Chairman of the Le Thuy District Expressway Clearance Council - said that there are still 399m in the area related to 19 cases, of which 5 cases the district has issued enforcement decisions, 12 cases are completing documents for enforcement; one case is in Korea, expected to return home on September 8 to receive money, one case we are still continuing to mobilize.

“The Provincial Party Secretary has made a working trip to the area, through which, when all procedures and regulations are fully implemented, enforcement must be carried out, and a few cases cannot affect the national project. After the decision on enforcement within 10 days or according to the specific time of the locality, it must be carried out, the district has decided to complete the site clearance in September,” said Mr. Tuong.

Land acquisition issues have prevented construction of some sections of the North-South Expressway through Quang Binh province. Photo: Cong Sang
Land acquisition issues have prevented some sections of the North-South Expressway through Quang Binh province from being constructed. Photo: Cong Sang

Implement solutions in accordance with regulations

Mr. Dang Dai Tinh - Chairman of Le Thuy District People's Committee - said that the site clearance work in Le Thuy district is more difficult because it is the longest area in the province, the project passes through the most densely populated area with nearly 1,000 households. Along with that, the land history is complicated, land transferred from forestry farms, encroached land, disputed land, no origin of land use time... so it takes a lot of time to handle. Along with that, the district is also stuck with solar power and nearly 700 graves.

After inspecting the progress of the North-South Eastern Expressway project, phase 2021-2025 through Quang Binh in Phu Thuy commune (Le Thuy), Secretary of the Quang Binh Provincial Party Committee Vu Dai Thang made proposals related to compensation, site clearance, and resettlement.

The Provincial Party Secretary emphasized the need to continue considering solutions to ensure harmony of interests for people and businesses.

For households subject to compensation and site clearance, after being informed, mobilized, and fully implementing policies but still not agreeing and handing over the site to the construction unit, it is necessary to implement solutions in accordance with regulations to clear the route, avoiding affecting the entire project because of a few individuals.

CÔNG SÁNG
RELATED NEWS

Xuyên lễ trên công trường cao tốc Bắc - Nam qua Quảng Bình

CÔNG SÁNG |

Những ngày nghỉ lễ, trên công trường cao tốc Bắc – Nam qua Quảng Bình vẫn rộn ràng máy móc, công nhân nhằm đẩy nhanh tiến độ công trình.

Dự án cao tốc Bắc - Nam qua Quảng Bình còn vướng mặt bằng

CÔNG SÁNG |

Công tác giải phóng mặt bằng Dự án xây dựng công trình đường bộ cao tốc Bắc - Nam phía Đông đoạn qua địa phận tỉnh Quảng Bình đến này vẫn còn hơn 500m.

Hơn 3.000 tỉ mở rộng cao tốc Bắc - Nam, đoạn qua Thừa Thiên Huế và Đà Nẵng

Huy Hùng |

Bộ Tài nguyên và Môi trường đang lấy ý kiến tham vấn cộng đồng dự án mở rộng cao tốc Bắc - Nam phía Đông, đoạn La Sơn - Hòa Liên.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Phá đường dây cờ bạc nghìn tỉ qua mạng, tạm giam 12 người

Thành Nhân |

Bến Tre - Lực lượng Công an vừa triệt xóa đường dây cờ bạc trên không gian mạng với tổng số tiền giao dịch hơn 1.800 tỉ đồng.

Nổ nồi hấp tinh dầu, 1 bé gái bị thương, 5 căn nhà ảnh hưởng

LÝ LINH |

TPHCM - Ngày 15.10, Công an huyện Bình Chánh đang điều tra vụ nổ nồi hấp tại một cơ sở sản xuất tinh dầu trên địa bàn xã Vĩnh Lộc A khiến một bé gái bị thương.

Nguyên chủ tịch xã ở Thái Bình bị tố lạm quyền để trục lợi

TRUNG DU |

Thái Bình - Nguyên Chủ tịch UBND xã Quỳnh Hải, huyện Quỳnh Phụ bị tố lợi dụng chức vụ quyền hạn để tư lợi, trục lợi cho bản thân, gia đình.

Xuyên lễ trên công trường cao tốc Bắc - Nam qua Quảng Bình

CÔNG SÁNG |

Những ngày nghỉ lễ, trên công trường cao tốc Bắc – Nam qua Quảng Bình vẫn rộn ràng máy móc, công nhân nhằm đẩy nhanh tiến độ công trình.

Dự án cao tốc Bắc - Nam qua Quảng Bình còn vướng mặt bằng

CÔNG SÁNG |

Công tác giải phóng mặt bằng Dự án xây dựng công trình đường bộ cao tốc Bắc - Nam phía Đông đoạn qua địa phận tỉnh Quảng Bình đến này vẫn còn hơn 500m.

Hơn 3.000 tỉ mở rộng cao tốc Bắc - Nam, đoạn qua Thừa Thiên Huế và Đà Nẵng

Huy Hùng |

Bộ Tài nguyên và Môi trường đang lấy ý kiến tham vấn cộng đồng dự án mở rộng cao tốc Bắc - Nam phía Đông, đoạn La Sơn - Hòa Liên.