Accelerating the construction of Hanoi Ring Road 4, many sections have been revealed

HỮU CHÁNH |

Hanoi - The packages of the Ring Road 4 parallel road project are being accelerated to complete in 2025.

According to Lao Dong in package No. 9 - construction of the Ring Road 4 parallel road through Dan Phuong and Hoai Duc districts (51km long) constructed by contractor Vinaconex, dozens of locomotives and a team of officers, engineers and workers were mobilized to work continuously "3 shifts, 4 teams".

Talking to reporters, Mr. Nguyen Hoang Hai - Commander of package No. 9 - said that up to now, the package implemented by Vinaconex has reached about 56% of the contract value.

The contractor has completed the paving of about 19km of single-line road, the remaining sections are being paved with crushed stone. Some items of the canal overpass are also being urgently completed.

Vanh dai 4 doan qua huyen Dan Phuong (Ha Noi) da duoc tham nhua mat duong. Anh: Huu Chanh
The parallel road of Ring Road 4 through Dan Phuong District (Hanoi) has been paved with asphalt. Photo: Huu Chanh

Mr. Hai added that for key projects such as Ring Road 4, contractors need to make the most of favorable weather conditions, increase overtime and overtime.

"Although it is difficult, the entire team of engineers and workers are united and determined to complete the project on schedule" - Mr. Hai emphasized.

s
The factory and a residential area in Duc Thuong commune, Hoai Duc have not been cleared. Photo: Huu Chanh

Regarding site clearance, Mr. Hai informed that in package No. 9, there are still 3 residential areas in Duc Thuong, Dong La communes (Hoai Duc) and Ha Mo commune (Dan Phuong).

"Currently, relevant units are relocating underground and above-ground technical infrastructure to hand over the site to the contractor. However, for these 3 residential areas, we do not know the date when the site will be handed over to continue construction of the project" - Mr. Nguyen Hoang Hai said.

Cong truong du an duong Vanh dai 4 doan qua xa, huyen Hoai Duc. Anh: Huu Chanh
Construction site of the Ring Road 4 project through Duc Thuong commune, Hoai Duc district. Photo: Huu Chanh
May moc, cong nhan dang trien khai hang muc rai cap phoi da dam. Anh: Huu Chanh
Machinery and workers are implementing the crushed stone allocation project. Photo: Huu Chanh
Nhieu may moc, cong nhan lam viec tren cong truong du an. Anh: Huu Chanh
Many machines and workers are working at the project site. Photo: Huu Chanh

In package No. 8, according to Mr. Nguyen Hoai Nam - Head of Technical Department, Construction Management Board of Ring Road 4 in the Capital Region, Truong Son Construction Corporation - the package has a total length of about 23km, of which about 20km of parallel roads have been paved with asphalt.

Package 8 also undertakes the construction of 3 overpasses on the route including the Ca Lo River overpass connecting Soc Son with Me Linh, the Hanoi - Lao Cai railway overpass and the Hau village bridge.

Cong nhan thi cong hang muc cau vuot song Ca Lo noi huyen Me Linh va Soc Son. Anh: Huu Chanh
Workers constructing the Ca Lo river overpass project connecting Me Linh and Soc Son districts. Photo: Huu Chanh

Regarding the progress of package No. 8, Mr. Nam said that up to this point, the contractor consortium has completed about 70% of the construction volume, ensuring progress compared to the plan.

According to Mr. Nguyen Hoai Nam, there are still 2 residential areas in Dai Thinh and Chu Phan communes (Me Linh) that have not been handed over.

"For the sections that have cleared the ground, the consortium of contractors is committed to completing the Ring Road 4 parallel road section through Me Linh and Soc Son in 2025" - Mr. Nam affirmed.

Cau vuot duong sat thuoc goi thau so 8 cung dang duoc thi cong hoan thien. Anh: Huu Chanh
The railway overpass under package 8 is also under construction. Photo: Huu Chanh

In package No. 10 (through Ha Dong district and Thanh Oai district) and package No. 11 (through Thuong Tin district), contractors are also speeding up the construction progress to ensure the progress of the entire route.

The Ring Road 4 project in the Capital Region started construction in June 2023, with a total length of 112.8km, passing through Hanoi, Hung Yen and Bac Ninh, with a total investment of more than VND 85,000 billion.

In Hanoi alone, the route is more than 57km long, passing through the districts: Ha Dong, Soc Son, Me Linh, Dan Phuong, Hoai Duc, Thanh Oai and Thuong Tin.

After 21 months since the groundbreaking date, 4 construction packages in Hanoi have been deployed simultaneously over a length of more than 48km, with 32 construction teams (including 23 road construction teams and 9 bridge construction teams).

Hanoi City aims to complete all site clearance work before April 15 and put the parallel road into operation in October 2025, welcoming the City Party Congress.

HỮU CHÁNH
TIN LIÊN QUAN

Hanoi has 2 weeks left to hand over enough land to build Ring Road 4

|

Hanoi - Districts must complete site clearance for the Ring Road 4 project before April 15 according to the direction of the Chairman of the City People's Committee.

River-crossing bridges and railways on Hanoi's Ring Road 4 take shape

|

Hanoi - The three river-crossing bridges and railway of the Ring Road 4 parallel road project through Me Linh district have been revealed and are under construction.

Hanoi reclaims land for Ring Road 1, accelerates progress of Ring Road 4

|

Hanoi is focusing on reclaiming land for the construction of Ring Road 1 from Hoang Cau to Voi Phuc, accelerating the completion of the Ring Road 4 parallel road in the fourth quarter of 2025.

The stock market continues to fall sharply, VN-Index loses more than 67 points

|

The Vietnamese stock market reopened after the holiday with selling pressure returning, red and light blue covering the electricity billboard.

Customers who mistakenly auctioned 4.92 billion VND/m2 of land in Hung Yen burst into tears because they were afraid of losing their deposit

|

On April 8, Mr. Pham Van Mien, Van Tuong village, Bao Khe commune, Tien Lu district (Hung Yen) burst into tears when he accidentally told the auction story, causing 1m2 of land to cost up to 4.92 billion VND.

Violations at VietGap vegetable production project in Binh Dinh

|

Binh Dinh - Through inspection, the authorities discovered many violations at the VietGap Safety Vegetable Production Project in Canh Vinh Commune (Van Canh District).

Ukraine confirms sending troops into Russian territory

|

On the evening of April 7, Ukrainian President Volodymyr Zelensky officially confirmed that the country's armed forces are present in Belgorod province under Russian territory.

Hanoi is suffocated and polluted on the first day of work after the holidays

|

Hanoi - Today, April 8, the first working day after the Hung Kings' Commemoration Day holiday, the streets returned to a state of congestion and pollution.

Hanoi has 2 weeks left to hand over enough land to build Ring Road 4

HỮU CHÁNH |

Hanoi - Districts must complete site clearance for the Ring Road 4 project before April 15 according to the direction of the Chairman of the City People's Committee.

River-crossing bridges and railways on Hanoi's Ring Road 4 take shape

HỮU CHÁNH |

Hanoi - The three river-crossing bridges and railway of the Ring Road 4 parallel road project through Me Linh district have been revealed and are under construction.

Hanoi reclaims land for Ring Road 1, accelerates progress of Ring Road 4

HỮU CHÁNH |

Hanoi is focusing on reclaiming land for the construction of Ring Road 1 from Hoang Cau to Voi Phuc, accelerating the completion of the Ring Road 4 parallel road in the fourth quarter of 2025.