Another sand mine put into operation to serve the highway

PHƯƠNG ANH |

Soc Trang - MS12 sand mine with a reserve of 645,000m3 is exploited to serve component project 4, Chau Doc - Can Tho - Soc Trang expressway.

On October 11, the People's Committee of Soc Trang province coordinated with Truong Son Construction Corporation (Army Corps 12) to organize the groundbreaking ceremony for the MS12 sand mine to serve the component 4 project of Chau Doc - Can Tho - Soc Trang expressway (section through Soc Trang province).

According to the People's Committee of Soc Trang province, the MS12 sand mine is located on the Hau River in An Lac Tay commune, Ke Sach district (Soc Trang province), with a total area of ​​over 60.2 hectares and a reserve of over 645,000m3. The total reserve allowed for exploitation is 628,003m3. The exploitation capacity from January to July is 78,000m3/month, equivalent to 3,000m3/day. From August to the 13th month, the exploitation capacity is 12,000m3/month, equivalent to 462m3/day. In the 14th month, the exploitation capacity is 10,003m3/month, equivalent to 385m3/day.

Exploitation period: 14 months from October 10, 2024. Exploitation from 7am to 5pm, no exploitation at night.

The exploitation depth is from cote level -8.8m to cote level -13.5m (national elevation system). The riverbed depth after the end of exploitation, environmental improvement and restoration is from cote -10.1m to cote -12.1m.

Nha thau khai thac mo cat MS12 phuc vu du an thanh phan 4 cao toc Chau Doc - Can Tho - Soc Trang (doan qua tinh Soc Trang). Anh: So TNMT tinh Soc Trang
Contractor exploiting MS12 sand mine to serve component 4 project of Chau Doc - Can Tho - Soc Trang expressway (section through Soc Trang province). Photo: Department of Natural Resources and Environment of Soc Trang province

Up to now, there are 2 sand mines (MS01, MS03) supplying sand for Component 4 Project with a maximum volume of 0.9 million m3/6.6 million m3 of sand by June 2025 (short of 5.7 million m3). The total maximum exploitation capacity of the mines (according to the exploitation license) has only reached 4,295m3/22,000m3/day.

Putting MS12 sand mine into operation aims to proactively source sand materials, meeting the construction progress of key projects under the direction of the Prime Minister.

PHƯƠNG ANH
RELATED NEWS

Trade union news: Dong Nai will provide job counseling for 33,000 people in the second quarter

|

Trade union news on March 22: Dong Nai will provide job counseling for 33,000 people in the second quarter; Expected base salary increase for the army and police from July 1...

Nghe An traffic police take critically ill people to the emergency room in time

|

Nghe An - Traffic police quickly used specialized vehicles to take the seriously injured woman to a medical facility, helping the victim overcome the critical condition.

Many cars have broken windows while running on the expressway through Quang Tri

|

Quang Tri - Many cars moving on the highway are suspected of being hit by rocks and breaking windows, functional forces are investigating and clarifying the cause.

Chelsea loses 4 consecutive matches

|

In the early morning of March 22 (Vietnam time), the 0-3 defeat to Everton in the Premier League marked Chelsea's fourth consecutive defeat in all competitions.

Appointment and transfer of personnel in Hai Phong, Tay Ninh, Thanh Hoa, Ha Tinh

|

From March 16-21, decisions on appointment and transfer of personnel were implemented in many localities such as Hai Phong, Tay Ninh, Thanh Hoa, Dien Bien, Ha Tinh.

The future of Maguire and Mainoo at Man United is decided

|

Man United are negotiating contracts with two English stars Kobbie Mainoo and Harry Maguire ahead of the important summer transfer window.

List of 500 elected National Assembly Deputies of the 16th term

|

The National Election Council approved the list of people elected as National Assembly Deputies of the 16th term, including 500 people.

Ở bên mỏ cát, Quảng Ngãi vẫn thiếu cát trầm trọng

Viên Nguyễn |

UBND tỉnh Quảng Ngãi đã khoanh định 9 vị trí khai thác cát để cấp cho dự án Hoàng Sa - Dốc Sỏi với tổng vốn đầu tư 3.500 tỉ đồng, tuy nhiên, sau 10 tháng chưa có mỏ cát nào được cấp phép khai thác trong khi trữ lượng cát tại Quảng Ngãi rất lớn.

Urgently add sand to the highway for more than 11,900 billion VND

PHƯƠNG ANH |

Soc Trang - 2 sand mines are being exploited to serve Component Project 4. However, the capacity is still low compared to the current sand shortage demand.

Soc Trang Chairman requests installation of GPS for sand suction and transportation ships

PHƯƠNG ANH |

The Chairman of the People's Committee of Soc Trang province proposed that it is necessary to install GPS tracking devices for transport ships and suction ships to manage sand mining activities.