Progress of the North-South expressway rest stop through Quang Binh

CÔNG SÁNG |

Quang Binh - Up to now, 2 rest stops on the North-South Expressway passing through the area are in the process of clearing and handing over the land.

On December 26, the Department of Transport of Quang Binh province said that it is in the process of clearing the additional land to hand over to the investor.

In Quang Binh, there will be two rest stops in the North-South expressway project, located in Quang Chau commune (Quang Trach district) and Dong Son ward (Dong Hoi city).

According to the Quang Binh Department of Transport, the initial plan was that these two stations would cover 9.83 hectares of land. Site clearance and land handover had been carried out previously.

By September 2024, the Ministry of Transport will expand the area of ​​the two stations by an additional 10.17 hectares, so the locality is continuing to clear the land for this additional area.

Of the total 10.7 hectares, at the rest stop in Quang Chau commune, there are 7.05 hectares. The government has issued a notice of land recovery and counting, and is currently making a compensation and support plan.

At the rest stop in Dong Son ward, there are 3.12 hectares, currently completing documents to issue a land recovery notice.

It is expected that in 2024, the procedures for handing over the site to the investor will be completed.

Project Management Board 6 said that it is currently bidding to find an investor for this rest stop. Once the site is handed over and an investor is found, construction will begin. Regarding progress, it is expected to be completed by the end of 2025, and by April 30, 2025, there will be a temporary rest stop for people.

CÔNG SÁNG
TIN LIÊN QUAN

Quickly end the backlog on the North-South expressway through Quang Binh

|

Quang Binh - The locality is implementing measures to resolve the backlog on the North-South Expressway.

Bustling day and night at the North-South expressway construction site

|

Smooth traffic on the North-South axis is an urgent requirement for the country's socio-economic development in the new period. Especially in the condition that both the railway and National Highway 1A are degraded, narrow, and flooded. Therefore, the Government is very "impatient", continuously giving instructions and finding solutions to speed up the construction progress of the North-South expressway project.

Cancer patients in Ho Chi Minh City have to fly to Da Nang, Hanoi for PET/CT scan

|

The only cyclotron producing radioactive homology for PET/CT machines in Ho Chi Minh City has stopped operating, causing a series of large hospitals to temporarily suspend diagnostic services.

Forecast of heavy rain in the North

|

According to the representative of the meteorological agency, from the evening and night of June 20 to June 22, it is necessary to be on guard against heavy rain in the midlands and mountainous areas of the North.

Recall Hai Be delicious syrup nationwide for being counterfeit

|

The delicious Hai Be syrup was identified as a fake product, not licensed for circulation by the authorities and required to recall all products nationwide.

2025 National Newspaper Association brings together 130 unique exhibition booths

|

Hanoi - 130 exhibition booths, hundreds of unique publications representing key press lines from the central to local levels at the 2025 National Press Festival.

With lights but not bright, the park in the center of Ho Chi Minh City is dark all year round

|

HCMC - Many people reported that the park at the end of Dang Thuy Tram Street (Binh Thanh District) has been in a state of "having lights but not bright" for a long time.

Many foreign enterprises are slow to pay social insurance and evade social insurance

|

According to the reporter of Lao Dong Newspaper, in recent times, many foreign enterprises have been slow to pay social insurance (SI).

Hà Tĩnh đôn đốc giải phóng mặt bằng cao tốc Bắc - Nam

TRẦN TUẤN |

Hà Tĩnh - Phó Chủ tịch UBND tỉnh Hà Tĩnh Trần Báu Hà vừa ký văn bản đôn đốc hoàn thành giải phóng mặt bằng dự án cao tốc Bắc - Nam trên địa bàn.

Quickly end the backlog on the North-South expressway through Quang Binh

CÔNG SÁNG |

Quang Binh - The locality is implementing measures to resolve the backlog on the North-South Expressway.

Bustling day and night at the North-South expressway construction site

HỮU LONG - HOÀI LUÂN |

Smooth traffic on the North-South axis is an urgent requirement for the country's socio-economic development in the new period. Especially in the condition that both the railway and National Highway 1A are degraded, narrow, and flooded. Therefore, the Government is very "impatient", continuously giving instructions and finding solutions to speed up the construction progress of the North-South expressway project.