On April 9, according to information from the Office of the People's Committee of Son La province, the Provincial People's Committee has just approved a contractor selection plan for the project to build the Na Tra - Pa Chong - Bom Kham inter-village road to the center of Muong Bam commune, Thuan Chau district.
The project has a total investment of more than 10.9 billion VND, aiming to improve transport infrastructure in mountainous areas with many difficulties.
According to the approval decision, the project is divided into 3 main packages:
Package No. 01 - Construction: Total value of more than 10.5 billion VND, including items such as roadbed, vertical ditches, road surface, culverts. The package will be widely auctioned domestically online, with an expected construction period of 270 days.
Package No. 02 - Construction supervision: Valued at more than 332 million VND, implemented in the form of a shortened bidding period, the supervision period is extended throughout the construction process.
Package No. 03 - Independent audit: Valued at about 73 million VND, to conduct an audit of the investment capital settlement report after the project is completed.
The project uses capital from the central budget to support the implementation of the National Target Program for Socio-Economic Development in Ethnic Minority and Mountainous Areas, combined with the budget of Thuan Chau District.
Investor (People's Committee of Thuan Chau District) is responsible for organizing the selection of contractors in accordance with the Bidding Law, ensuring publicity, transparency and efficiency. At the same time, the unit must review and update the volume and value of the actual bidding package, avoiding loss and waste of public investment.
The Department of Finance of Son La province will coordinate to monitor and inspect bidding activities. In case of arising issues beyond their authority, this agency will report to the Provincial People's Committee for consideration and handling.