Good signs at the Hanoi Ring Road 4 construction site

HỮU CHÁNH |

Hanoi - Ring Road 4 section through Soc Son and Me Linh districts is accelerating construction progress. The contractor has carpeted the first meters of asphalt on the project site.

Returning to the construction site of Hanoi Ring Road 4 (package No. 8, section through Soc Son district, Me Linh) after a few months, Lao Dong Newspaper reporter noted that the scene here has had many clear changes.

Package No. 8 (line section from Km0+000 to Km13+017.92 of Component Project 2.1 Construction of parallel road in Hanoi City), dozens of workers, engineers and many machines are still busy. In the rhythm of day and night, there is almost no time for machines to be silent at the construction site.

Mr. Nguyen Van Thai - technical officer in charge of package No. 8 - said that, overcoming certain difficulties, the contractor is accelerating, ahead of schedule and has a reserve in case of adverse weather during the period. construction period.

Everyone always follows the construction site closely and accompanies the contractor to promptly resolve difficulties and problems on the construction site. At the same time, count progress daily and weekly to promptly urge and adjust if progress is slow...

Mr. Thai said that package number 8, section passing through Soc Son and Me Linh districts, has completed more than 35% of the construction volume. Particularly, the section passing through Tan Dan commune (Soc Son) has been covered with layers of asphalt to prepare for completion.

According to Mr. Thai, the carpeting of asphalt layers marks an important milestone in the construction process of Project Component 2.1.

“The road is being carpeted with C25 hollow plastic, after this layer there will be 2 more layers of carpet. This is the first section to be paved over the entire length of Ring Road 4 of the Capital Region" - Mr. Thai added.

Taking advantage of the sunny weather, contractors accelerated the process of asphalting the road surface. In addition, the contractor divided into many construction phases to carry out construction and installation work, speeding up the project progress.

After more than a year of implementation, the contractors constructing Ring Road 4 - Capital Region have basically completed the foundation and roadbed and are covering the first kilometers with asphalt concrete.
The contractor is paving the first kilometers of asphalt concrete through Tan Dan commune (Soc Son district, Hanoi) after more than 1 year of project implementation. Photo: Huu Chanh
The contractor mobilized 50 workers and machinery to deploy plastic mats
Each asphalt carpet team will have 20 workers and engineers. Photo: Huu Chanh
This is the first paved section of the Ring Road 4 Project - Capital Region. The road is being carpeted with C25 hollow plastic carpet, and then needs to be carpeted with 2 more layers.
This is the first paved section of the Capital Region Ring Road 4 project. Photo: Huu Chanh
Every day the construction unit can cover 200m of road surface. (In the photo, workers are carrying out the process of carpeting the road surface).
Workers are carrying out the process of carpeting the road surface. Every day the construction unit can cover 200m of road surface. Photo: Huu Chanh
The road section after being carpeted with C25 hollow plastic.
The road section after being carpeted with C25 hollow plastic. Photo: Huu Chanh
In recent days, the dry weather has been favorable for asphalt paving on the road surface.
In recent days, the dry weather has been favorable for asphalt paving on the road surface. Photo: Huu Chanh
The asphalt paving of the road surface is an important milestone in project implementation. The route section from Km0+000 to Km13+017.92 of Project Component 2.1 is being implemented ahead of schedule.
The asphalt paving of the road surface is an important milestone in project implementation. The route section from Km0+000 to Km13+017.92 of Project Component 2.1 is being implemented ahead of schedule. Photo: Huu Chanh

Ring Road 4 of the Capital Region has a total length of 112.8 km, passing through 3 provinces and cities, including Hanoi (57.95 km), Hung Yen (19.31 km), Bac Ninh (36.26 km).

The project has a total investment of over 85,813 billion VND divided into 7 component projects.

Construction began in June 2023 and is on schedule to complete the parallel road according to project approval in 2026, and complete the expressway in 2027.

The parallel road (urban road) Ring Road 4, the section passing through Hanoi has a length of more than 57 km, passing through 7 districts. The project's basic completion time is targeted by the investor and contractors in 2025.

HỮU CHÁNH
RELATED NEWS

Hà Nội tăng 110 tỉ đồng cho quận Hà Đông để giải phóng mặt bằng Vành đai 4

KHÁNH AN |

Với nguồn ngân sách Trung ương trong nước, Hà Nội điều chỉnh tăng 110 tỉ đồng cho quận Hà Đông để thực hiện nhiệm vụ giải phóng mặt bằng dự án thành phần 1.1 xây dựng Vành đai 4 - Vùng Thủ đô.

Hình ảnh Vành đai 4 Vùng Thủ đô sau một năm thi công

HỮU CHÁNH |

Tròn một năm từ này khởi công, hình hài "siêu dự án" Vành đai 4 Vùng Thủ đô đã trở nên rõ nét. Hiện các nhà thầu đang đẩy nhanh thi công, đưa công trình về đích đúng tiến độ.

Hà Nội đẩy nhanh tiến độ "siêu dự án" Vành đai 4

Hữu Chánh |

Ngày 25.6.2024 đánh dấu cột mốc tròn 1 năm khởi công Vành đai 4 Vùng Thủ đô. Nhờ sự vào cuộc quyết liệt của các cấp, sự đồng lòng của địa phương, dự án đến nay đã đạt được nhiều kết quả tích cực.

Tuyển Indonesia thua trận đầu tiên tại vòng loại 3 World Cup 2026

NHÓM PV |

Tối 15.10, đội tuyển Indonesia nhận thất bại 1-2 trên sân tuyển Trung Quốc tại vòng loại thứ 3 World Cup 2026.

Ra mắt Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng

Vương Trần |

Tủ sách điện tử Tổng Bí thư Nguyễn Phú Trọng là cơ sở dữ liệu quý, phục vụ nghiên cứu, học tập và vận dụng trong sự nghiệp xây dựng và bảo vệ Tổ quốc.

Quảng Ngãi khuyến cáo không ồ ạt trồng cau

VIÊN NGUYỄN |

Giá cau ở Quảng Ngãi đạt mức kỷ lục 80.000 đồng/kg. Tuy nhiên, ngành chức năng khuyến cáo nên đa dạng hóa cây trồng, trong bối cảnh giá cau rất khó lường.

Phá đường dây cờ bạc nghìn tỉ qua mạng, tạm giam 12 người

Thành Nhân |

Bến Tre - Lực lượng Công an vừa triệt xóa đường dây cờ bạc trên không gian mạng với tổng số tiền giao dịch hơn 1.800 tỉ đồng.

Nổ nồi hấp tinh dầu, 1 bé gái bị thương, 5 căn nhà ảnh hưởng

LÝ LINH |

TPHCM - Ngày 15.10, Công an huyện Bình Chánh đang điều tra vụ nổ nồi hấp tại một cơ sở sản xuất tinh dầu trên địa bàn xã Vĩnh Lộc A khiến một bé gái bị thương.

Hà Nội tăng 110 tỉ đồng cho quận Hà Đông để giải phóng mặt bằng Vành đai 4

KHÁNH AN |

Với nguồn ngân sách Trung ương trong nước, Hà Nội điều chỉnh tăng 110 tỉ đồng cho quận Hà Đông để thực hiện nhiệm vụ giải phóng mặt bằng dự án thành phần 1.1 xây dựng Vành đai 4 - Vùng Thủ đô.

Hình ảnh Vành đai 4 Vùng Thủ đô sau một năm thi công

HỮU CHÁNH |

Tròn một năm từ này khởi công, hình hài "siêu dự án" Vành đai 4 Vùng Thủ đô đã trở nên rõ nét. Hiện các nhà thầu đang đẩy nhanh thi công, đưa công trình về đích đúng tiến độ.

Hà Nội đẩy nhanh tiến độ "siêu dự án" Vành đai 4

Hữu Chánh |

Ngày 25.6.2024 đánh dấu cột mốc tròn 1 năm khởi công Vành đai 4 Vùng Thủ đô. Nhờ sự vào cuộc quyết liệt của các cấp, sự đồng lòng của địa phương, dự án đến nay đã đạt được nhiều kết quả tích cực.