Deploying many construction teams of a project worth over VND7,200 billion in Can Tho

TẠ QUANG |

Can Tho - Despite many difficulties, the project to Upgrade and Expand National Highway 91 (Km0-Km7) worth more than VND 7,200 billion is still being urgently implemented by units.

Overtime, deploying many construction teams

Currently, Can Tho City is focusing on the project of Upgrading and expanding National Highway 91 (from Km0-Km7), passing through Cai Khe, Binh Thuy and Thoi An Dong wards. This is a key project, with a total investment of about VND 7,240.5 billion.

Cong nhan thi cong tai du an. Anh: Ta Quang
Workers constructing the project to Upgrade and Expand National Highway 91 (section from Km0-Km7) in Can Tho City. Photo: Ta Quang

According to a reporter from Lao Dong Newspaper, at the starting point of the project on Cach Mang Thang 8 Street (Cai Khe Ward), many vehicles and machines have been gathered. Along the project route, a team of engineers and workers are urgently constructing items.

Anh: Ta Quang
Vehicles and machinery are gathered at the starting point of the project. Photo: Ta Quang

Mr. Le Nhut Thu - Deputy Head of Project Management Department 2, Can Tho City Traffic and Agricultural Construction Investment Project Management Board (investor) - said that from the groundbreaking date (September 22, 2025) until now, the Board has directed construction units to gather machinery and equipment and divide them into many construction teams throughout the project. However, there were some difficulties in the implementation process.

According to Mr. Thu, the project is facing difficulties due to non-continuous site clearance problems. Recently, high tides have also partly affected the progress. The project is located in the city center, with houses and a lot of traffic. Therefore, the Board and construction units, supervision consultants and construction coordination must ensure traffic safety, organize fence and signs in full.

Anh: Ta Quang
According to Mr. Le Nhut Thu, despite facing challenges in terms of site clearance, the units are still divided into many construction teams throughout the project. Photo: Ta Quang

During the construction process, the units also encountered difficulties due to the scarcity of sand and stone materials. The city's leaders and the Project Management Board have recognized this problem, so they have directed all construction units to prepare materials in advance. When the site is available, contractors will step in and divide it into many teams, working overtime even on Saturdays and Sundays, to speed up the compensation process.

People agree, hope the project will be completed soon

As a household whose house is affected by the project, Ms. Pham Thi Ngoc Anh (Binh Thuy ward) excitedly shared: "When the project was implemented, not only me but all the people on National Highway 91 were very happy and in agreement. We hope the project will be completed soon to have a spacious, airy road, convenient for transportation and economic development".

Mr. Nguyen Van Tien - Secretary, Head of Area 4, Binh Thuy Ward - said that through the work of mobilizing each household to prepare records for the counting and compensation, most people have agreed. However, some households have difficulties with land documents, so the compensation progress is still slow. Currently, people are waiting to complete the documents to receive compensation and hand over the site, everyone wants the project to be done as quickly as possible.

Anh: Ta Quang
Mr. Nguyen Van Tien - Secretary, Head of Area 4, Binh Thuy Ward - shared with reporters. Photo: Ta Quang

Chairman of Can Tho City People's Committee Truong Canh Tuyen informed that the City Party Committee and the City People's Committee have agreed to implement additional support policies to ensure the rights and stabilize the lives of users whose land, houses and works have been recovered, ensuring fairness, publicity and transparency.

"Currently, the entire political system of the locality is focusing on and making efforts to carry out land acquisition, compensation, support, and resettlement to implement the project in a timely manner; at the same time, it is necessary to ensure the rights, stabilize the lives and production of affected families, individuals, and organizations," Mr. Truong Canh Tuyen emphasized.

Anh: Ta Quang
The total number of organizations, families, and individuals affected by the project is about 1,083 cases. Photo: Ta Quang

The City Party Committee and the People's Committee of Can Tho City have directed relevant units to urgently implement and focus on prioritizing the implementation of compensation, support and resettlement for the project before December 31, 2025. Organizations, families, and individuals affected are called for good and timely coordination with the Project Compensation, Support, and Resettlement Council in measuring and counting.

The project to upgrade and expand National Highway 91 (section from Km0-Km7) was approved by the Can Tho City People's Council on December 8, 2023, with a total scale of about 7.04km and a total investment of about VND 7,240.5 billion.

The total number of organizations, families, and individuals affected by the project is about 1,083 cases. Of which, 109 cases have previously received compensation and support from the National Highway 91 Expansion Project (Ben Xe - Tra Noc Intersection).

After completion, the project will ensure safe and convenient traffic connections along National Highway 91, promote the city and neighboring areas' socio-economic development; beautify the urban area of the city center, prevent flooding caused by high tides and heavy rains; improve the lives of local residents.

TẠ QUANG
RELATED NEWS

Can Tho faces difficulties with abandoned golden land

|

A series of "golden land" areas in the center have been left vacant for many years, but Can Tho still proposed to relocate the stadium away, causing many conflicting opinions in public opinion.

Can Tho focuses on compensation, support, and resettlement for a project worth over VND 7,200 billion before December 31

|

Can Tho - City leaders directed to focus on prioritizing the implementation of compensation, support, and resettlement for the project to Upgrade and Expand National Highway 91 before December 31.

The project worth over VND7,200 billion to upgrade 7km of National Highway 91 in Can Tho officially started construction

|

Can Tho - After many "missed deadlines", up to now, the National Highway 91 Upgrade and Expansion Project (Km0 - Km7) has officially started construction along with many other projects.

Proposal to discipline the Deputy Director of Lam Dong Department of Agriculture and Environment

|

Lam Dong - Mr. Nguyen Van Duc, Deputy Director of Lam Dong Department of Agriculture and Rural Development, was proposed to consider implementing the party discipline for violating things that party members are not allowed to do.

HCMC builds 5 bridges larger than VND175,000 billion, ending ferry problems

|

Ho Chi Minh City is about to build a road and a sea overpass connecting Can Gio - Vung Tau, Can Gio bridge, Cat Lai bridge, Phu My 2 bridge, Dong Nai 2 bridge, with a total investment of about 175,000 billion VND.

Fishing boat sinks, 4 fishermen saved

|

Quang Tri - 4 fishermen in distress when their fishing boat sank at sea near Hon La Island were rescued safely.

After the severe flood, Lam Dong farmers struggle to restore dragon fruit gardens

|

Lam Dong - After the floodwaters receded, many farmers began their journey to restore their dragon fruit gardens.

Tropical depression level 8 is about to enter the East Sea, latest forecast of path

|

According to the meteorological agency, the tropical depression is forecast to maintain the intensity of level 6 gusting to level 8 in the next 24 to 48 hours.

Can Tho faces difficulties with abandoned golden land

TẠ QUANG |

A series of "golden land" areas in the center have been left vacant for many years, but Can Tho still proposed to relocate the stadium away, causing many conflicting opinions in public opinion.

Can Tho focuses on compensation, support, and resettlement for a project worth over VND 7,200 billion before December 31

TẠ QUANG |

Can Tho - City leaders directed to focus on prioritizing the implementation of compensation, support, and resettlement for the project to Upgrade and Expand National Highway 91 before December 31.

The project worth over VND7,200 billion to upgrade 7km of National Highway 91 in Can Tho officially started construction

Tạ Quang |

Can Tho - After many "missed deadlines", up to now, the National Highway 91 Upgrade and Expansion Project (Km0 - Km7) has officially started construction along with many other projects.