Hanoi's Ring Road 4 is stuck with many residential areas

HỮU CHÁNH |

Hanoi - Difficulties due to changes in mechanisms and compensation policies have caused many residential areas of the Ring Road 4 project to not be cleared to hand over to contractors for construction.

The investment project to build the Ring Road 4 of the Capital Region through Hanoi is about 58km long, passing through 7 districts including Soc Son, Me Linh, Dan Phuong, Hoai Duc, Ha Dong, Thanh Oai and Thuong Tin.

According to the report of the Hanoi Traffic Construction Investment Project Management Board, after about 2.5 years since the groundbreaking date, the project's site clearance work has reached about 99%.

The remaining land is located at the relocation locations of floating underground works and some locations of residential land and garden land scattered in districts that are facing changes in compensation mechanisms and policies.

u
A residential area in Tan Chau village (Chu Phan commune, Me Linh, Hanoi) is located in the Ring Road 4 project area. Photo: Huu Chanh

In package No. 8, the construction of the Ring Road 4 parallel road through Soc Son and Me Linh districts, while the 2 residential areas in Dai Thinh and Chu Phan communes (Me Linh district) have not yet been handed over the site for the project.

"Up to now, we still do not know when the locality will hand over the remaining site for the contractor to complete the project" - said the representative of the consortium of package No. 8.

In package No. 9, the construction of Ring Road 4 through Dan Phuong and Hoai Duc districts is currently stuck with 3 residential areas in Duc Thuong, Dong La communes (Hoai Duc) and Ha Mo commune (Dan Phuong).

"The local site clearance progress is slowing down, which could affect the contractor's construction progress, while Hanoi requires the completion of the entire parallel route in 2025" - Mr. Nguyen Hoang Hai, Commander of Package No. 9, said.

a
Many households in Khe Ngoai 2 village (Van Khe commune, Me Linh) have not been cleared. In the distance is the Red River, where the Hong Ha bridge connecting Me Linh and Dan Phuong was built. Photo: Huu Chanh

In the area within the construction area of Hong Ha bridge in Hong Ha commune (Dan Phuong district) and Van Khe (Me Linh district), many households have not yet agreed to hand over the site for the project.

Similarly, some sections of the site in package No. 10, construction of parallel roads through Ha Dong and Thanh Oai districts; package No. 11, section through Thuong Tin, has not been handed over to the contractor by the locality for construction.

The construction works are mainly residential areas, factories, underground and above-ground technical infrastructure.

s
A section of the Ring Road 4 parallel road through Hong Ha commune, Dan Phuong district has been paved with asphalt. Photo: Huu Chanh

According to the contractors' representatives, currently, the materials are fully gathered, human resources and machinery are also ready for synchronous construction along the entire route.

In case the site clearance and relocation of floating underground works are completed before March 2025, the contractor will complete the project in December 2025 in accordance with the city's direction. Otherwise, it will be force majeure because many sections within the project scope have to be treated with weak soil, the minimum relocation time must be from 6-9 months.

a
Some households in Ha Mo commune (Dan Phuong district) have not yet been cleared. Photo: Huu Chanh

During a recent visit and encouragement to officers, engineers and workers at the Ring Road 4 construction site, Chairman of the Hanoi People's Council Nguyen Ngoc Tuan requested the project investor, construction contractor, supervision consultants and all workers and laborers to closely follow the plan and progress, and strive to complete the project.

With the remaining 1% of site clearance, localities need to resolutely resolve the issue because this is a key project, the determination must be even higher. Along with progress, quality must be ensured, said Mr. Nguyen Ngoc Tuan, adding that during the implementation process, if there are any difficulties or problems, it is necessary to report and propose to the city in the spirit of urging construction wherever there is a site, not letting the project be behind schedule.

HỮU CHÁNH
RELATED NEWS

Hanoi speeds up construction of Ring Road 4, striving to complete it in 2025

|

On the occasion of the beginning of spring, Hanoi leaders visited, wished a happy new year and encouraged cadres and workers at the construction site of the Ring Road 4 parallel road project and requested units to ensure progress and complete the project this year.

The Ring Road 4 Project must not be delayed

|

Chairman of the Hanoi People's Council Nguyen Ngoc Tuan requested the project investor and the construction contractor not to let the Ring Road 4 project slow down.

Putting aside Tet holiday to focus on construction of Ring Road 4 in the Capital region

|

On the first day of 2025, workers at the construction site of Ring Road 4 were still busy working to meet the schedule of completing the parallel road this year.

All vehicles trapped on Gia Bac Pass in Lam Dong have been rescued

|

Lam Dong - After many efforts, the rescue forces have cleared the landslides on Gia Bac Pass, and many vehicles are being rescued.

Vietnam table tennis team practices with Russia

|

The players of the Vietnam Table Tennis Team were rubbed off before the 33rd SEA Games with the Russian Federation team.

Mr. Putin affirmed that Russia has no intention of returning to G8

|

President Putin affirmed that Russia has no intention of returning to the G8, and highly appreciated the strong rise of the Indian economy.

Preparing for the peak of the dry season, the Lo River begins to dry up

|

Tuyen Quang - Although not yet the peak of the dry season, many upstream areas of the Lo River have begun to dry up, exposing underground rock covers.

Another deep flooding point on National Highway 1 through Lam Dong

|

Lam Dong - Floodwaters caused deep flooding at km1700 of National Highway 1, causing traffic congestion.

Hanoi speeds up construction of Ring Road 4, striving to complete it in 2025

Hữu Chánh |

On the occasion of the beginning of spring, Hanoi leaders visited, wished a happy new year and encouraged cadres and workers at the construction site of the Ring Road 4 parallel road project and requested units to ensure progress and complete the project this year.

The Ring Road 4 Project must not be delayed

KHÁNH AN |

Chairman of the Hanoi People's Council Nguyen Ngoc Tuan requested the project investor and the construction contractor not to let the Ring Road 4 project slow down.

Putting aside Tet holiday to focus on construction of Ring Road 4 in the Capital region

KHÁNH AN - HỮU CHÁNH |

On the first day of 2025, workers at the construction site of Ring Road 4 were still busy working to meet the schedule of completing the parallel road this year.