Please extend the implementation of the bypass project in Quang Tri

HƯNG THƠ |

QUANG TRI - The Eastern bypass project of Dong Ha city is at risk of falling behind schedule, so the locality has requested an extension of the implementation time and capital disbursement.

On October 2, the People's Committee of Quang Tri province confirmed that it had sent a document to the Ministry of Planning and Investment requesting an extension of the implementation period and disbursement of the socio-economic recovery and development program assigned to the Dong Ha city eastern bypass project (from the intersection of Nguyen Hoang street to the south of Hieu river bridge). The extension period is until June 30, 2025 with a capital of 70 billion VND.

If considered and allowed to extend implementation and disbursement until June 30, 2025, the People's Committee of Quang Tri province commits to continue directing units and localities to remove difficulties to speed up project progress and disburse all the capital allowed for extension.

According to the leaders of Quang Tri province, the progress of project implementation and the plan to disburse allocated capital did not meet expectations, forcing the locality to request an extension of the implementation and disbursement time due to many objective reasons.

For example, the site clearance was implemented at the right time when the 2024 Land Law and the 2013 Land Law overlapped, so the policies were not synchronized, leading to confusion.

In addition, on December 29, 2023, the Prime Minister decided to assign capital plans to projects under the Socio-Economic Recovery and Development Program and extend the implementation period to December 31, 2024, but the capital was not provided to the province until February 6, 2024. At this time, the Law on Bidding took effect on January 1, 2024, but the Decrees, Circulars, and related documents providing detailed instructions were issued slowly, leading to difficulties in the process of organizing contractor selection, prolonging the implementation time.

In particular, the scope of the bypass project passes through an area with weak soil, so the time to process the weak soil item is from 205 to 296 days, affecting the overall progress of the project. In addition, in Quang Tri province, there is unfavorable weather at the end of the year, with continuous rain and wind, so the construction of the roadbed will be difficult in the future.

It is known that the Eastern bypass project of Dong Ha city (section from Nguyen Hoang intersection to the South of Hieu river bridge) has a total investment of 230 billion VND. Currently, the disbursement value is more than 80 billion VND, the site clearance work is over 71%.

HƯNG THƠ
RELATED NEWS

From morning to night, Hanoi is immersed in heavy pollution, AQI sometimes ranks 2nd in the world

|

The IQ Air application shows that Hanoi suffered from severe air pollution on November 30.

Public service vehicles continue to appear at the old headquarters of Market Management Team No. 4, Lang Son

|

Lang Son - Public vehicles continue to appear at the old headquarters of Market Management Team No. 4 (Huu Lung commune).

Live football U17 Vietnam vs U17 Malaysia in the U17 Asian qualifiers

|

Live football U17 Vietnam and U17 Malaysia in the U17 Asian qualifiers, taking place at 19:00 today (November 30).

The silent wave of anger after the apartment fire in Hong Kong (China)

|

More than 128 people have died, 150 people are missing and Hong Kong (China) is covered in pain after the catastrophic apartment fire.

Penalties for if the wife forces her husband to work too hard

|

How is a wife punished for forcing her husband to work too much? Lawyer Nguyen Van Hau will answer this question.

piloting public electric bicycles in Hanoi from December 1

|

Hanoi - From tomorrow (December 1), people can use public electric bicycles.

Quang Tri urges contractors to speed up progress of 400 billion VND bypass road

HƯNG THƠ |

The nearly 400 billion VND bypass road in Quang Tri province is under construction. From now until the end of the year, the weather is forecast to be unfavorable, so disbursement will be difficult.

Đường tránh lũ hơn 785 tỉ đồng, 13 năm chỉ được bố trí 80 triệu đồng

HƯNG THƠ |

Dự án đường tránh lũ ở huyện Gio Linh, tỉnh Quảng Trị có tổng mức đầu tư hơn 785 tỉ đồng, nhưng do thiếu vốn, nên 13 năm chỉ mới được bố trí 80 triệu đồng.

Chậm giải phóng mặt bằng kéo dài ở dự án đường tránh Đông TP Buôn Ma Thuột

BẢO TRUNG |

Đắk Lắk - Tại dự án đường Hồ Chí Minh đoạn tránh phía Đông TP Buôn Ma Thuột, công tác bồi thường giải phóng mặt bằng liên tục chậm trễ ảnh hưởng lớn tới tiến độ thi công. Trước tình hình trên, Bộ Giao thông Vận tải đã hối thúc UBND tỉnh có biện pháp xử lý, đảm bảo tiến độ xây lắp.