Please extend the implementation of the bypass project in Quang Tri

HƯNG THƠ |

QUANG TRI - The Eastern bypass project of Dong Ha city is at risk of falling behind schedule, so the locality has requested an extension of the implementation time and capital disbursement.

On October 2, the People's Committee of Quang Tri province confirmed that it had sent a document to the Ministry of Planning and Investment requesting an extension of the implementation period and disbursement of the socio-economic recovery and development program assigned to the Dong Ha city eastern bypass project (from the intersection of Nguyen Hoang street to the south of Hieu river bridge). The extension period is until June 30, 2025 with a capital of 70 billion VND.

If considered and allowed to extend implementation and disbursement until June 30, 2025, the People's Committee of Quang Tri province commits to continue directing units and localities to remove difficulties to speed up project progress and disburse all the capital allowed for extension.

According to the leaders of Quang Tri province, the progress of project implementation and the plan to disburse allocated capital did not meet expectations, forcing the locality to request an extension of the implementation and disbursement time due to many objective reasons.

For example, the site clearance was implemented at the right time when the 2024 Land Law and the 2013 Land Law overlapped, so the policies were not synchronized, leading to confusion.

In addition, on December 29, 2023, the Prime Minister decided to assign capital plans to projects under the Socio-Economic Recovery and Development Program and extend the implementation period to December 31, 2024, but the capital was not provided to the province until February 6, 2024. At this time, the Law on Bidding took effect on January 1, 2024, but the Decrees, Circulars, and related documents providing detailed instructions were issued slowly, leading to difficulties in the process of organizing contractor selection, prolonging the implementation time.

In particular, the scope of the bypass project passes through an area with weak soil, so the time to process the weak soil item is from 205 to 296 days, affecting the overall progress of the project. In addition, in Quang Tri province, there is unfavorable weather at the end of the year, with continuous rain and wind, so the construction of the roadbed will be difficult in the future.

It is known that the Eastern bypass project of Dong Ha city (section from Nguyen Hoang intersection to the South of Hieu river bridge) has a total investment of 230 billion VND. Currently, the disbursement value is more than 80 billion VND, the site clearance work is over 71%.

HƯNG THƠ
RELATED NEWS

US and Iran show signs conflict will continue

|

US-Iran war escalates, threatening global energy security and maritime transport.

Officially eliminate typhoon Yagi and 8 other names, finalize replacement names

|

The Asia-Pacific Regional Typhoon Committee has officially finalized the use of Typhoon Tomo instead of Yagi after the heavy damage caused by this storm.

Lang Son Hotel "out of rooms" during the festival season, people open doors to invite guests to stay

|

Lang Son - While many tourists are struggling to find accommodation during the Ky Cung - Ta Phu festival, many local people have opened their houses to guests for free.

Reasons why the 2026 World Cup budget is cut by 100 million USD

|

3 months before the start of the 2026 World Cup, FIFA issued a surprise announcement that worried fans about the grandeur of this final round.

Important notes for candidates when registering for a maximum of 15 university aspirations in 2026

|

Arranging and selecting aspirations reasonably is considered an important factor to increase the chances of admission.

How to help children overcome shock when parents divorce

|

Divorce not only changes families but can also cause psychological harm to children if there is no care and sharing from parents.

Gasoline and oil prices simultaneously sharply decreased from 10 PM on March 11

|

After the Ministry of Industry and Trade and the Ministry of Finance disbursed the price stabilization fund, gasoline and oil prices simultaneously decreased sharply from 10:00 PM on March 11.

Quang Tri urges contractors to speed up progress of 400 billion VND bypass road

HƯNG THƠ |

The nearly 400 billion VND bypass road in Quang Tri province is under construction. From now until the end of the year, the weather is forecast to be unfavorable, so disbursement will be difficult.

Đường tránh lũ hơn 785 tỉ đồng, 13 năm chỉ được bố trí 80 triệu đồng

HƯNG THƠ |

Dự án đường tránh lũ ở huyện Gio Linh, tỉnh Quảng Trị có tổng mức đầu tư hơn 785 tỉ đồng, nhưng do thiếu vốn, nên 13 năm chỉ mới được bố trí 80 triệu đồng.

Chậm giải phóng mặt bằng kéo dài ở dự án đường tránh Đông TP Buôn Ma Thuột

BẢO TRUNG |

Đắk Lắk - Tại dự án đường Hồ Chí Minh đoạn tránh phía Đông TP Buôn Ma Thuột, công tác bồi thường giải phóng mặt bằng liên tục chậm trễ ảnh hưởng lớn tới tiến độ thi công. Trước tình hình trên, Bộ Giao thông Vận tải đã hối thúc UBND tỉnh có biện pháp xử lý, đảm bảo tiến độ xây lắp.