Please extend the implementation of the bypass project in Quang Tri

HƯNG THƠ |

QUANG TRI - The Eastern bypass project of Dong Ha city is at risk of falling behind schedule, so the locality has requested an extension of the implementation time and capital disbursement.

On October 2, the People's Committee of Quang Tri province confirmed that it had sent a document to the Ministry of Planning and Investment requesting an extension of the implementation period and disbursement of the socio-economic recovery and development program assigned to the Dong Ha city eastern bypass project (from the intersection of Nguyen Hoang street to the south of Hieu river bridge). The extension period is until June 30, 2025 with a capital of 70 billion VND.

If considered and allowed to extend implementation and disbursement until June 30, 2025, the People's Committee of Quang Tri province commits to continue directing units and localities to remove difficulties to speed up project progress and disburse all the capital allowed for extension.

According to the leaders of Quang Tri province, the progress of project implementation and the plan to disburse allocated capital did not meet expectations, forcing the locality to request an extension of the implementation and disbursement time due to many objective reasons.

For example, the site clearance was implemented at the right time when the 2024 Land Law and the 2013 Land Law overlapped, so the policies were not synchronized, leading to confusion.

In addition, on December 29, 2023, the Prime Minister decided to assign capital plans to projects under the Socio-Economic Recovery and Development Program and extend the implementation period to December 31, 2024, but the capital was not provided to the province until February 6, 2024. At this time, the Law on Bidding took effect on January 1, 2024, but the Decrees, Circulars, and related documents providing detailed instructions were issued slowly, leading to difficulties in the process of organizing contractor selection, prolonging the implementation time.

In particular, the scope of the bypass project passes through an area with weak soil, so the time to process the weak soil item is from 205 to 296 days, affecting the overall progress of the project. In addition, in Quang Tri province, there is unfavorable weather at the end of the year, with continuous rain and wind, so the construction of the roadbed will be difficult in the future.

It is known that the Eastern bypass project of Dong Ha city (section from Nguyen Hoang intersection to the South of Hieu river bridge) has a total investment of 230 billion VND. Currently, the disbursement value is more than 80 billion VND, the site clearance work is over 71%.

HƯNG THƠ
RELATED NEWS

Small traders travel hundreds of kilometers to bring kumquats and apricot blossoms to the mountain town for Tet sale

|

Dak Lak - Some small traders in the coastal area have traveled hundreds of kilometers to bring ornamental plants to the mountain town to sell during Tet, hoping for a bumper crop.

Year-end feast in Bat Trang ancient village

|

In the last days of the year, the year-end feast in Bat Trang is not only a reunion meal, but also a ritual to thank ancestors, preserving the family tradition through generations.

Russian gas unexpectedly reaches top of largest supply to EU

|

Russian gas still occupies a significant position in the European Union (EU) import structure in 2025.

Green banana prices in Hanoi reach 1 million VND per bunch

|

The price of green bananas on the 28th of Tet recorded a large difference, many bunches of small, large, and beautiful fruits were offered for sale from 500,000 VND to 1 million VND per bunch.

Ca Mau Hospital proposes handling people who livestreamed about deaths 1 day after hospitalization

|

Ca Mau Hospital affirms that there were no professional errors in the 84-year-old patient's death; proposes handling people who livestream on social networks.

The first houses with national grid electricity in Dien Bien

|

Dien Bien - More than 200 households of Mong people in Sang Nhe highland commune have just been able to use the national grid electricity before the Lunar New Year.

Unique horse mascot at Pho Do Pagoda

|

Ha Tinh - This year's Binh Ngo Tet holiday, Pho Do Pagoda (Tran Phu ward) is decorated with the mascot horse with brave wings, full of impressions.

Passenger car crammed with 16 people passing through Dong Nai heavily fined

|

Dong Nai - Thai Lan Intersection Traffic Police Station made a record of handling a passenger car carrying more than 16 people, with a total fine of 72 million VND.

Quang Tri urges contractors to speed up progress of 400 billion VND bypass road

HƯNG THƠ |

The nearly 400 billion VND bypass road in Quang Tri province is under construction. From now until the end of the year, the weather is forecast to be unfavorable, so disbursement will be difficult.

Đường tránh lũ hơn 785 tỉ đồng, 13 năm chỉ được bố trí 80 triệu đồng

HƯNG THƠ |

Dự án đường tránh lũ ở huyện Gio Linh, tỉnh Quảng Trị có tổng mức đầu tư hơn 785 tỉ đồng, nhưng do thiếu vốn, nên 13 năm chỉ mới được bố trí 80 triệu đồng.

Chậm giải phóng mặt bằng kéo dài ở dự án đường tránh Đông TP Buôn Ma Thuột

BẢO TRUNG |

Đắk Lắk - Tại dự án đường Hồ Chí Minh đoạn tránh phía Đông TP Buôn Ma Thuột, công tác bồi thường giải phóng mặt bằng liên tục chậm trễ ảnh hưởng lớn tới tiến độ thi công. Trước tình hình trên, Bộ Giao thông Vận tải đã hối thúc UBND tỉnh có biện pháp xử lý, đảm bảo tiến độ xây lắp.