Please extend the implementation of the bypass project in Quang Tri

HƯNG THƠ |

QUANG TRI - The Eastern bypass project of Dong Ha city is at risk of falling behind schedule, so the locality has requested an extension of the implementation time and capital disbursement.

On October 2, the People's Committee of Quang Tri province confirmed that it had sent a document to the Ministry of Planning and Investment requesting an extension of the implementation period and disbursement of the socio-economic recovery and development program assigned to the Dong Ha city eastern bypass project (from the intersection of Nguyen Hoang street to the south of Hieu river bridge). The extension period is until June 30, 2025 with a capital of 70 billion VND.

If considered and allowed to extend implementation and disbursement until June 30, 2025, the People's Committee of Quang Tri province commits to continue directing units and localities to remove difficulties to speed up project progress and disburse all the capital allowed for extension.

According to the leaders of Quang Tri province, the progress of project implementation and the plan to disburse allocated capital did not meet expectations, forcing the locality to request an extension of the implementation and disbursement time due to many objective reasons.

For example, the site clearance was implemented at the right time when the 2024 Land Law and the 2013 Land Law overlapped, so the policies were not synchronized, leading to confusion.

In addition, on December 29, 2023, the Prime Minister decided to assign capital plans to projects under the Socio-Economic Recovery and Development Program and extend the implementation period to December 31, 2024, but the capital was not provided to the province until February 6, 2024. At this time, the Law on Bidding took effect on January 1, 2024, but the Decrees, Circulars, and related documents providing detailed instructions were issued slowly, leading to difficulties in the process of organizing contractor selection, prolonging the implementation time.

In particular, the scope of the bypass project passes through an area with weak soil, so the time to process the weak soil item is from 205 to 296 days, affecting the overall progress of the project. In addition, in Quang Tri province, there is unfavorable weather at the end of the year, with continuous rain and wind, so the construction of the roadbed will be difficult in the future.

It is known that the Eastern bypass project of Dong Ha city (section from Nguyen Hoang intersection to the South of Hieu river bridge) has a total investment of 230 billion VND. Currently, the disbursement value is more than 80 billion VND, the site clearance work is over 71%.

HƯNG THƠ
RELATED NEWS

U22 Indonesia stops in the group stage of the 33rd SEA Games

|

On the evening of December 12, U22 Indonesia defeated U22 Myanmar 3-1 but still could not win a place in the semi-finals of the 33rd SEA Games men's football tournament.

Strong cold air forecast causing bad weather

|

Strong cold air causes unfavorable weather in many sea areas; The Gulf of Tonkin has northeast winds of level 7, sometimes level 8, gusting to level 9 from noon and afternoon of December 13.

The secret to helping Vietnamese karate fighters overcome Thailand

|

Boxer Khuat Hai Nam defeated host Thailand to win the gold medal for Vietnamese karate at the 33rd SEA Games.

Kim Chung CT3 social housing application is paid in large numbers due to lack of salary table photos for the whole company

|

Hanoi - On December 12, many people who came to submit documents at the CT3 Kim Chung social housing project had their documents returned due to the lack of photocopy of the salary table of the whole company.

Lieutenant General Le Van Huong holds the position of Deputy Chief of the General Staff of the People's Army

|

Lieutenant General Le Van Huong - Director of the Department of Military Affairs, General Staff was appointed to the position of Deputy Chief of the General Staff of the Vietnam People's Army.

Strong cold air is about to arrive, the North will have heavy rain, severe cold, some places below 5 degrees Celsius

|

Due to the impact of strong cold air, the mountainous and midland areas of the North will be very cold, with some mountainous areas experiencing severe cold with temperatures below 5 degrees Celsius.

Traffic police officers tell the moment the violator pushed him into the front of the truck

|

Hanoi - The subject was suddenly pushed from behind, fortunately the traffic police officers promptly reacted and avoided the danger.

SEA Games 33 Medal Schedule on December 12

|

Updated total medal table of the 33rd SEA Games on December 13.

Quang Tri urges contractors to speed up progress of 400 billion VND bypass road

HƯNG THƠ |

The nearly 400 billion VND bypass road in Quang Tri province is under construction. From now until the end of the year, the weather is forecast to be unfavorable, so disbursement will be difficult.

Đường tránh lũ hơn 785 tỉ đồng, 13 năm chỉ được bố trí 80 triệu đồng

HƯNG THƠ |

Dự án đường tránh lũ ở huyện Gio Linh, tỉnh Quảng Trị có tổng mức đầu tư hơn 785 tỉ đồng, nhưng do thiếu vốn, nên 13 năm chỉ mới được bố trí 80 triệu đồng.

Chậm giải phóng mặt bằng kéo dài ở dự án đường tránh Đông TP Buôn Ma Thuột

BẢO TRUNG |

Đắk Lắk - Tại dự án đường Hồ Chí Minh đoạn tránh phía Đông TP Buôn Ma Thuột, công tác bồi thường giải phóng mặt bằng liên tục chậm trễ ảnh hưởng lớn tới tiến độ thi công. Trước tình hình trên, Bộ Giao thông Vận tải đã hối thúc UBND tỉnh có biện pháp xử lý, đảm bảo tiến độ xây lắp.