Dak Nong speeds up disbursement, removes obstacles for public investment projects

BẢO LÂM |

Dak Nong is accelerating disbursement, removing obstacles for public investment projects, especially site clearance.

On May 15, Chairman of Dak Nong Provincial People's Committee Ho Van Muoi chaired a meeting on the disbursement of projects invested by the Provincial Investment and Construction Project Management Board (QLDA).

As of May 14, 2025, the Dak Nong Provincial Project Management Board has disbursed nearly 152 billion VND out of a total of 1,829 billion VND of the capital plan for 2025, reaching 8.3%.

According to information from the Project Management Board, the biggest problem in disbursing public investment capital is still site clearance (GPMB).

The time to carry out procedures for granting land exploitation and completing the conditions for the mine for exploitation takes a lot of time, leading to slow progress of the project.

Some contractors are also slow in mobilizing labor, materials and equipment, not meeting the committed plan.

The Provincial General Hospital Upgrade Project was allocated 270 billion VND in 2025, but to date, only nearly 19 billion VND has been disbursed, reaching 6.7% of the plan.

Director of the Project Management Board - Mr. Ha Sy Son - informed that, according to the contractor's commitment, in the next 4 months, 109 billion VND will be disbursed. However, the actual acceptance at the site showed that the project only disbursed 73 billion VND, 36 billion VND behind schedule.

Mr. Son also proposed to extend the project completion schedule from August 2025 to December 31, 2025.

Mr. Le Bao Anh - General Director of Construction Company No. 1 - Joint Stock Company contractor of the Provincial General Hospital Upgrade Project - accepted responsibility for the progress but also mentioned the difficulties in importing equipment globally.

By July 15, 2025, all equipment and machinery will return to the scene. At that time, we will speed up the construction, Mr. Bao Anh pledged.

Chu tich UBND tinh Dak Nong yeu cau day nhanh tien do, giai ngan von dau tu. Anh: Nguyen Luong
The Chairman of Dak Nong Provincial People's Committee requested to speed up the progress and disbursement of investment capital. Photo: Nguyen Luong

Mr. Ho Van Muoi emphasized that the biggest problem at present is site clearance. If the site clearance is not resolved before July 1, 2025, construction will face difficulties and complications.

Mr. Muoi requested that units quickly clear land at projects with problems, and emphasized the importance of consensus from the people in this process.

The Standing Vice Chairman of Dak Nong Provincial People's Committee - Mr. Le Trong Yen - emphasized that by June 30, 2025, projects under the authority of the district must complete site clearance.

He requested localities and investors to monitor and take responsibility to effectively implement this work. "To speed up progress, it is necessary to change methods and coordination methods. Compensation for crops and facilities for people is very important, said Mr. Yen.

Concluding the meeting, Chairman of Dak Nong Provincial People's Committee Ho Van Muoi emphasized that there is not much time left and required everyone to work seriously.

"We have to work day and night. Contractors need to work overtime and increase shifts to speed up the progress, said Mr. Muoi.

The Chairman of Dak Nong Provincial People's Committee also requested that the quality of the project should be given top priority, and that progress cannot be done at a minimum.

BẢO LÂM
TIN LIÊN QUAN

Low public investment disbursement rate, Chairman of Can Tho criticizes heads of 20 units

|

Can Tho - The Chairman of the city acknowledged that the public investment disbursement rate is slow to progress; the sense of responsibility of some Department Directors, Heads... is not high.

List of ministries, branches and localities with low public investment disbursement rates

|

Ministries, branches and localities with a disbursement rate of public investment capital lower than the national average need to speed up the implementation of investment and construction procedures in the coming time.

Many investors in Dak Nong disburse capital at 0 VND

|

Dak Nong is facing many challenges in disbursing public investment capital. Currently, there are 6 investors recording 0 VND disbursement.

Landslide on National Highway 15D, road to La Lay International Border Gate cut off

|

Quang Tri - The landslide occurred while the construction unit was expanding the curve on National Highway 15D to the La Lay international border gate, causing traffic disruption.

Russian general arrested on corruption charge

|

Russia arrested Senior Lieutenant General Viktor Strigunov, former Deputy Commander of the National Guard, on serious corruption charges.

Accidents lurk but many people still ignore them, determined to ride motorbikes onto the highway

|

Hanoi - Just because they want to get to work quickly, many people still ignore the danger of riding motorbikes on Thang Long Avenue Expressway.

Low pressure forecast to join low pressure near the East Sea right after storm today

|

2 low pressure areas near the East Sea are forecast to form right after Typhoon Today, the fourth typhoon this year in China.

Vietnam Airlines plane has just had to make emergency landing in India to rescue passengers

|

Informing Lao Dong Newspaper on the evening of July 7, a representative of Vietnam Airlines said that the airline had just had to make an emergency landing in India to rescue passengers.

Low public investment disbursement rate, Chairman of Can Tho criticizes heads of 20 units

Hàn Lâm |

Can Tho - The Chairman of the city acknowledged that the public investment disbursement rate is slow to progress; the sense of responsibility of some Department Directors, Heads... is not high.

List of ministries, branches and localities with low public investment disbursement rates

ANH HUY |

Ministries, branches and localities with a disbursement rate of public investment capital lower than the national average need to speed up the implementation of investment and construction procedures in the coming time.

Many investors in Dak Nong disburse capital at 0 VND

BẢO LÂM |

Dak Nong is facing many challenges in disbursing public investment capital. Currently, there are 6 investors recording 0 VND disbursement.