Ha Tinh reports to the Ministry of Public Security on solar power projects

TRẦN TUẤN |

Ha Tinh - Mr. Duong Thanh Hoa - Deputy Director of the Department of Industry and Trade said that the department has just reported to the Ministry of Public Security about solar power projects in the area.

Accordingly, in the period of 2016 - 2020, in Ha Tinh province, there are 3 solar power plant projects approved to supplement the power development plan. However, up to now, only 2 investment and construction projects have been completed and put into operation. These are the Cam Hoa Solar Power Plant Project (now Yen Hoa commune, Cam Xuyen district) with a capacity of 49MW in commercial operation since June 2019 and the Cam Hung Solar Power Plant Project (Cam Xuyen district) with a capacity of 29MW in commercial operation since December 2020.

Hien Ha Tinh moi co 2 du an dien mat troi di vao hoat dong. Anh: Tran Tuan.
Currently, Ha Tinh has only 2 solar power projects in operation. Photo: Tran Tuan

The Son Quang Solar Power Plant Project (now Quang Diem Commune, Huong Son District) with a capacity of 29MW was approved by the Ministry of Industry and Trade to adjust and supplement the Ha Tinh Province Power Development Plan for the period 2016 - 2025, although it has not yet been invested in construction until 2035.

The reason is that the investor has not completed the procedures for agreeing to connect with the management and operation unit; did not transfer funds for the locality to pay for site clearance to implement the project.

Currently, this project is not included in the planning list, the approved power plan VIII implementation plan.

Vung dat de thuc hien Du an dien mat troi Son Quang (nay la xa Quang Diem) nhung nhieu nam qua khong trien khai nen nong dan van canh tac  tai day. Anh: Tran Tuan.
The land to implement the Son Quang Solar Power Project (now Quang Diem commune) has not been implemented for many years, so farmers are still farming here. Photo: Tran Tuan

Also according to the report of the Department of Industry and Trade, in the past, Ha Tinh did not submit for approval additional solar power projects without a basis or legal basis for planning.

In Ha Tinh, there are also no solar power projects with shortcomings or violations related to land procedures such as: Starting a project without being allocated/leased land by competent authorities; building a project on protective natural forest land and protective plantation forests; the project is not suitable for the national mineral reserve area; not yet changing the land use purpose...

The acceptance of construction works for the Cam Hoa Solar Power Project and the Cam Hung Solar Power Project has been fully implemented in accordance with the provisions of law.

Regarding the rooftop solar power project (built on agricultural and forestry land with a large capacity under the farm model), the review process shows that agricultural farm projects are suitable for land for farming and farming.

The rooftop solar power systems have completed procedures for construction safety, fire prevention and fighting safety according to regulations.

TRẦN TUẤN
RELATED NEWS

Khanh Hoa proposes to connect a series of solar power projects

|

Khanh Hoa - There are still some solar power projects being temporarily connected, so the locality proposed that the Central Government agree to switch to the main connection option.

The woman suspected of stealing was exonerated, accepting an apology from Aeon Mall

|

Late on June 9, Aeon Mall issued a press release related to the incident that occurred at Aeon Mall Long Bien Shopping Center on June 7.

National Assembly Chairman: Cities are important actors of the ASEAN Community

|

National Assembly Chairman Tran Thanh Man highly appreciated the initiative to organize the ASEAN City Leaders' Meeting.

Elderly and weak people are no longer burdened with procedures to receive pensions and social insurance

|

Hanoi - Many elderly people are supported by officials of the Public Administration Service Center to their homes to certify their authorization to receive pensions.

11m high tsunami forces hundreds of New Zealanders to evacuate

|

Hundreds of coastal residents in New Zealand's capital Wellington had to evacuate when tsunamis up to 11m high hit the coastal area on June 9.

Ensuring electricity for double-digit economic growth target in the coming period

|

Lao Dong Newspaper respectfully introduces the presentation of Mr. Trinh Quoc Vu - Deputy Director of the Electricity Department, Ministry of Industry and Trade within the framework of the Workshop "Energy Transition - Motivation for Two-digit Growth Goals" co-organized by Lao Dong Newspaper and the Ministry of Industry and Trade on June 9, 2026.

Bộ Công an yêu cầu cung cấp thông tin dự án điện mặt trời ở Quảng Bình

CÔNG SÁNG |

Quảng Bình - Bộ Công an yêu cầu tỉnh cung cấp hồ sơ các dự án điện mặt trời trên địa bàn để phục vụ công tác xác minh.

Hoàn thuế sai trăm tỉ đồng cho Nhà máy điện mặt trời Lộc Ninh 3

Việt Dũng |

Trong vụ án liên quan cựu Thứ trưởng Bộ Công Thương, nhóm cựu cán bộ thuế tỉnh Bình Phước có những sai phạm ở Dự án Nhà máy điện mặt trời Lộc Ninh 3.

Khanh Hoa proposes to connect a series of solar power projects

Hữu Long |