Ha Tinh reports to the Ministry of Public Security on solar power projects

TRẦN TUẤN |

Ha Tinh - Mr. Duong Thanh Hoa - Deputy Director of the Department of Industry and Trade said that the department has just reported to the Ministry of Public Security about solar power projects in the area.

Accordingly, in the period of 2016 - 2020, in Ha Tinh province, there are 3 solar power plant projects approved to supplement the power development plan. However, up to now, only 2 investment and construction projects have been completed and put into operation. These are the Cam Hoa Solar Power Plant Project (now Yen Hoa commune, Cam Xuyen district) with a capacity of 49MW in commercial operation since June 2019 and the Cam Hung Solar Power Plant Project (Cam Xuyen district) with a capacity of 29MW in commercial operation since December 2020.

Hien Ha Tinh moi co 2 du an dien mat troi di vao hoat dong. Anh: Tran Tuan.
Currently, Ha Tinh has only 2 solar power projects in operation. Photo: Tran Tuan

The Son Quang Solar Power Plant Project (now Quang Diem Commune, Huong Son District) with a capacity of 29MW was approved by the Ministry of Industry and Trade to adjust and supplement the Ha Tinh Province Power Development Plan for the period 2016 - 2025, although it has not yet been invested in construction until 2035.

The reason is that the investor has not completed the procedures for agreeing to connect with the management and operation unit; did not transfer funds for the locality to pay for site clearance to implement the project.

Currently, this project is not included in the planning list, the approved power plan VIII implementation plan.

Vung dat de thuc hien Du an dien mat troi Son Quang (nay la xa Quang Diem) nhung nhieu nam qua khong trien khai nen nong dan van canh tac  tai day. Anh: Tran Tuan.
The land to implement the Son Quang Solar Power Project (now Quang Diem commune) has not been implemented for many years, so farmers are still farming here. Photo: Tran Tuan

Also according to the report of the Department of Industry and Trade, in the past, Ha Tinh did not submit for approval additional solar power projects without a basis or legal basis for planning.

In Ha Tinh, there are also no solar power projects with shortcomings or violations related to land procedures such as: Starting a project without being allocated/leased land by competent authorities; building a project on protective natural forest land and protective plantation forests; the project is not suitable for the national mineral reserve area; not yet changing the land use purpose...

The acceptance of construction works for the Cam Hoa Solar Power Project and the Cam Hung Solar Power Project has been fully implemented in accordance with the provisions of law.

Regarding the rooftop solar power project (built on agricultural and forestry land with a large capacity under the farm model), the review process shows that agricultural farm projects are suitable for land for farming and farming.

The rooftop solar power systems have completed procedures for construction safety, fire prevention and fighting safety according to regulations.

TRẦN TUẤN
RELATED NEWS

Khanh Hoa proposes to connect a series of solar power projects

|

Khanh Hoa - There are still some solar power projects being temporarily connected, so the locality proposed that the Central Government agree to switch to the main connection option.

Proposal for Hanoi to decide on the organizational structure, job position, and income regime

|

Hanoi is proposed to be proactive in deciding on the organization of the government apparatus; job positions, public service regimes, income regimes, and bonuses.

Scene of the fire at a wood furniture business facility in Ho Chi Minh City

|

Ho Chi Minh City - A fire broke out from a level 4 house used as a wood furniture business location on Do Xuan Hop street, Phuoc Long ward, Ho Chi Minh City.

Police investigate tourist suspected of dropping diamond ring at resort in Dak Lak

|

Dak Lak - The police agency is investigating and resolving the case of a tourist asking for help when he unfortunately dropped a diamond ring.

Large tree falls and hits person in Hanoi flower garden

|

Hanoi - A tree in Ly Tu Trong flower garden (Tay Ho ward) suddenly broke and fell, hitting people.

Thu Trang speaks out about information of discord with the "Mui Pho" film crew

|

Recently, there has been information that Thu Trang did not participate in promoting the movie "Mui pho", even disagreed with the cast in the movie.

Bộ Công an yêu cầu cung cấp thông tin dự án điện mặt trời ở Quảng Bình

CÔNG SÁNG |

Quảng Bình - Bộ Công an yêu cầu tỉnh cung cấp hồ sơ các dự án điện mặt trời trên địa bàn để phục vụ công tác xác minh.

Hoàn thuế sai trăm tỉ đồng cho Nhà máy điện mặt trời Lộc Ninh 3

Việt Dũng |

Trong vụ án liên quan cựu Thứ trưởng Bộ Công Thương, nhóm cựu cán bộ thuế tỉnh Bình Phước có những sai phạm ở Dự án Nhà máy điện mặt trời Lộc Ninh 3.

Khanh Hoa proposes to connect a series of solar power projects

Hữu Long |

Khanh Hoa - There are still some solar power projects being temporarily connected, so the locality proposed that the Central Government agree to switch to the main connection option.