Lam Dong delays completion of 400 billion VND traffic project

HOÀI THANH |

Lam Dong - The Cam Ly - Phuoc Thanh road construction project with a total investment of 400 billion VND has been approved to delay the completion and putting into use time.

On October 5, Mr. Tran Hong Thai - Chairman of Lam Dong Provincial People's Committee signed a decision agreeing to adjust the implementation time of the Cam Ly - Phuoc Thanh road construction project from 2021 - 2024 to 2021 - 2025.

Lam Dong Provincial People's Committee directed the Lam Dong Provincial Traffic Project Management Board to coordinate with relevant units under Da Lat City People's Committee and Lac Duong District People's Committee to speed up the progress of site clearance and urge the acceleration of project implementation progress.

The Cam Ly - Phuoc Thanh road construction project was approved by the Lam Dong Provincial People's Committee with a total investment of 400 billion VND from the central budget. The project is invested by the Lam Dong Provincial Traffic Project Management Board.

The construction package was won by the consortium of Investment and Construction Joint Stock Company 515 - Hung Nguyen Company Limited - Duy Ha Gold Company Limited - Construction and Investment Joint Stock Company 18.

Currently, contractors are implementing the construction of items such as roadbed, drainage ditches, cross-culverts, retaining walls and asphalt pavement. The value of implemented output is estimated at 119.5/213.14 billion VND, reaching 56% of the contract value.

Regarding disbursement, the capital allocated in 2023 is more than 108 billion VND. Currently, the investor has disbursed 100% of the capital plan for 2023. The capital allocated in 2024 is 104 billion VND. Currently, the investor has disbursed more than 40 billion VND, reaching 38.84% of the capital plan for 2024.

Previously, Lao Dong Newspaper published an article "400 billion VND traffic project in Lam Dong asks to delay progress".

The article reflects that the investor of Cam Ly - Phuoc Thanh road with a total investment of 400 billion VND has just requested a policy to adjust the project completion time after 2024.

HOÀI THANH
RELATED NEWS

Gold prices rebound, people line up from 6 am to buy

|

On January 5, domestic gold prices "turned around" and jumped up. The store limited the number of purchases and announced that it would stop receiving customers due to overload.

Announcing the schedule for paying pensions, social insurance allowances, and Tet gifts for the 2026 Lunar New Year

|

Hanoi City Social Insurance has just announced the schedule for paying pensions, social insurance allowances and guidance on spending Tet gifts for the Binh Ngo Lunar New Year 2026.

House catches fire at night in Dong Thap, killing 2 young children

|

Dong Thap - A fire at a house in My Phuoc Tay ward (Dong Thap province) killed 2 young children.

Rights when participating in electronic labor contracts of workers

|

The Government has just issued Decree 337/2025/ND-CP (effective from January 1, 2026) Regulating electronic labor contracts.

Passenger car overturns on National Highway 37 through Son La, 11 people injured

|

Son La - While traveling on National Highway 37, a passenger car suddenly overturned, injuring 11 people.

Bar owner speaks out about employee threatening to beat tourists at Nha Trang beach

|

Khanh Hoa - The bar owner has just spoken out about the incident of an employee threatening to beat a foreign tourist in the Nha Trang beach park area.

Medical staff in Nghe An have not received COVID-19 epidemic prevention allowance

|

Nghe An - Doctors and medical staff of Nghi Loc General Hospital propose not to receive epidemic prevention allowances according to Decree 05.

Beware of the 4 billion tree planting project in Ha Tinh "drying up" with the trees

Lê Thanh Phong |

A series of trees belonging to the 4 billion VND tree planting project in Cam Hung commune, Cam Xuyen district, Ha Tinh died.

Kon Tum will revoke power projects with slow investment progress

THANH TUẤN |

Kon Tum - This locality requires investors in power projects to urgently implement the progress approved in the investment policy.

Project delayed 3 times under comprehensive inspection in Quang Nam

Lam Duy |

The project of Viesky General Trading and Service Company Limited was comprehensively inspected in Quang Nam and requested to adjust the progress 3 times.

Dự án giao thông 400 tỉ đồng ở Lâm Đồng xin lùi tiến độ

PHAN TUẤN - PHẠM QUANG |

Lâm Đồng - Chủ đầu tư đường Cam Ly - Phước Thành có tổng mức đầu tư 400 tỉ đồng vừa xin chủ trương điều chỉnh thời gian hoàn thành dự án sau năm 2024.