Lam Dong delays completion of 400 billion VND traffic project

HOÀI THANH |

Lam Dong - The Cam Ly - Phuoc Thanh road construction project with a total investment of 400 billion VND has been approved to delay the completion and putting into use time.

On October 5, Mr. Tran Hong Thai - Chairman of Lam Dong Provincial People's Committee signed a decision agreeing to adjust the implementation time of the Cam Ly - Phuoc Thanh road construction project from 2021 - 2024 to 2021 - 2025.

Lam Dong Provincial People's Committee directed the Lam Dong Provincial Traffic Project Management Board to coordinate with relevant units under Da Lat City People's Committee and Lac Duong District People's Committee to speed up the progress of site clearance and urge the acceleration of project implementation progress.

The Cam Ly - Phuoc Thanh road construction project was approved by the Lam Dong Provincial People's Committee with a total investment of 400 billion VND from the central budget. The project is invested by the Lam Dong Provincial Traffic Project Management Board.

The construction package was won by the consortium of Investment and Construction Joint Stock Company 515 - Hung Nguyen Company Limited - Duy Ha Gold Company Limited - Construction and Investment Joint Stock Company 18.

Currently, contractors are implementing the construction of items such as roadbed, drainage ditches, cross-culverts, retaining walls and asphalt pavement. The value of implemented output is estimated at 119.5/213.14 billion VND, reaching 56% of the contract value.

Regarding disbursement, the capital allocated in 2023 is more than 108 billion VND. Currently, the investor has disbursed 100% of the capital plan for 2023. The capital allocated in 2024 is 104 billion VND. Currently, the investor has disbursed more than 40 billion VND, reaching 38.84% of the capital plan for 2024.

Previously, Lao Dong Newspaper published an article "400 billion VND traffic project in Lam Dong asks to delay progress".

The article reflects that the investor of Cam Ly - Phuoc Thanh road with a total investment of 400 billion VND has just requested a policy to adjust the project completion time after 2024.

HOÀI THANH
RELATED NEWS

Disburse about VND2,400 billion to compensate for the construction site of Ho Chi Minh City Ring Road 4 through the old Binh Duong

|

HCMC - The units have disbursed compensation of about VND 2,400 billion for site clearance to build the Ho Chi Minh City Ring Road 4 project, the section passing through the old Binh Duong area.

Forecast of the number of storms and tropical depressions at risk of appearing

|

It is forecasted that in December, there will be about 1-2 storms or tropical depressions in the East Sea and the possibility of affecting the mainland cannot be ruled out.

Hundreds of households in Lam Dong sighed because of coffee drying kilns surrounding residential areas

|

Lam Dong - Dozens of coffee drying kilns operate continuously day and night, emitting smoke, dust and noise, affecting the lives of hundreds of households.

Sleeper bus crashed onto the sidewalk, injuring and killing 3 people in Dong Thap

|

Dong Thap - A sleeper bus was traveling on National Highway 80 through Lap Vo commune when it crashed into the left side, causing 3 casualties.

Sharing of the victim who escaped the restaurant fire that killed 4 people in Ho Chi Minh City

|

HCMC - Currently, the health of the two victims in the restaurant fire has passed the critical stage and is being monitored at Gia Dinh People's Hospital.

Temporarily fixing a 40m long crack on National Highway 1 through Deo Ngang, waiting for experts to handle

|

Quang Tri - Road management forces are temporarily repairing and checking the current status of a large crack appearing on National Highway 1, Deo Ngang section.

Outstanding salary policy takes effect from January 1, 2026

|

The outstanding salary policy effective from January 1, 2026 has received much attention from cadres, civil servants, public employees and workers.

Beware of the 4 billion tree planting project in Ha Tinh "drying up" with the trees

Lê Thanh Phong |

A series of trees belonging to the 4 billion VND tree planting project in Cam Hung commune, Cam Xuyen district, Ha Tinh died.

Kon Tum will revoke power projects with slow investment progress

THANH TUẤN |

Kon Tum - This locality requires investors in power projects to urgently implement the progress approved in the investment policy.

Project delayed 3 times under comprehensive inspection in Quang Nam

Lam Duy |

The project of Viesky General Trading and Service Company Limited was comprehensively inspected in Quang Nam and requested to adjust the progress 3 times.

Dự án giao thông 400 tỉ đồng ở Lâm Đồng xin lùi tiến độ

PHAN TUẤN - PHẠM QUANG |

Lâm Đồng - Chủ đầu tư đường Cam Ly - Phước Thành có tổng mức đầu tư 400 tỉ đồng vừa xin chủ trương điều chỉnh thời gian hoàn thành dự án sau năm 2024.