Lam Dong delays completion of 400 billion VND traffic project

HOÀI THANH |

Lam Dong - The Cam Ly - Phuoc Thanh road construction project with a total investment of 400 billion VND has been approved to delay the completion and putting into use time.

On October 5, Mr. Tran Hong Thai - Chairman of Lam Dong Provincial People's Committee signed a decision agreeing to adjust the implementation time of the Cam Ly - Phuoc Thanh road construction project from 2021 - 2024 to 2021 - 2025.

Lam Dong Provincial People's Committee directed the Lam Dong Provincial Traffic Project Management Board to coordinate with relevant units under Da Lat City People's Committee and Lac Duong District People's Committee to speed up the progress of site clearance and urge the acceleration of project implementation progress.

The Cam Ly - Phuoc Thanh road construction project was approved by the Lam Dong Provincial People's Committee with a total investment of 400 billion VND from the central budget. The project is invested by the Lam Dong Provincial Traffic Project Management Board.

The construction package was won by the consortium of Investment and Construction Joint Stock Company 515 - Hung Nguyen Company Limited - Duy Ha Gold Company Limited - Construction and Investment Joint Stock Company 18.

Currently, contractors are implementing the construction of items such as roadbed, drainage ditches, cross-culverts, retaining walls and asphalt pavement. The value of implemented output is estimated at 119.5/213.14 billion VND, reaching 56% of the contract value.

Regarding disbursement, the capital allocated in 2023 is more than 108 billion VND. Currently, the investor has disbursed 100% of the capital plan for 2023. The capital allocated in 2024 is 104 billion VND. Currently, the investor has disbursed more than 40 billion VND, reaching 38.84% of the capital plan for 2024.

Previously, Lao Dong Newspaper published an article "400 billion VND traffic project in Lam Dong asks to delay progress".

The article reflects that the investor of Cam Ly - Phuoc Thanh road with a total investment of 400 billion VND has just requested a policy to adjust the project completion time after 2024.

HOÀI THANH
RELATED NEWS

63 people in An Giang suspected of poisoning after eating cake

|

An Giang - Functional forces are investigating and verifying a suspected case of collective food poisoning when eating cakes from a facility in Rach Gia ward.

Special polling stations in Hanoi are ready to welcome a big festival

|

Kim Lien communal house (Hanoi) - one of the "Thang Long Tu Tran" districts selected as a voting location for the election of National Assembly Deputies of the 16th term and People's Council Deputies at all levels.

Polling stations in Van Mieu - Quoc Tu Giam ward are ready for the country festival

|

Hanoi - Voting stations in Van Mieu - Quoc Tu Giam ward have completed preparations, decorated with colorful flags and flowers, ready for election day.

Images of the most overloaded road in Ho Chi Minh City waiting for expansion

|

Nguyen Tat Thanh Street is one of the most congested roads in Ho Chi Minh City, about to expand to at least 8 lanes, associated with the renovation of Nha Rong - Khanh Hoi area.

Mobilizing financial resources effectively for high and sustainable growth

|

Credit is the "blood vessel" of the financial market. The pressure to unlock capital is increasing sharply, requiring safe, directional, and effective cash flow.

Beware of the 4 billion tree planting project in Ha Tinh "drying up" with the trees

Lê Thanh Phong |

A series of trees belonging to the 4 billion VND tree planting project in Cam Hung commune, Cam Xuyen district, Ha Tinh died.

Kon Tum will revoke power projects with slow investment progress

THANH TUẤN |

Kon Tum - This locality requires investors in power projects to urgently implement the progress approved in the investment policy.

Project delayed 3 times under comprehensive inspection in Quang Nam

Lam Duy |

The project of Viesky General Trading and Service Company Limited was comprehensively inspected in Quang Nam and requested to adjust the progress 3 times.

Dự án giao thông 400 tỉ đồng ở Lâm Đồng xin lùi tiến độ

PHAN TUẤN - PHẠM QUANG |

Lâm Đồng - Chủ đầu tư đường Cam Ly - Phước Thành có tổng mức đầu tư 400 tỉ đồng vừa xin chủ trương điều chỉnh thời gian hoàn thành dự án sau năm 2024.