Reasons why 5 wind power projects are required to terminate investment policies

HƯNG THƠ |

Quang Tri - The province directed relevant units to carry out procedures to terminate investment policies for 5 wind power projects.

On April 25, Mr. Ha Sy Dong - Acting Chairman of the People's Committee of Quang Tri province confirmed that he had directed the Department of Finance and the Management Board of Quang Tri Economic Zone to carry out procedures to terminate the investment policy in accordance with the provisions of law for 5 wind power projects.

5 wind power projects proposed to terminate investment policies include Quang Tri 1 TNC project (50MW), Quang Tri 2 TNC (50MW), Huong Linh 5 (30MW), Huong Hiep 2 (30MW) and Huong Hiep 3 (30MW).

The above wind power projects have been granted investment policy decisions by the Provincial People's Committee, and have been approved by investors since 2021 and have adjusted investment policies. In particular, investors proposed to extend the progress and the project implementation progress is now overdue. For example, the Huong Linh 5 and Huong Hiep 2 wind power plant projects, Huong Hiep 3 projects have exceeded their investment period by more than 36 months.

In particular, all 5 projects mentioned above have not yet deposited investment guarantee funds.

In Quang Tri province, there are currently 20 wind power projects put into operation for power generation and commercial operation with a total capacity of 742.2MW. In addition, 1 project has completed construction and is completing related procedures to put into commercial operation (Huong Linh 4 - 30MW) and 10 projects with a total capacity of 394MW have been approved by competent authorities for investment policy and are under investment implementation.

Of the 10 projects under investment, 6 wind power plant projects are behind schedule, including: LIG Huong Hoa 2; TNC Quang Tri 1; TNC Quang Tri 2; Huong Linh2; Huong Hiep 2; Huong Hiep 3.

In addition to 5 projects that are behind schedule and are proposed to carry out procedures to terminate investment policies, LIG Huong Hoa 2 Wind Power Plant is required to report specific roadmaps and plans for departments to grasp the implementation progress, have clear commitments with the province to have a basis for guidance and handling difficulties and problems.

According to the Department of Industry and Trade of Quang Tri Province, the current planning of VIII electricity allocates wind power to accumulated province by 2030 of 1,800MW and the VIII power planning adjustment of the capacity increased by 560MW. In order to ensure the completion of the planning work for wind power sources until 2030, Quang Tri province will put into operation to ensure the allocated capacity, so it is necessary to have specific assessments on the capacity of investors for projects. In case the projects are prolonged, it is necessary to do the procedures to terminate the investment policy or it will affect the development of the province and the investment environment.

HƯNG THƠ
RELATED NEWS

More wind power projects request to sell shares to foreign investors

|

Quang Tri - There are many wind power and solar power projects that have come into operation or are under construction, asking to sell shares to foreign investors.

Many hydropower and wind power projects in Quang Tri are behind schedule

|

Quang Tri - The specialized agency proposed that the People's Committee of Quang Tri province require wind and hydropower projects that are behind schedule to deposit funds to ensure investment.

Live football match Hoang Anh Gia Lai vs Hai Phong in round 20 of V.League

|

Live football match Hoang Anh Gia Lai vs Hai Phong in round 20 of V.League 2025-2026 at 5:00 PM today (April 24).

Discussing 14 contents, many of which are related to the 14th Vietnam Trade Union Congress

|

Hanoi - In the afternoon of April 24, the Executive Committee of the Vietnam General Confederation of Labour organized a Conference to discuss 14 contents, many of which are related to the 14th Vietnam Trade Union Congress.

People live in hardship beside the hundred-billion road project in Tuyen Quang

|

Tuyen Quang - Many households located within the Son Duong - Tan Trao road project area that have not been relocated are facing dusty weather and muddy rain.

Live football U17 Laos vs U17 Australia in the third-place match of the Southeast Asian Championship

|

Live football U17 Laos vs U17 Australia in the third-place match of the 2026 Southeast Asian U17 Championship at 3:30 PM today (April 24).

Stocks are heavily sold off, PC1's capitalization evaporates nearly 1,500 billion VND

|

Nearly 23 million PC1 shares were dumped on the floor in a context of no buyers, reflecting great selling pressure from investors.

More wind power projects request to sell shares to foreign investors

HƯNG THƠ |

Quang Tri - There are many wind power and solar power projects that have come into operation or are under construction, asking to sell shares to foreign investors.

Many hydropower and wind power projects in Quang Tri are behind schedule

HƯNG THƠ |

Quang Tri - The specialized agency proposed that the People's Committee of Quang Tri province require wind and hydropower projects that are behind schedule to deposit funds to ensure investment.

Dự án điện gió chưa có giấy phép môi trường sẽ bị xử phạt

HƯNG THƠ |

Quảng Trị - Tỉnh Quảng Trị đã nhiều lần yêu cầu các dự án điện gió lập hồ sơ đề nghị cấp giấy phép môi trường, nhưng một số dự án chưa thực hiện.