Reason for terminating contract of 1 contractor for 2,300 billion VND hospital project

ĐÌNH TRỌNG |

The 1,500-bed hospital project has been delayed, and Binh Duong province has decided to terminate the contract with one contractor.

Recently, explaining at the 16th Session of the 10th Provincial People's Council (July 24), Mr. Vo Van Minh - Chairman of the People's Committee of Binh Duong province said that the province has directed the Provincial Construction Investment Project Management Board to urgently handle the termination of the contract with the construction unit of the Central Technical Block project and the funeral home of the 1,500-bed Hospital project.

Regarding the above issue, the Binh Duong Province Construction Investment Project Management Board said that the Central Technical Block and Funeral Home Project was constructed by the Joint Venture of N.T Joint Stock Company and Vietnam Technical Trading Joint Stock Company. Up to now, the implementation volume has reached 32.2%.

Unfinished work accounts for 67.8%. The remaining volume is mainly equipment installation. The mechanical construction part has been completed 90%, but the progress of importing main equipment such as generators, electrical cabinets, electrical cables, fire fighting equipment... by the construction unit is very slow.

Du an benh vien cham tien do keo dai. Anh: Dinh Trong
Binh Duong decided to terminate the contract with 1 contractor. Photo: Dinh Trong

The Project Management Board urged the construction unit to speed up the progress, but the construction unit still implemented very slowly.

Some equipment imported to the project does not ensure sufficient quality records according to design document requirements.

The Board has reported to the Provincial People's Committee and has approved the termination of the contract with the contractor, N.T. Joint Stock Company. Currently, the Board has Notice No. 15/TB-QLDA dated June 20, 2024 on the termination of the contract with the contractor and is implementing the next steps to terminate the contract.

Du an benh vien keo dai nhieu nam van chua xong. Anh: Dinh Trong
The hospital project has been dragging on for many years and is still not finished. Photo: Dinh Trong

According to the reporter, over the past two years, the people and leaders of Binh Duong province have been very impatient with the progress of the 1,500-bed hospital project (Dinh Hoa ward, Thu Dau Mot city). This is a large provincial hospital project invested in to relocate the old, degraded Binh Duong General Hospital.

The project was initially estimated to have an investment capital of about 2,300 billion VND. The project allocated capital to start building the foundation in late 2014. However, the project then stopped construction for nearly 3 years. It was not until late 2018 that construction began again and was promised to be completed around June 2020. However, after many delays, many items are still unfinished and the items cannot be connected to each other.

ĐÌNH TRỌNG
RELATED NEWS

Gold price update closing session 4: SJC gold bars, gold rings simultaneously decrease

|

Gold price update at the closing session 4: Domestic gold simultaneously decreased by 3.2 to 4.2 million VND/tael.

Notice of conclusion on the content of supervision for the Standing Committee of Phu Tho Provincial Party Committee

|

On April 2, Inspection and Supervision Team No. 15 led by Comrade Bui Thi Minh Hoai - Member of the Politburo, Secretary of the Party Central Committee, Chairman of the Central Committee of the Vietnam Fatherland Front - announced the conclusions on the content of supervision (phase 1) and deployed the contents of inspection (phase 2) for the Standing Committee of Phu Tho Provincial Party Committee.

Ministry of Health announces list of food safety testing facilities

|

The Food Safety Department - Ministry of Health has just announced the latest list of 26 testing facilities serving state management of food safety.

Commending 10 outstanding young faces and 80 promising young faces of the entire army

|

On the afternoon of April 2nd, the Central Military Commission and the Ministry of National Defense organized a ceremony to commend outstanding young faces and promising young faces of the entire army in 2025.

Government stipulates principles for management and use of trade union funds

|

Decree No. 105/2026/ND-CP of the Government has stipulated the subjects of application, principles for management and use of trade union funds and the deadline for paying trade union fees.

Gold prices reverse sharply after Trump's speech

|

Gold prices turned down after Donald Trump's statement, which did not clarify the prospect of cooling down the conflict, causing the market to become cautious again.

Nearly 20 months without pay, teacher works as a construction worker, teacher returns to sell spring rolls and sausages

|

Phu Tho - Nearly 20 months without salary, dozens of teachers at Song Hong Technical - Professional Secondary School (old) do all kinds of jobs to make a living.

Rót thêm 120 tỉ đồng để cứu vãn bệnh viện bỏ hoang nhiều năm

NGUYỄN TRƯỜNG |

Sau nhiều năm bỏ hoang, tỉnh Ninh Bình quyết định rót thêm 120 tỉ đồng để cải tạo Bệnh viện Sản - Nhi (cũ) thành Bệnh viện y học Cổ truyền tỉnh Ninh Bình.

Triển khai 2 giải pháp gỡ khó Bệnh viện Ung bướu TP Cần Thơ

Phong Linh |

Sở Y tế TP Cần Thơ đang cố gắng triển khai song song 2 giải pháp để gỡ khó tình trạng quá tải tại Bệnh viện Ung bướu TP Cần Thơ.

Thay nhà thầu, điều chỉnh dự án bệnh viện 1.500 giường

ĐÌNH TRỌNG |

Dự án Bệnh viện 1.500 giường kéo dài thời gian thực hiện, tỉnh Bình Dương quyết định thay nhà thầu, điều chỉnh dự án thiết bị bệnh viện.