The reason the hundred billion industrial cluster in Thai Nguyen stagnates is prolonged

Nguyễn Hoàn |

The problems in compensation and site clearance have caused after nearly 6 years of implementation, the project of Ba Xuyen Industrial Cluster, Song Cong City, Thai Nguyen Province is sleazy, unfinished and sprawling.

Radious at the project of an industrial cluster hundred billion dong

Ba Xuyen Industrial Cluster project has a total investment of more than 431 billion dong. Founded under Decision No. 3406 -QD - People's Committee dated 7.11.2018 of Thai Nguyen People's Committee, assigned Minh Tuan Construction and Trading Investment Joint Stock Company as an investor.

Made on an area of ​​48.53ha in Ba Xuyen commune, Song Cong city (Thai Nguyen) with technical infrastructure items: internal roads, electricity and water systems, wastewater treatment plants Capacity of 5,000m3/day and night ...

According to the expected plan, Ba Xuyen Industrial Cluster will be completed in 2024. However, recorded by the reporter at the beginning of February 2025, although it has been nearly 6 years from the time of implementation To the finish line, sloppy and unfinished scenery.

Inside the industrial cluster is still an empty land, the technical infrastructure items have not been built. Around the material gathered, the weeds grow upward. Some areas have been digged, forming deep, unobtrusive water pits or placing a warning sign, potentially unsafe.

Mr. Nguyen Van Nhat (Song Cong City) shared that when Ba Xuyen Industrial Cluster began to deploy, the locals were very expected when they were completed, they would create many jobs in the locality and promote the economy. However, at present, the project is sleazy and disordered, causing many people to wonder whether the project will continue to implement or not and will never be completed.

The stagnation situation not only affects the local industrial development planning but also directly affects the lives of people in the project area. Many households want to repair and build houses but cannot be implemented due to planning.

Struggling to find a solution

Information from the People's Committee of Ba Xuyen Commune, one of the main reasons for Ba Xuyen industrial cluster that has not been completed is due to problems in compensation and site clearance. Many households with land in the area have been recovered to serve the project that has not agreed with the compensation plan. They that compensation is still low, not enough to buy land and stabilize their lives in a new place.

In addition, the unprocessed resettlement infrastructure is also the reason why many households are not ready to relocate. After more than 5 years of implementation, Ba Xuyen Industrial Cluster project has only released 30.96/48.53ha, reaching nearly 64%, there are still about 30 households who have not handed over the ground.

Another reason is because right from the early stages, investors have not drastically implemented, leading to difficulties and problems such as adjusting the detailed planning of the project, the time limit for the Prime Minister to allow the transfer. Purpose of using rice land has expired, the investor must apply for extension of the implementation time ...

Also according to information from the local authorities, investors are completing the documents to send to the competent authority to extend the project implementation to 2026.
improve production and create labor jobs.In order to implement effectively, in the coming time, it is necessary to remove problems soon in compensation and site clearance.At the same time, the investor needs to be proactive in resources, accelerate the progress to soon put the project into operation.

Nguyễn Hoàn
RELATED NEWS

Auction of industrial cluster land in Dong Nai worth more than 788 billion VND

|

Dong Nai - The land of Long Giao Industrial Cluster in Cam My district was auctioned for starting price of more than VND 788 billion.

Tuyen Quang has an additional 50ha industrial cluster

|

Tuyen Quang - Xuan Van Industrial Cluster in Yen Son district has a scale of 50 hectares and is implemented in 2 phases.

Hanoi Secretary sets deadline for site clearance for Ring Road 4 project

|

Hanoi - Secretary of the City Party Committee Nguyen Duy Ngoc requested that no later than December 31, 2025, the site must be handed over to the construction unit of the Ring Road 4 project.

Hour 9: Love gambling - Part 1

|

Hour 9 No. 178 - A successful couple but apart, both husband and wife have a "third person". How will they face this marriage tragedy?

Dak Lak bans ships from going out to sea before storm No. 15

|

Dak Lak - Chairman of the People's Committees of coastal communes and wards announced a ban on ships going out to sea and fishing activities at sea, before storm No. 15.

Tomorrow night, storm No. 15 Koto will encounter increased cold air, forecast for upcoming developments

|

Storm No. 15 is still likely to strengthen in the next 24 hours when moving in warm ocean waters.

The new land price list in Hanoi takes effect from January 1, 2026, highest at 702 million VND/m2

|

Hanoi officially applied the new land price list from January 1, 2026, an increase of 2-26% compared to the current land price list.

Two men risked their lives to save hundreds of people during the fierce flood night

|

Dak Lak - Amid the imminent danger, two men risked their lives by rowing a boat to save hundreds of people, becoming a life-and-death support for the whole village in the fierce flood.

Kiểm điểm vi phạm tại Cụm Công nghiệp Từ Liêm

Trang Khanh |

Hà Nội – Thanh tra TP Hà Nội vừa kiến nghị kiểm điểm về trách nhiệm tập thể, cá nhân những tồn tại, khuyết điểm tại Cụm Công nghiệp Từ Liêm.

Auction of industrial cluster land in Dong Nai worth more than 788 billion VND

HÀ ANH CHIẾN |

Dong Nai - The land of Long Giao Industrial Cluster in Cam My district was auctioned for starting price of more than VND 788 billion.

Tuyen Quang has an additional 50ha industrial cluster

Việt Bắc |

Tuyen Quang - Xuan Van Industrial Cluster in Yen Son district has a scale of 50 hectares and is implemented in 2 phases.