The reason the hundred billion industrial cluster in Thai Nguyen stagnates is prolonged

Nguyễn Hoàn |

The problems in compensation and site clearance have caused after nearly 6 years of implementation, the project of Ba Xuyen Industrial Cluster, Song Cong City, Thai Nguyen Province is sleazy, unfinished and sprawling.

Radious at the project of an industrial cluster hundred billion dong

Ba Xuyen Industrial Cluster project has a total investment of more than 431 billion dong. Founded under Decision No. 3406 -QD - People's Committee dated 7.11.2018 of Thai Nguyen People's Committee, assigned Minh Tuan Construction and Trading Investment Joint Stock Company as an investor.

Made on an area of ​​48.53ha in Ba Xuyen commune, Song Cong city (Thai Nguyen) with technical infrastructure items: internal roads, electricity and water systems, wastewater treatment plants Capacity of 5,000m3/day and night ...

According to the expected plan, Ba Xuyen Industrial Cluster will be completed in 2024. However, recorded by the reporter at the beginning of February 2025, although it has been nearly 6 years from the time of implementation To the finish line, sloppy and unfinished scenery.

Inside the industrial cluster is still an empty land, the technical infrastructure items have not been built. Around the material gathered, the weeds grow upward. Some areas have been digged, forming deep, unobtrusive water pits or placing a warning sign, potentially unsafe.

Mr. Nguyen Van Nhat (Song Cong City) shared that when Ba Xuyen Industrial Cluster began to deploy, the locals were very expected when they were completed, they would create many jobs in the locality and promote the economy. However, at present, the project is sleazy and disordered, causing many people to wonder whether the project will continue to implement or not and will never be completed.

The stagnation situation not only affects the local industrial development planning but also directly affects the lives of people in the project area. Many households want to repair and build houses but cannot be implemented due to planning.

Struggling to find a solution

Information from the People's Committee of Ba Xuyen Commune, one of the main reasons for Ba Xuyen industrial cluster that has not been completed is due to problems in compensation and site clearance. Many households with land in the area have been recovered to serve the project that has not agreed with the compensation plan. They that compensation is still low, not enough to buy land and stabilize their lives in a new place.

In addition, the unprocessed resettlement infrastructure is also the reason why many households are not ready to relocate. After more than 5 years of implementation, Ba Xuyen Industrial Cluster project has only released 30.96/48.53ha, reaching nearly 64%, there are still about 30 households who have not handed over the ground.

Another reason is because right from the early stages, investors have not drastically implemented, leading to difficulties and problems such as adjusting the detailed planning of the project, the time limit for the Prime Minister to allow the transfer. Purpose of using rice land has expired, the investor must apply for extension of the implementation time ...

Also according to information from the local authorities, investors are completing the documents to send to the competent authority to extend the project implementation to 2026.
improve production and create labor jobs.In order to implement effectively, in the coming time, it is necessary to remove problems soon in compensation and site clearance.At the same time, the investor needs to be proactive in resources, accelerate the progress to soon put the project into operation.

Nguyễn Hoàn
RELATED NEWS

Auction of industrial cluster land in Dong Nai worth more than 788 billion VND

|

Dong Nai - The land of Long Giao Industrial Cluster in Cam My district was auctioned for starting price of more than VND 788 billion.

Tuyen Quang has an additional 50ha industrial cluster

|

Tuyen Quang - Xuan Van Industrial Cluster in Yen Son district has a scale of 50 hectares and is implemented in 2 phases.

Thailand apologizes for the incident of not playing the national anthem in the match between U22 Vietnam and U22 Laos

|

A rare incident occurred in the opening match of the 33rd SEA Games men's football event between U22 Vietnam and U22 Laos when players of both teams had to "sing" the National Anthem.

Hanoi Police warn of the "diplomatic" scam of social housing spreading online

|

Hanoi - At the Social Housing Dialogue Conference, representatives of Hanoi City Police warned about the "diplomatic" trick of buying social housing

Truck overturned on Cu Hin Pass, causing prolonged traffic congestion

|

Khanh Hoa - The truck overturned accident at Cu Hin Pass caused a long traffic jam from Nha Trang to Cam Ranh airport.

Forecast of bad weather areas in the next 2 days due to tropical depression and cold air

|

The meteorological agency warns that the Dak Lak - Khanh Hoa sea area is affected by the tropical depression.

Establishment of Da Nang Free Trade Zone with seaports, airports and economic zones

|

The Government proposes a series of specific mechanisms and policies for the development of Da Nang, including the establishment of a Free Trade Zone with seaports, airports and economic zones.

Live football U22 Vietnam vs U22 Laos at SEA Games 33

|

Live match between U22 Vietnam and U22 Laos at SEA Games 33, taking place at 4:00 p.m. today (December 3).

Kiểm điểm vi phạm tại Cụm Công nghiệp Từ Liêm

Trang Khanh |

Hà Nội – Thanh tra TP Hà Nội vừa kiến nghị kiểm điểm về trách nhiệm tập thể, cá nhân những tồn tại, khuyết điểm tại Cụm Công nghiệp Từ Liêm.

Auction of industrial cluster land in Dong Nai worth more than 788 billion VND

HÀ ANH CHIẾN |

Dong Nai - The land of Long Giao Industrial Cluster in Cam My district was auctioned for starting price of more than VND 788 billion.

Tuyen Quang has an additional 50ha industrial cluster

Việt Bắc |

Tuyen Quang - Xuan Van Industrial Cluster in Yen Son district has a scale of 50 hectares and is implemented in 2 phases.