Starting construction of the most polluted canal in Ho Chi Minh City before April 30

MINH QUÂN |

HCMC - Go Vap and Binh Thanh districts are speeding up site clearance to start the first package of the Xuyen Tam canal renovation project before April 30, 2025.

On April 3, the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board ( urban Infrastructure Board) said that site clearance is taking place urgently to ensure the progress of the XL-03 package.

This is the section from Luong Ngoc Quyen Street to Vam Thuat River, passing through Go Vap District and Ward 13, Binh Thanh District.

In Go Vap district, 900 m out of a total of 1,300 m of the XL-03 package has been handed over (equivalent to 69.23%). Meanwhile, Binh Thanh District has handed over 1,140 m out of a total of 1,300 m (equivalent to 87.69%).

Currently, the remaining 200 m in each district are being urgently completed by localities for site clearance procedures, expected to be handed over to the investor at the end of April or early May 2025.

In parallel with site clearance, preparations for the groundbreaking ceremony are also being vigorously implemented to ensure the groundbreaking of the XL-03 package before April 30, 2025.

Rach Xuyen Tam duoc coi la rach o nhiem nhat TPHCM.  Anh: Anh Tu
Xuyen Tam Canal is considered the most polluted canal in Ho Chi Minh City. Photo: Anh Tu

After the XL-03 package was started, the next two packages in Binh Thanh District, including: XL-01 package - renovating the section from Nhieu Loc - Thi Nghe canal to Bui Dinh Tuy bridge; XL-02 package - renovating the section from Bui Dinh Tuy bridge to Luong Ngoc Quyen street, including branches of Binh Loi, Binh Trieu canals and Cau Son canals.

To be able to start construction of these two packages before September 2, 2025, the Ho Chi Minh City Urban Infrastructure Board believes that local authorities need the strong participation of the entire political system as well as the consensus of the people, especially households affected by the project.

The Xuyen Tam canal dredging, environmental improvement and infrastructure construction project was approved by the Ho Chi Minh City People's Council in October 2023, with a total initial capital of more than VND 9,664 billion. Of which, the cost of compensation, support and resettlement accounts for nearly VND6,400 billion.

By September 2024, the Ho Chi Minh City People's Council had adjusted the investment policy, raising the total capital to more than VND 17,200 billion (an increase of more than VND 7,500 billion). The additional funding is mainly for site clearance, with costs increasing from nearly VND6,400 billion to more than VND14,000 billion.

Du an cai tao rach Xuyen Tam can thu hoi dat hon 2.000 ho dan. Anh: Anh Tu
The Xuyen Tam canal renovation project needs to reclaim land from more than 2,000 households. Photo: Anh Tu

The total land area recovered by the project is 197,349 m2, affecting 2,215 households. In Go Vap district, the project reclaims land from 138 cases. Of which, 40 households were completely cleared, 98 households were partially cleared.

In Binh Thanh District, there are 2,077 cases of land acquisition, including 1,230 households and 23 organizations that have been completely cleared. The remaining 824 cases were partially cleared.

Rach Xuyen Tam hien nay. Anh: Minh Quan
Xuyen Tam Canal today. Photo: Minh Quan
Phoi canh rach Xuyen Tam sau khi cai tao. Anh: Ban Ha tang do thi TPHCM
Perspective of Xuyen Tam canal after renovation. Photo: Ho Chi Minh City Urban Infrastructure Board

Xuyen Tam Canal is nearly 9 km long, flowing through Binh Thanh and Go Vap districts, and is considered one of the most polluted canals in Ho Chi Minh City.

The project will dredge a canal bed 3.5 m deep, widening the canal bed by 20 - 30 m. The wastewater and rainwater collection system will be built synchronously.

A 6 m wide road will be built on both sides of the canal, with two lanes on each side, along with a 3-4 m wide sidewalk and a system of parks and trees.

The entire Xuyen Tam canal renovation project will be completed in 2028.

MINH QUÂN
RELATED NEWS

Project worth over 17,200 billion VND in Ho Chi Minh City needs to report to the National Assembly

|

HCMC - The Xuyen Tam canal renovation project increased its total investment from more than VND9,664 billion to more than VND17,200 billion, so it needs to be reported to the National Assembly according to regulations.

Evacuation of 1,270 households in Binh Thanh and Go Vap, where will they be resettled?

|

HCMC - 1,270 households completely cleared in Binh Thanh and Go Vap districts to renovate Xuyen Tam canal will be resettled in many different locations.

Binh Thanh reclaims 53.7 hectares of land, clears 1,230 households

|

HCMC - Binh Thanh District reclaimed 53.7 hectares of land, affecting 2,077 cases, including 1,230 households that were completely cleared to implement the Xuyen Tam canal renovation project.

After 2 suspensions, the vice principal of the suspected poisoning student case is about to return to work

|

Quang Tri - Kim Ngan Commune People's Committee is discussing a plan for the Vice Principal of Kim Thuy Primary School to return to work after the suspected food poisoning incident.

Musician talks about the reality of AI singing Trinh's music, composing million views

|

It is no coincidence that people still believe that artistic products are the spiritual children of artists, musician Minh Ca Ri shared when mentioning AI music.

Ho Chi Minh City Secretary warns of the risk of losing staff if 20,000 public real estates are not well managed

|

HCMC - After the merger, the city will manage about 20,000 public assets worth hundreds of billions of USD. If not managed well, there is a risk of violations, leading to the loss of staff.

Apartment fire on the 16th floor of an apartment building in Ho Chi Minh City

|

HCMC - A fire broke out in an apartment on the 16th floor of an apartment building in Phuoc Long Ward, fortunately there were no casualties.

Hundreds of thousands of Ukrainian refugees in the US have their food subsidies suspended

|

Washington has just issued a decision to remove Ukrainian refugees living in the US from the food subsidy program, part of Trump's budget cutting efforts.

Project worth over 17,200 billion VND in Ho Chi Minh City needs to report to the National Assembly

MINH QUÂN |

HCMC - The Xuyen Tam canal renovation project increased its total investment from more than VND9,664 billion to more than VND17,200 billion, so it needs to be reported to the National Assembly according to regulations.

Evacuation of 1,270 households in Binh Thanh and Go Vap, where will they be resettled?

MINH QUÂN |

HCMC - 1,270 households completely cleared in Binh Thanh and Go Vap districts to renovate Xuyen Tam canal will be resettled in many different locations.

Binh Thanh reclaims 53.7 hectares of land, clears 1,230 households

MINH QUÂN |

HCMC - Binh Thanh District reclaimed 53.7 hectares of land, affecting 2,077 cases, including 1,230 households that were completely cleared to implement the Xuyen Tam canal renovation project.