Close-up of the Hon Rom Golf Course project worth over VND500 billion, still in the shape of 13 years

Duy Tuấn |

Lam Dong - The Hon Rom Golf Course project has been 13 years behind schedule, and has just been pointed out by the Provincial Inspectorate for a series of shortcomings.

Du an San Golf Hon Rom tai phuong Mui Ne la mot trong cac du an gap vuong mac, cham tien do, ton dong keo dai, nguy co gay that thoat, lang phi ma Thanh tra tinh Lam Dong dua vao thanh tra chuyen de tu thang 8.
The Hon Rom Golf Course project in Mui Ne ward is one of the projects facing difficulties, delays, and long-standing backlogs, risking loss and waste, which the Lam Dong Provincial Inspectorate has conducted a thematic inspection since August.
Du an do Cong ty TNHH Phat trien S.I lam chu dau tu, duoc cap giay chung nhan dau tu tu nam 2007 voi quy mo gan 197ha, tong von hon 548 ti dong. Day la du an nam tren doi, ven khu vuc bien Hon Rom.
The project is invested by S.I Development Company Limited, granted an investment certificate since 2007 with a scale of nearly 197 hectares, with a total capital of more than 548 billion VND. This is a project located on a hill, along the Hon Rom sea area.
Tai con doc dan len du an, cac cac tam hang rao chan ngang loi vao. Ong Nguyen Thanh Tan - nguoi dan song tai khu vuc nay cho biet, cac tam hang rao tai loi vao du an duoc dung len da lau. Khong thay phuong tien thi cong ra vao, chi co bao ve ra vao thay ca moi ngay.
At the slope leading to the project, the fences blocked the entrance. Mr. Nguyen Thanh Tan - a resident of this area said that the fences at the project entrance have been erected for a long time. In the past, no construction vehicles were seen coming in or out, only security guards came in and out to take turns every day.
Theo con doc tham nhua dan len du an, ben trong la chot gac cua bao ve. Cac loi vao co thanh chan.
Following the asphalt slope leading to the project, inside is the guardhouse. There are barricades at all entrances.
Ben trong du an da tham nhua duong giao thong noi bo, xay dung nha lam viec, cong vien, ho boi, he thong cap, thoat nuoc, dien va trong cay xanh doc theo via he…
Inside the project, internal traffic roads have been paved, houses have been built, parks, swimming pools, water supply and drainage systems, electricity and trees have been planted along the sidewalk...
Close-up of the inside and outside of the project. Clip: Duy Tuan
Sau gan 1 thang Thanh tra tinh lam viec, hien da co ket luan va cong bo cong khai. Thanh tra tinh Lam Dong ket luan, den thoi diem thanh tra, du an da cham tien do hon 13 nam. Ve xay dung, Cong ty TNHH Phat trien S.I thi cong nhieu hang muc khi khong co giay phep.
After nearly 1 month of project inspection, Lam Dong Provincial Inspectorate has issued an inspection conclusion and publicly announced the results. According to the conclusion of Lam Dong Provincial Inspectorate, by the time of inspection, the project had been behind schedule for more than 13 years. Regarding construction, S.I Development Company Limited constructed many items without a license.
Doanh nghiep con no 17,5 ti dong tien thue dat, chua dap ung nghia vu theo luat. De thao go vuong mac, tao dieu kien cho cong ty Co phan Phat trien S.I va thu hut dau tu, Thanh tra tinh kien nghi UBND tinh xem xet de xuat Trung uong cho phep doanh nghiep tiep tuc thuc hien du an theo dung trinh tu, thu tuc phap luat.
The enterprise still owes 17.5 billion VND in land rent, has not fulfilled its legal obligations and some other shortcomings. To remove obstacles, create conditions for S.I Development Joint Stock Company and attract investment, the Provincial Inspectorate recommended that the Provincial People's Committee consider and propose to the Central Government to allow businesses to continue implementing the project in accordance with legal procedures and order.
Neu duoc chap thuan, cac so, nganh phai huong dan nha dau tu dieu chinh du an; ra soat, danh gia tinh kha thi cua du an, nguon luc cua nha dau tu; don doc doanh nghiep nop 17,5 ti dong tien thue dat. Nha dau tu duoc yeu cau nhanh chong hoan thanh nghia vu tai chinh, thuc hien dieu chinh phap ly va bao dam tien do khi tiep tuc trien khai.
If approved, departments and branches must guide investors to adjust the project; review and evaluate the feasibility of the project and investors' resources; urge businesses to pay VND 17.5 billion in land rent. Investors are required to quickly fulfill financial obligations, make legal adjustments and ensure progress when continuing implementation.
Duy Tuấn
RELATED NEWS

sentosa Villa project in Lam Dong is more than 11 years behind schedule, facing many violations

|

Lam Dong - The Provincial Inspectorate pointed out a series of problems related to land, construction and real estate business at sentosa Villa project.

Inspectorate points out a series of problems in the La Gi residential and commercial area encroachment project

|

Lam Dong - Many problems with land, planning and real estate business at the La Gi New Residential - Trade - Service Area Encroachment Project.

Government Inspectorate points out violations at Trang An and Bai Dinh projects

|

The inspection agency recommended reviewing the responsibilities of collectives and individuals related to shortcomings and violations in the Trang An and Bai Dinh projects (Ninh Binh province).

Current relationship and the truth about the arrest of Nhat Kim Anh

|

Since 2 days ago, the news of Nhat Kim Anh's arrest has caused a stir in public opinion. What is the singer's current life?

People aged 65 to under 75 need to contact the Ward People's Committee to complete procedures to issue health insurance cards

|

HCMC - People who are eligible but do not have a health insurance card or an expired health insurance card should contact the Ward People's Committee to complete the procedures for issuing a health insurance card.

People suffer because unfinished projects have turned into a pollution gap in the capital

|

The sewer renovation project in Long Bien (Hanoi) has been unfinished for more than ten years, people have to live next to a polluted black water hole.

The Golden Heart Social and Cultural Fund grants support to union members in flooded areas of Nghe An

|

Nghe An - The Golden Heart Social and Cultural Fund coordinated with the Provincial Federation of Labor to provide support to union members in difficult circumstances in the area.

Approving the election results of some personnel in Hanoi and Son La

|

The National Assembly Standing Committee has approved the election results of the Chairman of the Hanoi People's Council and the Chairman of the Son La Provincial People's Council for the 2021-2026 term.

sentosa Villa project in Lam Dong is more than 11 years behind schedule, facing many violations

Duy Tuấn |

Lam Dong - The Provincial Inspectorate pointed out a series of problems related to land, construction and real estate business at sentosa Villa project.

Inspectorate points out a series of problems in the La Gi residential and commercial area encroachment project

Duy Tuấn |

Lam Dong - Many problems with land, planning and real estate business at the La Gi New Residential - Trade - Service Area Encroachment Project.

Government Inspectorate points out violations at Trang An and Bai Dinh projects

TRÍ MINH |

The inspection agency recommended reviewing the responsibilities of collectives and individuals related to shortcomings and violations in the Trang An and Bai Dinh projects (Ninh Binh province).