Close-up of $1.4 billion gas-fired power plant ready for grid connection

HÀ ANH CHIẾN |

Dong Nai - Nhon Trach 3 and 4 power plants, the first in Vietnam to use liquefied natural gas (LNG), are ready to connect to the grid for the first time on February 5.

h2
On February 4, Lao Dong Newspaper reporters were present at the Nhon Trach 3 and 4 Power Plant project in Ong Keo Industrial Park, Nhon Trach District, Dong Nai Province to record the preparations for the first grid connection scheduled for February 5.
h2
Nhon Trach 3 and 4 Power Plant Project is the first power plant project in Vietnam using liquefied natural gas (LNG) with a total capacity of 1,500 - 1,600 MW, total investment of 1.4 billion USD. Putting both plants into commercial operation in 2025 will add about 9 billion kWh of electricity/year, contributing to ensuring national energy security, realizing the Net zero target and promoting the development of gas-fired power projects in Vietnam according to Power Plan VIII.
h3
According to the records, currently at the project, preparations for connecting to the grid have been completed. In the turbine house area, considered the "heart" of the project, there are always 2 security guards to ensure the operation is absolutely safe.
h4
Mr. Phan Minh Tam - Deputy Head of Safety Department, Power Project Board said that all items of the project are ready, just waiting for the "order" to connect to the national grid.
h5
Mr. Le Ba Quy - Director of the Power Project Management Board, Vietnam Oil and Gas Power Corporation - JSC said that this is a national key project using imported natural gas (LNG) and is the only project out of 13 LNG gas-electricity projects in the Power Plan VIII that is being implemented, so it is closely directed by the Government and ministries, especially the progress of this project.
h6
Regarding progress, up to now, the project has completed nearly 96% of the volume, many items of the factory have been tested and put into use such as: 220kV distribution yard system supplying electricity to the factory, main transformer system and self-used transformer of the factory, water treatment system, compressed air system, wastewater treatment system,...
h7
500 kV and 220 kV distribution yard areas are ready.
h8
On the afternoon of February 4, inside the project's Central Control Room, foreign experts and a team of Vietnamese officers and engineers were still diligently checking the techniques before the connection operation.
h9
To ensure the project's progress, Vietnam Oil and Gas Power Corporation - JSC said that during the 2025 Lunar New Year holiday, officers, engineers, and workers worked continuously at the construction site. Therefore, on January 29, 2025 (the first day of Tet), Nhon Trach 3 Power Plant completed the no-load operation test at 3,000 rpm and is ready to connect to the grid for the first time tomorrow (February 5).
h10
A team of engineers is checking the operation of the surveillance camera system at the project.
h11
Previously, on February 3, Mr. Vu Hong Van - Secretary of Dong Nai Provincial Party Committee and Mr. Vo Tan Duc - Chairman of Dong Nai Provincial People's Committee and the delegation of Dong Nai province wished a Happy New Year to the cadres, employees and workers at Nhon Trach 3 and Nhon Trach 4 Power Plant projects.
h12
According to Mr. Le Ba Quy, based on the current progress, Nhon Trach 3 Power Plant will be put into commercial operation in July 2025, and Nhon Trach 4 Power Plant will be put into commercial operation in October 2025.
HÀ ANH CHIẾN
TIN LIÊN QUAN

Bac Lieu seeks ways to overcome difficulties for LNG Power Plant project

|

Bac Lieu - Right in the first working week of the year of At Ty, the province organized a meeting with businesses to prepare for the investment promotion conference.

PV Power signed a credit of 521.5 million USD for Nhon Trach 3 and 4 Power Plant Project

|

On October 1, 2024, PV Power announced a credit contract of 521.5 million USD with Citi and ING, insured by KSURE and SERV, to finance the Nhon Trach 3 and 4 Power Plant Project.

News 20h: dangerous complications when children have flu

|

News 20h on 9.2: Doctors recommend how to protect children when flu flu out; Dead buffaloes for unknown reasons, cows died similarly in Quang Tri ...

Strengthening the recruitment, Ukraine faces the risk of division

|

Many people feel discontented by Ukrainian military activities to deal with manpower shortage.

Inspector of Ho Chi Minh City Banking University and the question of where hundreds of billions go

|

Inspectors determined that Ho Chi Minh City Banking University collected masters fees in contravention of regulations, financial management had errors.

A fine, minus the score of the passenger car driver overtaking on the highway

|

Justify the behavior of overtaking on Noi Bai - Lao Cai highway, the driver presented due to rushing to the wharf.

95 typical workers are members of the Communist Party of Vietnam

|

On behalf of the President of the VGCL, Standing Vice Chairman Thai Thu Xuong signed Decision No. 2718/QD-TLD on praising the typical workers as the first member of the Communist Party of Vietnam in 2025.

Update gold price closed session 9.2: loss up to 3.5 million/tael

|

Update gold price closed session 9.2: After a week of strong fluctuations, SJC gold bar buyers in the country lose up to 3.5 million VND/tael.

Bac Lieu seeks ways to overcome difficulties for LNG Power Plant project

NHẬT HỒ |

Bac Lieu - Right in the first working week of the year of At Ty, the province organized a meeting with businesses to prepare for the investment promotion conference.

PV Power signed a credit of 521.5 million USD for Nhon Trach 3 and 4 Power Plant Project

Gia Trang |

On October 1, 2024, PV Power announced a credit contract of 521.5 million USD with Citi and ING, insured by KSURE and SERV, to finance the Nhon Trach 3 and 4 Power Plant Project.

Cận cảnh nhà máy điện hơn 1 tỉ USD đang thi công ở Đồng Nai đạt tiến độ 85%

HÀ ANH CHIẾN |

Đồng Nai - Theo ghi nhận của phóng viên Báo Lao Động tại công trường thi công Nhà máy điện Nhơn Trạch 3 và 4 (xã Phước Khánh, huyện Nhơn Trạch), hàng nghìn cán bộ, kỹ sư, công nhân miệt mài thi công trong cả ngày lễ lẫn ngày thường. Đến nay, tổng tiến độ dự án đã đạt 85%. Đây là dự án nhiệt điện sử dụng nhiên liệu khí LNG đầu tiên tại Việt Nam, tổng mức đầu tư 1,4 tỉ USD.